PreviewProject mandate Pre-project The person or body that wants the project The leadership or board that decides whether to look into it further Someone asks for a project and a decision is needed on looking into it. Project Manager
Day in the Role Options analysis Weighted decision matrix
The need every option must meet Everyday health care within 15 minutes of home for 18,000 Riverside residents.
Criterion Weight A B C D Option Do nothing Renovate the old clinic (12 rooms) Convert the warehouse (24 rooms) Build new on a green site Fits the €4.5M budget 3 5 ×3 = 15 4 ×3 = 12 4 ×3 = 12 1 ×3 = 3 Time to open 2 5 ×2 = 10 4 ×2 = 8 3 ×2 = 6 1 ×2 = 2 Capacity for demand 3 1 ×3 = 3 2 ×3 = 6 5 ×3 = 15 5 ×3 = 15 Risk (5 = low risk) 2 2 ×2 = 4 4 ×2 = 8 3 ×2 = 6 3 ×2 = 6 Community access 1 1 ×1 = 1 3 ×1 = 3 4 ×1 = 4 4 ×1 = 4 Weighted total 33 37 43 30 Rank 3 2 1 4
Scoring key: 1 = poor · 2 = weak · 3 = acceptable · 4 = good · 5 = excellent. Weight: how much the criterion matters (1 to 3). Always keep “Do nothing” as option A.
Recommended option A B C D
Why The only option that fits the budget, meets demand and can open by next autumn.
What would change our choice If the warehouse survey shows major structural problems, re-score option C on cost and risk.
PreviewOptions analysis Pre-project The project manager or business analyst, with experts for each option The sponsor, as part of the business case There's more than one way to meet a need, including doing nothing. Project Manager
Day in the Role Cost-benefit analysis Cost-benefit analysis over time
Option assessed C. Convert the warehouse
Amounts in € thousands
Item Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Total
Costs Building conversion 3,100 3,100 Equipment 700 700 IT and booking system 200 200 Opening and hiring 200 200 Staff and running costs 1,900 1,900 1,900 1,900 1,900 9,500 Total costs 4,200 1,900 1,900 1,900 1,900 1,900 13,700
Benefits Regional health funding 1,600 1,600 1,600 1,600 1,600 8,000 Fewer minor emergency visits 900 900 900 900 900 4,500 Total benefits 0 2,500 2,500 2,500 2,500 2,500 12,500
Net (benefits − costs) -4,200 600 600 600 600 600 -1,200 Cumulative -4,200 -3,600 -3,000 -2,400 -1,800 -1,200
Payback About 7 years
When the cumulative line turns positive.
Benefits we can't price Travel time saved for residents Earlier diagnosis Less pressure on the emergency department
Assumptions Opening in month 7, benefits from Year 1 Funding per registered patient stays at today's rate Prices in today's euros
Sensitivity: what if? If this happens The result becomes Building costs +20% Payback about 8 years Benefits start 6 months late Payback about 7.5 years Funding −10% Payback about 9.5 years
PreviewCost-benefit analysis Pre-project The project manager with finance Finance and the sponsor, as part of the business case You need to show whether an option is worth its money over time. Process Improvement Specialist, Project Manager
Day in the Role Business case Business case report
Decision requested Approve €4.2M to convert the Riverside warehouse into a community health clinic, opening in 7 months.
Executive summary Residents of Riverside travel 40 minutes for basic care and wait 3 weeks for a GP. Converting the empty warehouse into a 24-room clinic is the only option that fits the budget, meets demand and opens by next autumn.
Investment €4.2M
Running cost €1.9M / year
Payback ≈ 7 years
Opening Month 7
1. Why we need this 40-minute journeys to the nearest clinic GP waiting time 3 weeks and rising Many minor cases at the emergency department
2. Options considered Option Outcome of the comparison Do nothing Not chosen: waiting times keep growing Renovate old clinic Not chosen: too small for demand Convert warehouse Recommended: right size, fits budget and time Build new Not chosen: €7.5M and 18 months
3. Benefits Benefit Today Target By when Owner Travel time to care 40 min Under 15 min Opening Atticus (Sponsor) GP waiting time 3 weeks Under 1 week Year 1 Amani (Clinical Lead) Minor emergency visits 100% −20% Year 1 Amani (Clinical Lead)
4. Main risks Risk Likelihood (L/M/H) Impact (L/M/H) Response Old building structure M H Structural survey before purchase Equipment lead times (14 weeks) H M Order in month 1 Not enough staff hired in time M H Start hiring in month 3
5. Approval Approved Approved with conditions Not approved
PreviewBusiness case Pre-project Usually written by the project manager or business analyst for the sponsor The sponsor and the body that funds the project Leaders must decide whether a project deserves funding. Project Manager
Day in the Role Feasibility study Can it be done? Under what conditions?
The idea A community health clinic in the empty Riverside warehouse, opening next autumn.
Feasibility by area Legal Feasible Conditions Not feasible
Health licence possible; planning permission for change of use needed
Technical Feasible Conditions Not feasible
Building can be converted if a structural survey confirms the roof and floors
Financial Feasible Conditions Not feasible
About €4M build, within the capital budget; running costs largely covered by regional funding
Practical Feasible Conditions Not feasible
Doctors and nurses can be hired regionally with a 3-month lead time
Overall Feasible Feasible with conditions Not feasible
Conditions:
Structural survey before purchase Planning permission for change of use
PreviewFeasibility study Pre-project The project manager or an analyst, with experts The sponsor or leadership team An idea needs checking before anyone spends money on a business case. Project Manager
Day in the Role Project charter Authorisation to start the project
This charter formally starts the project below and gives the project manager authority to use the resources described. It is signed by the sponsor.
Project Riverside Health Centre
Start date 1 April
Sponsor Atticus (Director of Community Health)
Project manager Annelise (Project Manager)
Objective Outcome Residents of Riverside get everyday care within 15 minutes of home
Measure GP waiting time under 1 week
By when Clinic open in month 7; target within 1 year of opening
In scope Building conversion Equipment Booking system Hiring and training Licence to open Out of scope Emergency care Hospital beds Pharmacy (possible later)
Key milestones Design approved Month 1
Building works done Month 5
Licence granted Month 6
Clinic opens Month 7
Budget, time and scope tolerances Approved Tolerance Budget €4.2M ± €25k without escalation Time Opening in month 7 ± 2 weeks within a stage Scope As above No change without approval
Authority of the project manager Detail May decide alone Spending up to €25,000; schedule changes within a stage Must escalate to the sponsor Anything larger, any change to the opening date or scope
Key stakeholders Name Role Involvement Atticus (Sponsor) Sponsor Decides, owns the budget Amani (Clinical Lead) Clinical lead Defines clinical needs, accepts the clinic Abigail (Finance) Finance Approves spending Azadeh (Community Council) Community council Voice of residents
Sponsor Atticus (Director of Community Health) Project manager Annelise (Project Manager)
PreviewProject charter Initiating Drafted by the project manager Signed by the sponsor A project is approved and needs an official start, an owner and limits. Project Manager
Day in the Role Stakeholder register Who matters, what they need, how we engage
Power and interest Influence ↑ Keep satisfied High influence · low interest Health authority inspector
Manage closely High influence · high interest Atticus (Sponsor) Amani (Clinical Lead) Abigail (Finance)
Monitor Low influence · low interest Warehouse neighbours
Keep informed Low influence · high interest Residents Azadeh (Community Council) Nurses' union
Interest → Key Engagement levels: write where each person is now and where you need them.
1 Unaware2 Resistant3 Neutral4 Supportive5 LeadingInterest and influence: H = high · M = medium · L = low. Keep this register factual: people may read it.
Register Name Role or group What they expect Interest Influence Now Needed How we engage How often Owner Atticus (Sponsor) Sponsor Clinic open on time, within €4.2M H H Supportive Leading Weekly one-page status, monthly board Weekly Annelise (Project Manager) Amani (Clinical Lead) Clinical lead Safe clinical design, enough staff H H Supportive Leading Design workshops, board member Weekly Annelise (Project Manager) Abigail (Finance) Finance Business Partner Spending stays within €4.2M and follows the rules H H Neutral Supportive Monthly budget review, early warning of any overspend Monthly Annelise (Project Manager) Health authority inspector Regulator Building meets licence rules L H Unaware Supportive Design review month 1, site visit month 4 At milestones Antonia (Compliance Lead) Azadeh (Community Council) Community council Residents told first, fair access H L Resistant Supportive Monthly update, named contact Monthly Aya (Project Coordinator) Residents Users of the clinic Care close to home, short waits H L Neutral Supportive Newsletter, open evening in month 6 Monthly Aya (Project Coordinator) Nurses' union Staff representatives Fair contracts, safe staffing levels H L Neutral Supportive Briefing before hiring starts, consulted on rotas At milestones Adaugo (HR Lead) Warehouse neighbours Local businesses Little noise and traffic during works L L Neutral Neutral Letter before works, contractor hotline At milestones Arash (Contractor)
PreviewStakeholder register Initiating The project manager, with the team Usually not formally approved You need one list of who matters, what they expect and how to engage them. Scrum Master, Product Owner, Process Improvement Specialist, Project Manager
Day in the Role RACI chart Who does what, who owns it
R Responsible: does the work
A Accountable: owns the result. Exactly one per row
C Consulted: asked before
I Informed: told after
Deliverable or decision Atticus (Sponsor) Annelise (Project Manager) Amani (Clinical Lead) Aine (IT Lead) Adaugo (HR Lead) Antonia (Compliance Lead) Alfonso (Software Vendor) Abigail (Finance) One A? Building design A R C C C I ✓ Building works I A I C C I ✓ Equipment purchase I A C C R ✓ Booking system setup I C A R ✓ Hiring and training I C A R I ✓ Licence application I C C R ✗ Opening date A R C I I C I I ✓ Spending above €25k A R C ✓
Write a person's name at the top of each column. Check that each row has one A, and that no column is overloaded with R's.
Gaps and follow-ups Licence application: Antonia (Compliance Lead) is responsible, but nobody is accountable yet. Atticus (Sponsor) to decide by Friday.
PreviewRACI chart Initiating The project manager, agreed with the people named in it The sponsor or project board, for the main lines Several people and suppliers share deliverables and ownership must be clear. Project Manager
Day in the Role RAID log Risks · Assumptions · Issues · Dependencies
Project Riverside Health Centre
Reviewed on Thursday 4 April
R
Risks Might happen. Write the cause, then the effect. Likelihood (L) and impact (I): H, M or L.
ID Risk (cause → effect) L I Owner Response Status R1 Equipment takes 14 weeks, so opening could slip H M Aya (Project Coordinator) Order early with a cancellation clause (approved) Open R2 Old structure needs more repair than expected, costs rise M H Annelise (Project Manager) €40k survey before works; contingency held by sponsor Open R3 Not enough nurses hired in time M H Adaugo (HR Lead) Start hiring in month 3, agency backup Open
A
Assumptions Treated as true without proof. Check each one by a date; if it fails, it becomes an issue.
ID Assumption Check by Status A1 Warehouse purchase completes in month 1 Kick-off Failed: see I1 A2 Regional funding per patient stays at today's rate Month 3 Open
I
Issues Happening now. Each needs an owner, an action and a due date.
ID Issue Priority Owner Action Due I1 Purchase completes in month 2, not month 1 High Annelise (Project Manager) Re-plan works, options to Atticus (Sponsor) Friday
D
Dependencies What we need from others, or others need from us.
ID Dependency From or to whom Needed by Status D1 Licence inspection needs the finished building Health authority Month 6 Planned D2 Network cabling before booking system install Building contractor Month 4 Open
PreviewRAID log Initiating The project manager Reviewed by the project board Risks, assumptions, issues and dependencies need one owned, visible list. Project Manager
Day in the Role Kick-off meeting pack Kick-off: agenda and minutes
Date Thursday 4 April
Time 10:00 to 12:00
Place Council building, room 2
Chair Annelise (Project Manager)
Notes by Aya (Project Coordinator)
Purpose of the meeting Start the Riverside Health Centre project together: one goal, clear roles, first actions.
Agenda 10:00 Why this project matters Led by Atticus (Sponsor)
10:15 Objective, scope and milestones Led by Annelise (Project Manager)
10:40 Who does what (RACI) Led by Annelise (Project Manager)
11:05 How we work and communicate Led by Aya (Project Coordinator)
11:25 Main risks and assumptions Led by Annelise (Project Manager)
11:45 Questions and next steps Led by All
Present Atticus (Sponsor) Amani (Clinical Lead) Abigail (Finance) Aine (IT Lead) Adaugo (HR Lead) Antonia (Compliance Lead) Alfonso (Software Vendor) Azadeh (Community Council) Aya (Project Coordinator) Annelise (Project Manager) Apologies Arash (contract not yet signed) Parking lot Hire doctors or nurses first? (Amani (Clinical Lead), Adaugo (HR Lead): resolved 13:30) Pharmacy as a later extension: Azadeh (Community Council) Decisions Weekly team meeting on Mondays at 09:00; project board monthly Senior doctors and lead nurses hired first, the rest from month 4 Purchase delay logged as issue I1 Actions Action Owner Due Done Re-plan building works for a month 2 purchase Annelise (Project Manager) Friday Book the inspector's design review Antonia (Compliance Lead) Next week First residents' update Aya (Project Coordinator) End of month Network requirements to the contractor Aine (IT Lead) Month 2
Next meeting Monday 8 April, 09:00
PreviewKick-off meeting pack Initiating The project manager Not approved Everyone involved is meeting for the first time. Project Manager
Day in the Role Delivery approach and tailoring Predictive, agile or hybrid, and the right amount of process
Approach per part Part of the work Requirements clear? Cost of late change Need for user feedback Approach Building works L M H L M H L M H Predictive Agile Hybrid
Booking system L M H L M H L M H Predictive Agile Hybrid
Hiring and training L M H L M H L M H Predictive Agile Hybrid
Licence L M H L M H L M H Predictive Agile Hybrid
Clear requirements and costly change point to predictive; a strong need for user feedback points to agile. Mixed parts make the project hybrid.
Tailoring the organisation's standards Standard document or control Kept, combined or dropped Why Risk register, issue log Combined One RAID log is enough for this size Benefits plan Kept Benefits continue after closure Software design document Dropped Vendor's own; the backlog serves us Weekly highlight report Kept Sponsor's preferred update
PreviewDelivery approach and tailoring Initiating The project manager The sponsor and the portfolio office You're deciding predictive, agile or hybrid, and how much process to use. Project Manager
Day in the Role Scope statement What is in, what is out, how it will be accepted
Project objective Residents of Riverside get everyday care within 15 minutes of home; GP waiting time under 1 week within a year of opening.
IN What we will deliverDeliverable Accepted when Converted building Building-control sign-off; joint inspection passed Clinical equipment Installed, tested and certified on site Booking system 50 test bookings succeed online and by phone 30 staff hired and trained All roles filled; training records complete Licence to operate Granted by the health authority Opening First patients seen; residents informed
OUT Not in this projectEmergency care Hospital beds Pharmacy (possible later) Café Dental care Constraints Budget €4.2M Opening in month 7 Health authority licence rules Assumptions Survey findings are complete Regional funding per patient unchanged
PreviewScope statement Planning The project manager, with the users and experts The sponsor Everyone must agree exactly what will and won't be delivered. Project Manager
Day in the Role Work breakdown structure The whole scope, broken into pieces
1 · Project Riverside Health Centre
1 Building
1.1 Design
1.2 Asbestos removal
1.3 Structural repairs
1.4 Fit-out
2 Equipment
2.1 Clinical equipment
2.2 Furniture
2.3 Installation
3 Booking system
3.1 Purchase
3.2 Setup
3.3 Integration
3.4 Testing
4 People
4.1 Hiring
4.2 Training
4.3 Rotas
5 Licence and opening
5.1 Licence
5.2 Mock clinic day
5.3 Opening event
6 Project management
6.1 Planning
6.2 Reporting
6.3 Closure
Rule of thumb: every box is a deliverable (a noun), the boxes under a parent add up to exactly the parent, and project management has its own branch.
WBS dictionary (key work packages) Code Description Accepted when Estimate 1.4 Fit-out: rooms, floors, ventilation to infection-control standard Building-control sign-off €1.4M · 8 weeks 3.2 Setup: appointment types, opening hours, staff rotas in the system 50 test bookings succeed €40k · 4 weeks
PreviewWork breakdown structure Planning The project manager, built with the team Part of the scope baseline, approved with the plan The whole scope must be broken into pieces you can plan and own. Project Manager
Day in the Role Project schedule Gantt chart · weeks 1 to 30
Activity Critical path (no slack)◆ Milestone Shade the weeks for each activity; mark critical bars darker.
ID Activity Dur. After Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 A1 Survey and design 7 wk A2 Purchase completes 1 wk A1 A3 Asbestos removal 3 wk A2 A4 Building works 14 wk A3 A5 Equipment order and delivery 14 wk A1 A6 Booking system setup 10 wk A2 A7 Hiring 12 wk A2 A8 Training 5 wk A6, A7 A9 Equipment installation 2 wk A4, A5 A10 Inspection 1 wk A9 A11 Licence 2 wk A10 A12 Opening – A8, A11 ◆
Critical path and slack Critical path: A1 → A2 → A3 → A4 → A9 → A10 → A11 → A12, no slack. Hiring (A7) and training (A8) have 5 weeks of slack.
PreviewProject schedule Planning The project manager The sponsor or board, as part of the plan You need to know when everything happens and what decides the end date. Process Improvement Specialist, Project Manager
Day in the Role Cost baseline Budget, reserves and spending profile
Amounts in € thousands
Approved on Tuesday, month 1
Cost per deliverable WBS Deliverable Estimate 1 Building 3,000 2 Equipment 650 3 Booking system 200 4 People 120 5 Licence and opening 30 6 Project management 50
Total work estimates 4,050
From estimates to funding Work estimates 4,050 Bottom-up, from the WBS
+ Contingency reserve 150 For identified risks · project manager
= Cost baseline 4,200 Approved yardstick for spending
+ Management reserve 300 For the unknown · sponsor approves use
= Total funding 4,500 What the funder sets aside
Spending over time 0 1,050 2,100 3,150 4,200 M1 M2 M3 M4 M5 M6 M7 Bars: planned spend per month. Line: cumulative spend (the S-curve).
Month M1 M2 M3 M4 M5 M6 M7 Planned 150 350 900 1,000 900 600 300 Cumulative 150 500 1,400 2,400 3,300 3,900 4,200
PreviewCost baseline Planning The project manager with finance The sponsor and finance The budget must be set, phased over time and tracked. Project Manager
Day in the Role Risk register Ranked risks and opportunities, with responses
Scoring scales Score Likelihood Impact (time or cost) 5 Over 70% Over 1 month late or over €150k 4 50 to 70% 2 to 4 weeks or €75k to €150k 3 30 to 50% 1 to 2 weeks or €25k to €75k 2 10 to 30% Under 1 week or under €25k 1 Under 10% Hardly noticeable
Agree your own scales with the team before scoring. Score = likelihood × impact.
Register ID Risk or opportunity L I Score Owner Strategy Response actions R1 Equipment takes 14 weeks; opening could slip 4 3 12 Aya (Project Coordinator) Reduce Order early with cancellation clause R2 Old structure needs more repair; costs rise 3 4 12 Annelise (Project Manager) Reduce Survey done; contingency €150k R3 Not enough nurses hired in time 3 4 12 Adaugo (HR Lead) Reduce Start hiring month 3; agency backup R4 Equipment prices rise 15% before ordering 4 3 12 Alder (Procurement) Transfer Fixed-price contract signed now R5 Licence refused over ventilation 2 5 10 Antonia (Compliance Lead) Reduce Inspector reviews design in month 2 R6 Opportunity: digital health grant pays €80k 3 2 6 Aine (IT Lead) Enhance Application by week 6
Strategies for threats: avoid · transfer · reduce · accept. For opportunities: exploit · enhance · share · accept.
PreviewRisk register Planning The project manager Reviewed by the project board Risks need scores, owners and responses in one place. Process Improvement Specialist, Project Manager
Day in the Role Statement of work Contract schedule: what the supplier delivers
Reference RHC-SOW-01
Supplier The building contractor (selected by tender)
This statement of work forms part of the contract between Day in the Role (the buyer) and the supplier named above.
1. BackgroundThe council is converting the Riverside warehouse into a community health clinic that must open in month 7.
2. Scope of workThe supplier will:
Remove asbestos from the roof and walls Repair the structure as listed in the survey Complete the fit-out to the approved design Not included:
Clinical equipment IT and network equipment (cabling is included) 3. Deliverables and datesDeliverable Due Site cleared of asbestos Week 11 Structure repaired Week 17 Fit-out complete Week 25 Handover documents Week 26
4. AcceptanceBuilding-control sign-off and a joint inspection with the council's compliance lead.
5. Contract type and price Fixed price Time and materials (with a cap) Cost-reimbursable plus fee
Price €3,000,000
6. Payment milestonesPayment due when Share of price On start 10% Site cleared, accepted 30% Structure repaired, accepted 30% Fit-out accepted 20% 6 months without defects 10%
7. ChangesChanges to scope, dates or price are agreed in writing by both parties before work on them starts.
PreviewStatement of work Planning The project manager with procurement Procurement and the sponsor A supplier must know exactly what to deliver, by when and how it's accepted. Project Manager
Day in the Role Communication plan Who needs what, how, and how often
Who hears what Audience What they need How How often From Atticus (Sponsor) Progress, risks, decisions needed One-page status by email Weekly, Friday Annelise (Project Manager) Project board Progress against baselines, exceptions Meeting and report Monthly Annelise (Project Manager) Project team Actions, blockers, next week Monday meeting Weekly Aya (Project Coordinator) Residents News, dates, how to register Newsletter and council website Monthly Aya (Project Coordinator) Health authority inspector Design and building progress Review meeting At milestones Antonia (Compliance Lead) Suppliers Dates, changes, acceptance Progress meeting Fortnightly Annelise (Project Manager)
The weekly rhythm Mon Team meeting
Tue Board (1st Tue)
Wed Supplier meeting (fortnightly)
Thu
Fri Status to Atticus (Sponsor) Residents' update (last Fri)
Write each regular meeting or report on its day. Note how often (weekly, fortnightly, monthly).
Escalation: how bad news travels Anything that threatens a milestone or a tolerance: same day to Annelise (Project Manager), within two days to Atticus (Sponsor) with options.
Channels With n people there are n × (n − 1) ÷ 2 possible channels.
People 12
Channels 66
PreviewCommunication plan Planning The project manager The sponsor Many people need different information at different times. Process Improvement Specialist, Project Manager
Day in the Role Project management plan The plan on a page
Scope baseline Scope statement v1.0 and WBS (6 deliverables)
Schedule baseline Opening in week 30 (month 7); critical path through the building works
Cost baseline €4.2M including €150k contingency; €300k reserve held by the sponsor
Management approach per area Area How we manage it Detail in Risk Weekly review; board monthly Risk register Quality Checks at each building phase; mock clinic day Scope statement Buying Fixed price for works; capped T&M for investigations Statement of work Communication Weekly status, monthly board and residents' update Communication plan Stakeholders Engagement plan per key person Stakeholder register Resources Time agreed with line managers RACI chart
Change control 1 Request logged
2 Impact assessed (scope, time, cost, risk)
3 Decided within tolerance or by the board
4 Plans and baselines updated
5 Everyone informed
Tolerances Annelise (Project Manager): up to €25k and 2 weeks per stage. Beyond that: the board.
PreviewProject management plan Planning The project manager The sponsor or project board All plans and baselines must be agreed as one reference. Project Manager
Day in the Role Project roadmap The whole project on one page
Initiating
Planning◆ Plan approved
Executing
Monitoring◆ Stage gate
Closing◆ Go or no-go
Building
Survey
Design approved
Works
Acceptance
Handover
Equipment
Ordered
Delivered
Installed
Booking system
Vendor chosen
Sprints 1–2
Sprints 3–6
Sprints 7–8
Online go-live
People
Hiring plan
Hiring
Training
Release team
Licence
Compliance register
Application
Inspection
Licence
◆ = decision point or stage gate. One lane per part of the project; the detail lives in the schedule.
PreviewProject roadmap Planning The project manager Shared with the sponsor and board Leaders need the whole project on one page. Project Manager
Day in the Role Requirements traceability matrix Every need, built and tested
ID Requirement Source Met by Tested by Designed Built Tested Accepted R04 Wheelchair access to every treatment room Clinical team Design rev C Walk-through ✓ ✓ ✓ ✓ R12 Hand-wash basin in every room Infection control Drawing M-03 Inspection IT-07 ✓ ✓ ✓ R19 Hearing loop at reception Accessibility rules Electrical package Test IT-15 ✓ R22 Baby-changing room Community council Layout rev D Inspection ✓ ✓ R31 Online and phone booking Residents Booking system User acceptance tests ✓ ✓ ✓
Every requirement needs a deliverable and a test. Empty “Met by” or “Tested by” cells are gaps to fix now.
PreviewRequirements traceability matrix Planning The project manager or analyst Reviewed with the senior user Every requirement must be built, tested and accepted, with nothing lost. Project Manager
Day in the Role Compliance register Every obligation, owned and evidenced
Obligation Rule or law What it requires Owner Evidence Due Status Health licence Clinic licensing rules Licence before opening Antonia (Compliance) Licence certificate Month 7 R A G Building regulations Building code Sign-off of the works Arash (Contractor) Building-control certificate Month 6 R A G Fire safety Fire safety law Certificate and evacuation plan Arash (Contractor) Fire certificate Month 6 R A G Data protection Data protection law Impact assessment, safeguards Aine (IT Lead) Signed assessment Month 3 R A G Accessibility Equality and accessibility law Accessible building and booking Aine and architect Test results Month 6 R A G Waste Environmental rules Licensed disposal, recycling Arash (Contractor) Waste records Ongoing R A G
Green: evidence in place · Amber: on track · Red: at risk. Obligations that cross teams need one clear owner.
PreviewCompliance register Planning The quality and compliance lead Reviewed by the project board Laws and regulations apply and none can be missed. Project Manager
Day in the Role Data protection impact assessment Privacy risks and safeguards, before the build
System or process Clinic booking system
Data protection officer The council's data protection officer
1. What personal data, and why Data Why it's needed Who sees it Kept for Name, phone, email To book and send reminders Reception Health records period Date of birth To identify the patient Reception, clinicians Health records period Short reason for visit To choose the right clinician Clinicians Health records period
2. Risks to the people concerned Risk Likelihood (L/M/H) Severity (L/M/H) Safeguard Unauthorised access to records L H Role-based access, access logging, staff training Collecting more than needed M M Short reason field only, no free-text history Data kept too long L M Automatic deletion after the legal period
3. Principles checked Only the data needed is collected People are told how their data is used Access is limited to those who need it Data is deleted when no longer needed
PreviewData protection impact assessment Planning The project manager or system owner, with the data protection officer The data protection officer A project will handle people's personal data. Project Manager
Day in the Role Resource plan Who's needed when, and how much
Load per month (% of their time on the project) Person M1 M2 M3 M4 M5 M6 M7 Antonia (Compliance Lead) 40% 50% 60% 80% 95% 70% 60% Aine (IT Lead) 50% 60% 80% 80% 90% 60% 40% Adaugo (HR Lead) 20% 40% 60% 60% 60% 40% 20% Aya (Coordinator) 80% 90% 90% 90% 90% 90% 80% Anwar (Facilities) 10% 30% 60% 70% 80% 90% 60%
Shade cells above 90% lightly and above 100% darker. Include holidays and other duties.
Peaks and how we fixed them Person When Load Fix Antonia Month 5 160% → 95% Two tasks with float moved; one inspection by the council team Aine Month 5 Holiday during testing Holiday moved to month 7 by agreement
PreviewResource plan Planning The project manager with the coordinator Line managers agree the time You need to check real people can do the plan, month by month. Project Manager
Day in the Role Training plan Who learns what, when, and how we know they're ready
Group (number) Booking system Infection control Fire safety Patient flow How readiness is checked Ready Reception (6) Wk 26 Wk 27 Wk 27 Five practice bookings each Nurses (12) Wk 26 Wk 25 Wk 27 Wk 27 Observed practice Doctors (6) Wk 26 Wk 25 Wk 27 Observed practice Healthcare assistants (4) Wk 25 Wk 27 Wk 27 Observed practice
Write the week each group takes each course. Ready = they have shown they can do it, not just attended.
PreviewTraining plan Planning The HR and training lead The senior user People must be able to do new work by a fixed date. Project Manager
Day in the Role Risk management plan How this project handles risk
Risk appetite by area Area Risk appetite What it means in practice Patient safety Low Moderate High
No avoidable risk to patients is accepted Legal compliance Low Moderate High
Every obligation met before opening Cost Low Moderate High
Within contingency; reserve with sponsor approval Schedule Low Moderate High
± 2 weeks per stage Opening-day extras Low Moderate High
Nice to have; can be dropped
Roles and review rhythm Risk owners update their risks weekly. The project manager reviews the register weekly; the board reviews the top 10 monthly.
Reserves Contingency €150k, used by the project manager for identified risks and logged. Management reserve €300k, used only with the sponsor's approval.
When we put numbers on risk Expected value for decisions over €25k; schedule simulation before each stage gate.
PreviewRisk management plan Planning The project manager The sponsor Everyone should handle risk the same way, with an agreed appetite. Project Manager
Day in the Role Request for proposal Invitation to submit a proposal
Reference RFP-RHC-03
Issued Week 6
Contact Alder (Procurement Officer)
Day in the Role invites suppliers to submit a proposal for the work described below. All bidders receive the same information.
1. About the projectThe council is converting the empty Riverside warehouse into a community health clinic that must open in month 7.
2. What we needAsbestos removal, structural repairs and full fit-out to the approved design, as described in statement of work RHC-SOW-01 (attached).
3. How proposals will be judgedCriterion Weight (%) Price 40 Experience with healthcare buildings 20 Method and safety plan 25 Timeline 15
Criteria and weights will not change after proposals are received.
4. TimelineStep Date RFP issued Week 6 Questions in writing by Week 7 Bids due Week 9 Decision Week 10 Works start Week 11
5. How to respondWritten bid, fixed price, maximum 20 pages Questions only in writing to the procurement contact; answers shared with all bidders Declare any link to council staff or the project team 6. Conflicts of interestBidders must declare any link to the buyer’s staff or project team. Undeclared links may exclude a bid.
PreviewRequest for proposal Planning Procurement with the project manager Procurement lead You invite suppliers to bid on clearly described work. Project Manager
Day in the Role Stage plan The detailed plan for the next stage
Stage Handover and opening
From Week 27
To Week 34
Stage objective Open the clinic safely in week 30, hand it over, close contracts and the project.
Deliverables and timing Deliverable Owner Wk 27 Wk 28 Wk 29 Wk 30 Wk 31 Wk 32 Wk 33 Wk 34 Licence granted Antonia Mock clinic day Amani Go or no-go Atticus Opening and hypercare All Contract closure Alder Lessons and closure report Annelise
Stage budget €180,000
Time tolerance ± 1 week
Cost tolerance ± €10,000
Main risks this stage Licence conditions not met in time Queues on day one Online booking go-live after opening
PreviewStage plan Planning The project manager The project board, at the stage gate The next stage needs a detailed plan for the board to approve. Project Manager
Day in the Role Work package Work order: one piece of work, handed over
Work package 4.1
Name Hiring
Handed to Adaugo (HR and Training Lead)
Handed over by Annelise (Project Manager)
What to deliver 3 doctors 6 nurses 2 healthcare assistants 1 reception lead Accepted when Contracts signed, checks complete, start dates agreed before week 23.
Start Week 11
Finish Week 22
Effort About 40 days of HR time
Tolerances Inside these limits the owner decides; beyond them, escalate before acting.
Constraints Offers sent within 48 hours of the final interview.
Reporting Short update every Monday; escalate at once if two weeks behind or a key role can't be filled.
✂ Closing stub Accepted on
Checked by
Closed
PreviewWork package Executing The project manager, agreed with the team lead or supplier Accepted by the team lead or supplier who takes it on A piece of work is handed to a team or supplier. Project Manager
Day in the Role Team charter Written by the team, for the team
Team Riverside clinical team
Our purpose Open a clinic where Riverside residents get safe, friendly everyday care close to home.
Our values Patients first Every decision starts with the patient
Speak up Anyone can stop work for safety
Help each other No one is left alone with a busy shift
Keep promises If we can't, we say so early
How we decide Clinical decisions: the senior doctor on shift. Rota changes: agreed on Mondays; Amani (Clinical Lead) decides if we can't agree.
How we communicate Monday team meeting. Urgent things by phone, not email. Replies within one working day.
When we disagree Talk to the person first, in private. Not solved in a week? Bring it to Amani (Clinical Lead).
We agree to this charter Amani (Clinical Lead)
Ayodele (Doctor)
Ambrose (Doctor)
Alina (Doctor)
Asha (Nurse)
Arjun (Nurse)
Aurelia (Nurse)
Ana (Nurse)
Aled (Healthcare Assistant)
PreviewTeam charter Executing The team, facilitated by its lead Agreed by the whole team A new or changed team needs shared rules for working together. Scrum Master, Product Owner, Process Improvement Specialist, Project Manager
Day in the Role Supplier performance review Scored on evidence, improved together
Supplier Building contractor
Contract RHC-SOW-01
Period Month 4
Scores Measure Score (circle one) Evidence Time 1 2 3 4 5 Two weeks behind (damp in north wall) Quality 1 2 3 4 5 Ventilation defect in rooms 4 to 6 Safety 1 2 3 4 5 No incidents; asbestos removal certified Communication 1 2 3 4 5 Cabling completion not shared Cost 1 2 3 4 5 One claim, settled at €20,000
1 = well below what was agreed · 3 = as agreed · 5 = well above. Every score needs evidence.
Average 3.4 of 5
What went well Excellent safety record Quick response to the asbestos condition Overall Performing well Improvement needed Formal warning
Improvements agreed Action Owner By when Recovery plan with weekly checkpoints Arash (Contractor) Friday Drawing revision log, confirmed by each trade Arash (Contractor) Next week Weekly coordination meeting attendance Arash (Contractor) Ongoing
PreviewSupplier performance review Executing The project manager with procurement Shared with and acknowledged by the supplier A supplier's performance needs a regular, evidence-based review. Project Manager
Day in the Role Quality inspection checklist Checked against the requirements
Deliverable Ventilation, treatment rooms 1 to 8
Location Riverside clinic, ground floor
Date Week 18
Inspector Antonia (Compliance Lead)
Checks Check Against (requirement) Pass Fail Notes Duct size matches design, rooms 1–3 Design drawing M-04 rev C ✓ Duct size matches design, rooms 4–6 Design drawing M-04 rev C ✓ Undersized: rev B used Duct size matches design, rooms 7–8 Design drawing M-04 rev C ✓ Air changes per hour At least 6 per hour ✓ Measured 7 Filters fitted and labelled Infection-control spec 3.2 ✓ Access panels for cleaning One per room ✓
Defects to fix Defect Owner Fix by Re-checked Replace ducts, rooms 4–6 Arash (Contractor) Week 19 Confirm all trades have drawing rev C Arash (Contractor) Week 18 ✓
Pass: accepted Pass with minor defects Fail: fix and re-inspect
PreviewQuality inspection checklist Executing The quality lead or inspector Signed by the inspector and the party responsible for fixes A deliverable must be inspected against its requirements. Project Manager
Day in the Role Project newsletter Community update
Day in the Role · Riverside Health Centre Clinic News
Issue 4 Month 4
The clinic is taking shape: walls up, first staff hired
What's happened Asbestos removal finished safely and on time. Builders are now fitting out the treatment rooms. Nine doctors and nurses have joined the team and are preparing for opening.
What it means for you Site deliveries only between 9:30 and 15:00, so local shops have their mornings back. Opening is planned for month 7.
Coming next Ventilation and electrics Booking system testing Open evening dates announced You asked Q Will appointments cost money?
A No. The clinic is a public service and appointments are free.
Q Can I register now?
A Registration opens in month 6. We'll tell you how in the next issue.
Questions? Contact Aya, Project Coordinator · Riverside clinic line · council website
PreviewProject newsletter Executing The project manager or communications lead The sponsor, for sensitive messages A wide audience needs regular, plain-language news. Project Manager
Day in the Role Lessons log What we learned, and what we changed
Write lessons when they happen, good and bad. Ask “why” about the process, not “who”. Apply them while the project is still running.
When Type What happened Why What we will do Applied? Week 9 Keep ImproveFit-out started in a certified area during asbestos removal Checked with compliance first Always check partial starts with the safety lead ✓ Week 14 Keep ImproveLead nurse lost to a slow offer Contract took 3 weeks Offers within 48 hours ✓ Week 18 Keep ImproveWrong ducts in three rooms Revised drawing never reached the subcontractor Drawing revision log confirmed by each trade ✓ Week 19 Keep ImproveDelivery window agreed with shop owners Listened before explaining Meet affected neighbours before works start ✓ Week 21 Keep ImproveIntegration knowledge held by one person No pairing on critical systems Pair on every critical system In progress
Top lessons to pass on to the next project Agree offer deadlines with HR before hiring starts Log and confirm every drawing revision No single person holds critical knowledge alone
PreviewLessons log Executing The project manager Reviewed by the board at stage ends Lessons should be captured while they're fresh and used straight away. Process Improvement Specialist, Project Manager
Day in the Role Sprint Review notes What we saw, what we said, what changes
Sprint goal Receptionists can book, move and cancel appointments by phone.
What was shown Shown Works for users? Feedback Book an appointment Yes Needs workFast and clear Move an appointment Yes Needs workWorks Cancel an appointment Yes Needs workWorks Book a follow-up Yes Needs workTakes six clicks; needs to be one
Who took part Amani (Clinical Lead), two receptionists, Annelise (Project Manager), Alfonso (Software Vendor), Ananya (Vendor Development Lead)
Changes to the backlog (decided by its owner) One-click follow-up moved to the top of the backlog SMS reminders moved earlier Reporting screens moved later
PreviewSprint Review notes Executing The supplier's Product Owner or the project coordinator Not approved An agile supplier shows work and the feedback must not be lost. Scrum Master, Product Owner, Project Manager
Day in the Role Incident report Safety incident: record, causes, actions
Incident People first. Make the area safe. Preserve evidence. Report as the law requires.
When Week 18, 10:05
Where East scaffold, level 2
Who A contractor's worker
Severity Injury, hospital treatment
What happened A worker fell about two metres from the east scaffold while moving materials. Injured arm; conscious throughout.
Immediate actions First aid given and ambulance called
Scaffold closed and scene kept unchanged
Reported to the authorities by the contractor
Sponsor informed
Causes (blameless investigation) A guard rail was removed for a delivery and not replaced. No step in the process checked guard rails before the scaffold was used again.
Corrective actions Action Owner By when Sign-off of every scaffold before reuse Arash (Contractor) Immediately Toolbox talk for all crews Arash (Contractor) This week Add to the lessons log Annelise (Project Manager) Today
PreviewIncident report Executing The contractor or employer, with the project manager Health and safety lead A safety incident happens on the project. Project Manager
Day in the Role Change readiness assessment Are people ready for the new way of working?
Group Understand why Can do the new tasks Have the tools Have support Action Reception R A G R A G R A G R A G Extra practice for two receptionists Transferring nurses R A G R A G R A G R A G Champions on every shift for four weeks Doctors R A G R A G R A G R A G Second set of logins before opening Facilities R A G R A G R A G R A G Briefing on the new patient flow
Check with the people themselves, by what they can do, not just what they attended.
PreviewChange readiness assessment Executing The change or training lead The senior user You need to know if people are ready for new ways of working. Project Manager
Day in the Role Meeting minutes and action log Decisions and actions, not a transcript
Meeting Site coordination
Date Thursday, week 12
Chair Annelise (Project Manager)
Notes by Aya (Project Coordinator)
Next meeting Thursday, week 13, 08:00
Present Arash (Contractor), Aine (IT Lead), Anwar (Facilities Coordinator), Antonia (Compliance Lead)
Apologies Alfonso (Software Vendor)
Items No. Item Discussion Decision 1 Previous actions All done except the network test date Aine to confirm by Friday 2 Cabling handover Finished last week; IT not told Three-week look-ahead shared every Monday 3 Deliveries Shops complain about morning lorries Delivery window 9:30 to 15:00
Actions Action Owner Due Done Share the three-week look-ahead Arash (Contractor) Every Monday Confirm network test date Aine (IT Lead) Friday Tell the shops about the delivery window Aya (Project Coordinator) Tomorrow
Send the same day. Confirm the actions at the start of the next meeting.
PreviewMeeting minutes and action log Executing The chair or project coordinator Confirmed at the start of the next meeting A meeting's decisions and actions must be recorded and followed up. Project Manager
Day in the Role Purchase order What we're buying, at what price, by when
Purchase order PO-1042
Date Week 4
Budget code RHC-02 Equipment
Deliver by Week 23
Supplier Medical equipment supplier (framework FW-17)
Deliver to Riverside warehouse, loading bay B
Item Quantity Unit price (€) Total (€) X-ray unit 1 180,000 180,000 Ultrasound scanner 2 45,000 90,000 Examination couch 12 2,500 30,000 Installation and testing 1 15,000 15,000 Order total 315,000
Terms Payment 30 days after accepted delivery Fixed prices under framework contract FW-17 Cancellation allowed without cost until week 14 Authorised by (within their budget authority) Atticus (Sponsor)
PreviewPurchase order Executing Procurement or the project coordinator Whoever holds the budget authority for the amount Goods or services are bought and the order must be formal. Project Manager
Day in the Role Status report Where we are against the baselines
Reporting period Month 4 (weeks 14 to 17)
Overall R A G
Why Two weeks behind on building works with a recovery plan; booking tests at 50%.
Status by area Area Status Why Scope R A G No unapproved changes Time R A G Building works 2 weeks behind; recovery plan agreed Cost R A G CPI 0.98; forecast inside baseline Quality R A G Ventilation defect fixed; booking tests at 50% pass Risk R A G Licence inspection not yet booked
Green: on plan. Amber: off plan, recoverable within tolerance, with a plan. Red: beyond tolerance or needs a decision.
Performance (€ thousands) PV Planned value 2,400
EV Earned value 2,200
AC Actual cost 2,250
SPI EV ÷ PV 0.92
CPI EV ÷ AC 0.98
SPI or CPI below 1 means behind schedule or over cost.
Done this period Asbestos removed and certified Structure repaired 9 clinical staff hired Next period Treatment room fit-out Booking system test cycle 2 Book licence inspection Top risks and issues Booking system tests failing (recovery plan Friday) Building works recovery Licence inspection backlog Decisions needed from you None this week. A possible exception on the booking system next week.
PreviewStatus report Monitoring The project manager Not approved Leaders need a regular, honest picture against the plan. Project Manager
Day in the Role Change request Request · impact · decision
Change no. CR-07
Raised by Amani (Clinical Lead)
Date Week 22
Type Scope
1. What change? Move two walls in the treatment area so a wheelchair and a trolley fit side by side.
2. Why? Safe access for wheelchair users; the current layout fails the clinical team's walk-through.
3. Impact (L = low, M = medium, H = high) Area Impact Detail Scope L M H Two walls and ventilation ducts moved Time L M H 1 week on the critical path, recoverable by overlapping two finishing tasks Cost L M H €18,000 from contingency Quality L M H Improves accessibility; ventilation re-inspection needed Risk L M H Small risk of rework in the overlap Other work L M H Equipment layout drawing updated
4. Options Option Cost Time Risk Do it now, overlap finishing tasks €18,000 0 weeks net Low Do it after opening €30,000 Clinic closed 1 week Medium Don't do it €0 None Access problem remains
5. Decision Approved Approved with conditions Rejected Deferred
Decided by Change board: Atticus (Sponsor), Amani (Clinical Lead), Arash (Contractor)
After approval: update the change log, plans, baselines and contracts, and tell everyone affected.
PreviewChange request Monitoring Raised by anyone The project manager within tolerance Someone wants to change scope, time, cost or quality. Project Manager
Day in the Role Change log Every change, and the contingency it used
No. Date Change Raised by Cost € Days Decision Decided by Contingency left € Opening contingency 150,000 CR-05 Week 17 Extra drying work, north wall damp Arash (Contractor) 20,000 0 Approved Annelise (Project Manager) 130,000 CR-07 Week 22 Move two walls in the treatment area Amani (Clinical Lead) 18,000 0 Approved Change board 112,000 CR-08 Week 24 Oak panelling in reception (unrequested) Arash (Contractor) 0 0 Rejected: replaced with specified surface Annelise (Project Manager) 112,000 CR-09 Week 24 One extra receptionist for Saturdays Azadeh (Community Council) 2,000 0 Approved Atticus (Sponsor) 110,000
Only approved changes reduce the balance. Record rejected and deferred changes too.
Starting contingency €150,000
Used so far €40,000
Remaining €110,000
PreviewChange log Monitoring The project manager Reviewed by the board You need the history of every change and the reserve it used. Project Manager
Day in the Role Exception report A tolerance will be exceeded: options for the board
Exception A forecast is beyond tolerance. The board must decide.
Reference EX-01
Date Week 23
Area Time (online booking)
What happened The council's patient records system needs a security upgrade before the booking system can connect. Integration will be three weeks late.
Tolerance and forecast Time (weeks) -2 +2
+3 weeks for online booking Cost (€ thousands) -25 +25
Within tolerance: about +€10k against the stage plan Shaded band: agreed tolerance. Marker: current forecast.
Impact Online booking not ready for opening in week 30. Online users' benefits start later. No effect on the building or licence.
Options Option Cost Time Risk A. Open with phone booking; online from week 4 after opening €0 On time Low B. Delay opening by 3 weeks €0 +3 weeks Public promise broken C. Pay for an extra vendor team €40,000 May still slip Medium
Recommendation A B C
Why Opens on time at no cost; phone booking was already planned as the back-up.
Board decision Approved option A
PreviewException report Monitoring The project manager The sponsor or board decide on the options A forecast goes beyond an agreed tolerance. Project Manager
Day in the Role Acceptance certificate Checked, accepted, handed over
Deliverable Converted building, Riverside clinic
Supplier Building contractor (RHC-SOW-01)
Date Week 26
Accepted with conditions
Checked against the agreed criteria Acceptance criterion Result Evidence Building-control sign-off Met Not metCertificate BC-2231 Ventilation to design (rev D) Met Not metRe-inspection, week 25 Wheelchair routes in all patient areas Met Not metWalk-through with Amani (Clinical Lead) Infection-control surfaces Met Not metAntonia (Compliance Lead)'s checklist Fire safety certificate Met Not metFire officer, week 26
Outstanding minor defects Defect Fix by Owner Room signs missing Week 27 Arash (Contractor) Two door closers too strong Week 27 Arash (Contractor) Paint touch-ups, corridor Week 28 Arash (Contractor)
Result Accepted Accepted with conditions Not accepted
Payment held back 10% held until all defects are closed
Accepted by (user side) Amani (Clinical Lead)
PreviewAcceptance certificate Monitoring The project manager prepares it Signed by the user representative A deliverable is handed over and must be signed off against criteria. Project Manager
Day in the Role End-stage report Stage gate: continue, with conditions, or stop
Pre-project
◆ Initiating
◆ Planning
◆ Executing
◆ Monitoring
◆ Closing
◆ = stage gate. Circle the gate this report is for.
Stage performance against baselines Area Baseline Actual or forecast Status Time Opening week 30 Week 30 (online booking +4 weeks) R A G Cost €4.2M €4.1M to €4.13M R A G Scope 6 deliverables 6, plus 3 approved changes R A G Quality Accepted to criteria Accepted with 6 minor defects R A G
Business case check Question Answer Still needed? Yes: waiting times keep rising Still affordable? Yes: about €4.2M, inside the approved funding Benefits still achievable? Yes: online booking benefits a month later Payback About 7.1 years (was 7)
Risks going forward Licence inspection (slot booked, week 28) Staff training complete in time Online booking go-live after opening Lessons from this stage Book every external inspection as early as possible Watch supplier backlogs as triggers The drawing revision log works Next stage Handover and opening: licence, mock clinic day, opening in week 30, contract closure and the benefits plan.
Board decision Go Go with conditions Stop
Conditions The licence result must be in before the opening event is announced.
PreviewEnd-stage report Monitoring The project manager The project board decides at the stage gate A stage ends and the board decides whether to continue. Project Manager
Day in the Role Decision log What we decided, and why
No. Date Decision Options considered Why Decided by D07 Week 9 Hybrid delivery: building predictive, booking agile One approach for all · per part Each part run the way that fits it Board D14 Week 23 Open with phone booking; online four weeks later Delay · extra vendor team · phone first On time, no extra cost Board D18 Week 31 Return €210k by postponing garden and screens Equal cuts · by priority Benefits protected Board D21 Week 33 Pharmacy as a follow-on project Add now · later Keeps opening safe Alessandro (Deputy Chief Executive)
Record the reason, not just the decision. It answers “why did we do that?” months later.
PreviewDecision log Monitoring The project manager or coordinator Reviewed by the board Important decisions need recording, with their reasons. Project Manager
Day in the Role Issue log Problems happening now, and who's on them
ID Issue Impact Priority Owner Action Due Status I07 Furniture supplier in administration Half the furniture missing; deposit at risk H M L Alder (Procurement) Claim under the bond; release finished chairs; order standard furniture Week 20 Open I08 East scaffold closed after incident Two days' delay in one area H M L Arash (Contractor) Investigation and sign-off rule Week 18 Closed I09 Online booking integration late Online booking after opening H M L Alfonso (Software Vendor) Phone booking fallback (board decision) Week 23 Managed
Issues are happening now. Risks (might happen) go in the risk register. Every issue needs an owner, an action and a date.
PreviewIssue log Monitoring The project manager Reviewed by the board Problems are happening now and need owners and actions. Project Manager
Day in the Role Quality audit report Are the project's processes working?
Scope Change control, risk management and document control, weeks 14 to 24
Auditor Adeline (Portfolio Manager)
Findings Finding Severity Evidence Approved changes not always reflected in plans (2 of 5) Major Minor Observation
CR-05 and CR-07 records Two risks without review dates Major Minor Observation
Risk register Issue log well used and up to date Major Minor Observation
Issue log
Corrective actions (fix the process, not just the instance) Action Owner By when Post-approval checklist for every change Annelise (Project Manager) This week Review dates for all risks Aya (Project Coordinator) Friday
Follow-up check Re-check in four weeks
PreviewQuality audit report Monitoring The auditor The sponsor Someone checks whether the project's processes actually work. Project Manager
Day in the Role Document and drawing register One register of current versions
Document or drawing Version Status Issued Changed because Confirmed by Floor plan v8 Approved Week 22 Walls moved (CR-07) All trades Floor plan v6 Withdrawn Week 14 Superseded Ventilation layout rev D Approved Week 22 Walls moved Contractor, ventilation Electrical layout rev F Approved Week 23 Sockets moved Electricians Booking system settings 1.4 Approved Week 25 One-click follow-up Vendor, IT
Status: draft · approved · withdrawn. Withdrawn versions are removed from site and shared folders.
PreviewDocument and drawing register Monitoring The project coordinator or document controller Changes approved through change control Drawings or documents change and people must use the latest version. Project Manager
Day in the Role Sponsor briefing Everything a new sponsor needs on one page
From (outgoing sponsor) Atticus (Director of Community Health)
→ To (new sponsor) Alessandro (Deputy Chief Executive)
Why the project exists Riverside residents travel 40 minutes for basic care and wait 3 weeks for a GP. The clinic brings everyday care within 15 minutes of home.
Where it stands Area Status Note Time R A G Opening week 30; online booking after opening Cost R A G Within the reduced budget after the €210k return Scope R A G Six deliverables, four approved changes Risk R A G Licence inspection booked for week 28
Key decisions so far Warehouse option (business case) Hybrid delivery Phone booking at opening €210k returned by postponing extras Promises made Opening in month 7 (the mayor) Monthly residents' updates (community council) What we need from you Confirm the tolerances Chair the next board Decide on the pharmacy idea
PreviewSponsor briefing Monitoring The project manager, with the outgoing sponsor Discussed with the new sponsor A new sponsor or senior leader takes over the project. Project Manager
Day in the Role Readiness checklist Ready to go live?
Go-live Monday, week 30
Readiness by area Area Status note Critical Ready? Fallback if not ready Building Accepted, defects listed R A G Licence Granted after two conditions closed R A G Staff 30 hired and trained R A G Phone booking Second line added after rehearsal R A G Online booking Integration 3 weeks late R A G Phone booking for the first 4 weeks Supplies and courier Courier moved to 15:30 R A G Communication Opening announced, newsletter sent R A G
Every critical item must be green, or have a fallback everyone accepts.
Rehearsal findings Finding Fix Owner Re-tested Phone queue too long at peak Second receptionist 08:00 to 11:00 Amani (Clinical Lead) ✓ Lab samples missed the courier Pick-up moved to 15:30 Aya (Project Coordinator) ✓
Decision Go Go with fallbacks No-go
PreviewReadiness checklist Closing The project manager with the operations lead The sponsor and the user side decide go or no-go Go-live is near and readiness must be checked on facts. Project Manager
Day in the Role Handover certificate From project to operations
What is handed over Riverside Health Centre: building, equipment, booking system and team
Date Opening day, week 30
From the project Annelise (Project Manager)
→ To operations Amani (Clinical Lead)
Transferred Building manuals and warranties
Equipment certificates
Booking system admin access and guide
Training records
Licence
Supplier contacts
Benefits management plan
Still open, with new owners Open item Owner By when Online booking go-live IT (Aine (IT Lead)'s successor) Week 4 after opening Paint touch-ups, corridor Arash (Contractor) Week 31
Support after handover Four weeks of joint support: project team on site Mondays and Thursdays, same-day response to issues. Ends in week 34.
From the date above, the operations owner is responsible for running the result and for the benefits plan.
PreviewHandover certificate Closing The project manager Signed by the operations owner and the project manager The result passes from the project to the people who'll run it. Project Manager
Day in the Role Benefits management plan Who checks the benefits, how and when
Benefits GP waiting time
Baseline 3 weeks
→ Target Under 1 week
Measured by Average wait for a routine appointment
Owner Amani (Clinical Lead)
Travel time to care
Baseline 40 minutes
→ Target Under 15 minutes
Measured by Travel time survey of residents
Owner Atticus (Sponsor)
Minor emergency visits
Baseline 100% (today's level)
→ Target −20%
Measured by Regional emergency department data
Owner Amani (Clinical Lead)
Review points Opening Baselines confirmed Abigail (Finance)
Month 6 All benefits Atticus (Sponsor)
Month 12 All benefits and the business case Council leadership
Risks to the benefits Appointment no-shows Staff turnover in the first year Slow take-up of online booking
PreviewBenefits management plan Closing Drafted by the project manager The sponsor Benefits will arrive after the project and need owners and measures. Project Manager
Day in the Role Contract closure checklist Every contract closed, on the agreed terms
Closure steps per contract Contract Accepted Claims settled Final payment Retention released Documents received Closure letter Building works (RHC-SOW-01) ✓ ✓ ✓ Month 6 ✓ ✓ Booking system ✓ ✓ ✓ — ✓ ✓
Tick each step, or write the agreed date if it comes later (for example a retention release).
Final accounts (€) Supplier Contract value Approved changes Final amount Building contractor 3,000,000 38,000 3,038,000 Booking system vendor 200,000 5,000 205,000
What we learned about buying Fixed price worked well for clearly defined works Check the buyer's own systems before signing integration contracts Supplier scorecards from month 1 kept reviews factual
PreviewContract closure checklist Closing Procurement with the project manager Procurement A supplier's work ends and the contract must be closed properly. Project Manager
Day in the Role Lessons report What the next project should know
Project Riverside Health Centre
Worked well: repeat Safety-first decisions on site Early engagement after the newspaper story Drawing revision log Phone booking fallback planned in advance Didn't work: avoid Slow job offers lost a key candidate The council's own security upgrade surprised everyone Inspection backlog spotted late Recommendations for future projects 1 Book external dependencies first
Why Purchases, inspections and system upgrades caused every major delay
For All projects with outside approvals 2 Set offer deadlines before hiring starts
Why A 3-week contract lost our best lead nurse
For Projects that hire 3 Pair people on critical systems
Why One resignation put integration at risk
For Projects with IT work 4 Agree status colour rules on day one
Why A green dashboard hid failing tests for weeks
For All projects
PreviewLessons report Closing The project manager, with the team and suppliers The board The project ends and the next one should learn from it. Project Manager
Day in the Role Project closure report The final account of the project
Objectives and results Objective Result Status Clinic open in month 7 Yes: opened week 30 R A G Care within 15 minutes for Riverside Yes: 12 minutes on average R A G GP waiting under 1 week within a year On the way: 1.5 weeks; reviewed at month 12 R A G
Baselines and actuals Cost (€M) Baseline 4.2
Actual 4.16
Time (weeks) Baseline 30
Actual 30
Scope 6 deliverables plus 4 approved changes; online booking 4 weeks after opening
Funds Approved funding € 4,500,000
Spent € 4,160,000
Returned € 340,000
Open items after closure Item Owner and date Online booking go-live IT, week 4 after opening Retention release Procurement, month 6 Benefits reviews Atticus (Sponsor), months 6 and 12
Board closure The board confirms the project is complete and formally closed. Records are archived.
PreviewProject closure report Closing The project manager The project board formally closes the project A project ends, or stops, and must be closed formally. Project Manager
Day in the Role Benefits review Is the investment paying off?
Review point Month 6 after opening
Progress from baseline to target GP waiting time (weeks)
3 1 1.5
Achieved On the way Not happening
Travel time to care (minutes)
40 15 12
Achieved On the way Not happening
Minor emergency visits (% change)
0 -20 -12
Achieved On the way Not happening
Left: baseline before the project. Right: target. Marker: today’s measurement.
Causes and actions Benefit Cause Action Owner GP waiting time 15% of appointments are no-shows Text reminders the day before Amani (Clinical Lead) Minor emergency visits Residents don't know about evening slots Awareness campaign Azadeh (Community Council)
Overall The project delivered what was approved, on time and under budget. Benefits are partly realised, with clear actions. Next review: month 12.
PreviewBenefits review Closing The benefit owners, coordinated by the sponsor The sponsor and leadership Months after go-live, you check whether the money achieved its purpose. Project Manager
Day in the Role Gemba walk notes Following one item through the process
Process Routine appointment with a blood test
Item followed One patient, with her permission
When Tuesday, 10:00
Observers Amara (Process Improvement Specialist), Ayumi (Healthcare Assistant)
Steps and waits Time Step or place Work time Wait before next step What we saw Kind of waste 10:00 Check-in at reception 4 min 22 min Queue of 6; screen shows no wait times Waiting 10:26 Consultation with the GP 9 min GP asks for a blood test 10:35 Back to reception to book the blood test 3 min 15 min Patient walks back past the waiting room Movement 10:53 Blood taken by Ayumi (Healthcare Assistant) 5 min 36 min Form waits for a GP signature Waiting 11:34 Form signed, patient leaves Patient asks when results will come Failure demand
Work time 21 min
Wait time 73 min
Total time 94 min
Questions to follow up Why does a blood test need a second trip to reception? Why does the form wait for a signature after the blood is taken? How do patients find out when results are back? Write what you see, not opinions. Look at the process, never at who is slow. Kinds of waste: waiting, extra processing, movement, transport, rework, overproduction, excess stock, unused talent, failure demand.
PreviewGemba walk notes Process improvement Whoever does the walk, usually the improvement specialist with someone who does the work Not approved You follow one item through a process and need to record what really happens. Process Improvement Specialist
Day in the Role Improvement opportunity log Every idea, sorted and followed up
Just do it Obvious, low-risk fix: do it now
Workshop Small problem, cause known: a short focused session
Project Important problem, cause unknown: a full improvement project
No. Idea or problem Where seen Kind of waste Route Impact (H/M/L) Owner Status 1 Supplies far from treatment rooms Gemba walk Movement Just do it M Ayumi (Healthcare Assistant) Done 4 Half of stock expires before use Supply room Excess stock Just do it L Ayumi (Healthcare Assistant) Done 7 Patients ring to ask about results Phones Failure demand Workshop H Alma (Reception Team Lead) Planned 9 Second trip to reception for blood tests Gemba walk Movement Workshop M Aurelie (Practice Nurse Manager) Planned 12 Routine appointment takes 10 days on average, up to 25 Data Waiting Project H Amara (Process Improvement Specialist) Chosen 15 Phone queue at 8 o'clock Phones Waiting Project H Alma (Reception Team Lead) Part of 12
Chosen project, and why Idea 12, appointment access: highest impact on patients and cost of poor quality, and directly linked to the month 12 target. Agreed with Atticus (Sponsor).
PreviewImprovement opportunity log Process improvement The improvement specialist The sponsor decides which ideas become projects Improvement ideas pile up and you need to sort, track and choose them. Process Improvement Specialist
Day in the Role Improvement charter Problem, goal, scope and team on one page
Project Routine appointment access
Sponsor Atticus (Director of Community Health)
Process owner Aurelie (Practice Nurse Manager)
Project leader Amara (Process Improvement Specialist)
Problem statement Over the last 20 weeks, patients asking for a routine GP appointment at the Riverside Health Centre waited a median of 10 days, and 1 in 4 waited more than 14. The target is under 7. About 1,900 appointments a year are missed, patients call repeatedly, and some go to the emergency department instead.
Goal Median wait of 5 working days or less, and 9 in 10 patients offered an appointment within 7 days, within five months. Measured weekly from booking data.
In scope Routine GP appointments From first request (phone, online or in person) to appointment offered All five GPs Out of scope Urgent same-day appointments (watched for side effects) Nurse appointments Home visits What customers need (critical to quality) Requirement Target Measured how Appointment within 7 days 90% Booking data, weekly Date offered on first contact 95% Reception tally, then booking data Median wait 5 working days Booking data, weekly
Team and roles Name Role Hours a week Atticus Sponsor 1 Aurelie Process owner 2 Amara Project leader (Green Belt) 20 Augustin Mentor (Black Belt) 1 Astrid Data Analyst 4 Alma Reception Team Lead 4 Ayumi Healthcare Assistant 3 Arjun GP 3
Plan: phases and reviews DefineWeek 2
MeasureWeek 6
AnalyseWeek 10
ImproveWeek 16
ControlWeek 20
Expected benefits About €35,000 a year: €22,785 of clinic savings from fewer missed appointments and repeat calls, and €12,480 of avoided emergency visits (method agreed with Abigail, Finance Business Partner). Better patient experience.
PreviewImprovement charter Process improvement The project leader, with the team The sponsor signs it An improvement project starts and everyone must agree its problem, goal and edges. Process Improvement Specialist
Day in the Role Phase review checklist End of phase: checks and decision
Phase Define Measure Analyse Improve Control
Project Routine appointment access
Date Week 2, Wednesday
Checks Question Yes or no Evidence Is the problem stated with data, and without causes or solutions? Yes Charter: median 10 days, 1 in 4 over 14 Is the goal measurable, with a date? Yes Median 5 days, 90% within 7, in five months Is the scope clear, with what's out? Yes Routine GP appointments only Do we know what customers need? Yes Survey, complaints, 14 conversations; three CTQs Are the team and their time agreed? Yes Signed by managers; about 4 hours each a week Are stakeholders mapped, with a plan? Yes Stakeholder register Are benefits estimated, with finance? Yes About €35,000 a year; method agreed Any risks to the project? Yes Winter demand peak during Improve
Help needed from the sponsor Protected time for the team Access to the booking system data A 30-minute check-in each month Decision Go on to the next phase Go on, with conditions Change course Stop the project
Go on to Measure. Online booking is kept as an idea to test in Improve if the analysis supports it.
PreviewPhase review checklist Process improvement The project leader prepares it The sponsor decides A phase of an improvement project ends and the sponsor must decide what next. Process Improvement Specialist
Day in the Role Data collection plan What we measure, exactly, and how much
Y = the result the customer feels. X = a possible cause. Write each definition so two people would get the same number.
Measure Y or X Operational definition Data type Source How many Who When Waiting time Y First request, by any route, to the date of the appointment offered; calendar days Continuous Booking system and call log 60 random, weeks 12 to 20 Astrid (Data Analyst) Week 3 Date on first contact Y Patient offered a date during their first request; yes or no Discrete (yes or no) Reception tally sheet Every request for 2 weeks Alma (Reception Team Lead) Weeks 3 and 4 Slot release time X Time each routine slot became bookable Continuous Booking system log All slots, 4 weeks Astrid (Data Analyst) Week 3 Urgent use of routine slots X Routine slot used for an urgent case, by the agreed guide Discrete (yes or no) Booking records All bookings, 4 weeks Astrid (Data Analyst) Week 4 Doctor sessions a week X Bookable routine sessions per week, all doctors Count Rota 20 weeks Aurelie (Practice Nurse Manager) Week 3 Missed appointments X Booked appointment not attended, no cancellation Discrete (yes or no) Booking system 20 weeks Astrid (Data Analyst) Week 3
Sampling: how records are chosen, and why that many Waiting time: 60 requests chosen at random from weeks 12 to 20 (at least 41 needed for ±2 days). Yes-or-no measures: every request, because each record holds less information.
How the data is checked Attribute agreement on urgent or routine before using that split. Gauge study on stopwatch call timing.
PreviewData collection plan Process improvement The project leader, with the data analyst Agreed with the process owner A team is about to collect data and must agree exactly what and how much. Process Improvement Specialist
Day in the Role Measurement system study Can we trust the data?
Measure Call length (minutes)
Method Stopwatch on recorded calls
People Alma, Anouk, Arturo
Items 10 calls
Repeats 2 each
Gauge study: measured values Result Value Guide Verdict Repeatability 11.9% Reproducibility 7.0% Total gauge 13.8% Under 10% good · 10 to 30% may be acceptable Acceptable Distinct groups 10 5 or more Good
Attribute agreement: categories Agreement Value Alma: agrees with self / with GP 95% / 90% Anouk: agrees with self / with GP 85% / 75% Arturo: agrees with self / with GP 90% / 80% All three with GP 65%, then 95% after the guide
Gauge share of total variation: under 10% good, 10 to 30% may be acceptable for the purpose, over 30% fix the method. Agreement: 90% or more good, under 80% act.
Decision Call times: use for capacity planning; add a start-and-stop rule. Urgent or routine: use only after the one-page guide and retest (95%).
PreviewMeasurement system study Process improvement The project leader or data analyst Reviewed at the Measure phase review You need to show that a measurement can be trusted before using its data. Process Improvement Specialist
Day in the Role FMEA worksheet How the process could fail, ranked by risk
Process Routine appointment booking
Team
Date
Step Failure mode Effect S Cause O Current control D RPN Action Phone request Can't get through at 8 am Told to call back; wait grows 7 All slots released at 8 am 8 None 3 168 Release slots ahead (Improve) Triage Urgent case booked into a routine slot Routine capacity lost 6 No clear rule 6 None 7 252 Urgent slots, daily count Booking Wrong appointment type Patient rebooked 4 Unclear list 3 Checked at check-in 5 60 Rota Rota released late Fewer slots to offer 7 Rota done on Fridays 4 None 6 168 Rota 4 weeks ahead Appointment Patient misses it Slot wasted 6 No reminder for phone bookings 7 Online reminders only 4 168 Reminders for everyone Appointment Session cancelled late Patients rebooked 8 Sickness 3 Phone calls to patients 2 48
S = severity, O = occurrence, D = detection, each 1 to 10 (D: 1 = always caught, 10 = never caught). RPN = risk priority number = S × O × D. Act on the highest RPNs, and on any S of 9 or 10.
PreviewFMEA worksheet Process improvement The project leader, with the people who do the work Reviewed by the process owner You need to list and rank how a process could fail. Process Improvement Specialist
Day in the Role Root cause verification Which causes are proven, and how
Result: proven (data shows it drives the result, with a clear mechanism) · likely (strong signs, not yet tested) · ruled out (data shows it doesn't).
Suspected cause How tested Evidence Result Only today's slots released, at 8 am 5 whys; booking data 38% of first requests told to call back; 2.1 days added Proven Two doctor sessions lost from week 12 Two-sample t-test; Mann-Whitney Weekly median wait +3.3 days; p below 0.0001 Proven Monday demand meets flat capacity ANOVA; Kruskal-Wallis; Mood's median; Friedman Monday 15.9 days against 6.4 to 10.2; worst every week Proven No reminders for phone bookings Two-proportion test; chi-square Missed 19.0% without against 8.1% with; missed rises with wait Proven (pilot to confirm) Urgent cases use routine slots FMEA Highest risk score (252); not yet measured Likely: measure in Improve Some doctors are slower Multi-vari Doctor averages within 1.3 days Ruled out
How the causes link Long waits lead to more missed appointments (6% to 29%), which waste slots and make waits longer.
PreviewRoot cause verification Process improvement The project leader Accepted at the Analyse phase review The causes of a problem must be shown to be proven before choosing solutions. Process Improvement Specialist
Day in the Role Pilot plan and results Plan, do, study, act
Plan, do, study, act. Write the prediction before the pilot starts.
Plan: what we're testing Book up to 2 weeks ahead, text reminders for every booking, protected urgent slots with a system lock, two extra Monday sessions moved from Thursday. Whole clinic, 4 weeks.
Prediction and results: same definitions as the baseline Measure Baseline Prediction Result Median wait (days) 10 5 or less 4 Within 7 days 45% 85% or more 88% Missed appointments 15.7% 10% or less 8.5% Thursday and Friday waits 7.1 to 9.0 days no worse no worse
Risks, and when we'd stop Thursday waits rise: checked weekly Patients forget bookings made far ahead: reminders System lock fails: daily urgent count Study: what we learned All measures improved significantly (two-proportion and Mann-Whitney tests, p below 0.0001). Adopt; add cover for the two lost sessions to reach 90%.
Act: decision Adopt Adapt and test again Drop
PreviewPilot plan and results Process improvement The project leader, with the process owner The sponsor approves the plan and accepts the results You test a change on a small scale before rolling it out. Process Improvement Specialist
Day in the Role Implementation plan From pilot to normal work
Tasks Task Owner By when Done Booking up to 2 weeks ahead for all staff Alma (Reception Team Lead) Week 1 ✓ System lock on urgent slots Astrid (Data Analyst) Week 1 ✓ Monday sessions in the rota Aurelie (Practice Nurse Manager) Week 2 ✓ Reminders for every booking Astrid (Data Analyst) Week 1 ✓ Recruit cover for 2 sessions Aurelie and Atticus Week 4 Weekly results to the team Amara (Process Improvement Specialist) Weekly
Training and communication Audience Message or skill How When Receptionists New booking script 1-hour training Week 1 Doctors Pilot results, what changes Team meeting, pilot doctors speak Week 1 Patients Book ahead, reminders Posters, website, text Week 1 Council Results so far Atticus's report Week 4
Risks Cover not found in time Thursday waits grow Old habits return How we'll know it worked 90% offered an appointment within 7 days and median 5 days or less, measured weekly from week 2.
PreviewImplementation plan Process improvement The project leader, with the process owner The sponsor A proven change has to become the normal way of working everywhere. Process Improvement Specialist
Day in the Role Control plan Keeping the gains
Process Routine appointment booking
Process owner Aurelie (Practice Nurse Manager)
Review date
Measures Measure Definition and sample How often Owner Limits or target Chart Waiting time First request to appointment offered, calendar days; 5 random requests a day Daily Astrid (Data Analyst) Xbar 1.85 to 6.86; R up to 9.41 Xbar-R Daily average wait All routine requests booked that day Daily Astrid (Data Analyst) 2.76 to 5.56; CUSUM h = 2.2 I-MR and CUSUM Not offered within 7 days Share of the day's requests Daily Alma (Reception Team Lead) Upper limit by day (about 0.21) P chart Missed appointments Out of 50 checked a day Daily for 3 months, then weekly Alma (Reception Team Lead) Up to 9.8 of 50 NP chart Booking errors Errors per booking Daily Alma (Reception Team Lead) Upper limit by day (about 0.12) U chart 8 am answer time 12 calls, minutes Monthly Alma (Reception Team Lead) 1.38 to 3.39 Xbar-S
Response plan Signal First action Who acts Who to tell Doctor off at short notice Book cover from the list Aurelie (Practice Nurse Manager) Doctors' team Booking system down Paper booking sheets; enter later Alma (Reception Team Lead) IT, Aurelie CUSUM or EWMA signal Check locum sessions and the rota Aurelie (Practice Nurse Manager) Atticus (Sponsor) if not fixed in a week Point outside any limit Find the cause the same day; record it Measure owner Aurelie
Lean controls Weekly 5-minute 5S check of the booking desk, against the photo standard Monthly test of the urgent-slot lock Two-bin kanban for the 12 most-used supplies; cards checked weekly Signals: a point outside a limit, 8 in a row on one side of the centre line, 6 in a row rising or falling. Record every signal, its cause and the action.
PreviewControl plan Process improvement Written by the project leader The process owner signs it An improved process is handed to its owner and must stay on track. Process Improvement Specialist
Day in the Role Improvement storyboard The whole project on one page
Project Routine appointment access at the Riverside Health Centre
Team Amara (lead), Astrid, Alma, Ayumi, Arjun · sponsor Atticus · owner Aurelie · mentor Augustin
Define Patients waited a median of 10 days for a routine appointment; 1 in 4 over 14. Goal: median 5 days or less, 90% within 7 days, in five months.
Measure Swimlane map and value stream (19 minutes of work in 10.4 days). Measurement checked: attribute agreement 95%, gauge 13.8%. Baseline: 55% over 7 days, sigma level 1.4.
Analyse Proven: same-day slot release (call-back loop), two lost doctor sessions since week 12 (+3.3 days), Monday demand on flat capacity, no reminders for phone bookings (missed 19% against 8%). Urgent use of routine slots confirmed by regression.
Improve Book up to 2 weeks ahead, reminders for every booking, protected urgent slots with a system lock, two extra Monday sessions, cover for lost sessions. Pilot: median 4 days, 88% within 7, missed 8.5%.
Control Control plan with six charted measures and a response plan, owned by Aurelie. After roll-out: 91% within 7 days, median 4. Benefits €36,705 a year, confirmed by finance; payback about 9 months.
Before and after Measure Before Median wait 10 days Within 7 days 45% Missed 15.7% Sigma level 1.4
Measure After Median wait 4 days Within 7 days 91% Missed 8.3% Sigma level about 2.8
Lessons Check the measurement before trusting the data Front-line staff found most of the causes Small drifts need CUSUM or EWMA, not just standard charts Next steps Next project from the opportunity log: telling patients when their test results are back.
PreviewImprovement storyboard Process improvement The project leader The sponsor, at the closing review An improvement project closes and its story must be told on one page. Process Improvement Specialist
Day in the Role Capability study report How well the process meets its requirement
Process Routine appointment booking
Requirement Upper limit 7 days
Data and period Waits, weeks 12 to 20 (stable period)
Sample size 60 random requests
1. Stability first Run chart of 20 weeks: a shift at week 12 (9 points above the median). Weeks 12 to 20 are stable and used.
2. Shape of the data Statistic Value Mean 10.43 days Median 10 days Standard deviation 6.46 days Range 3 to 28 days Shape Skewed right Normality test p about 0.0001: not normal
3. Capability Measure Value How calculated Observed over the limit 55% 33 of 60 Per million 550,000 0.55 × 1,000,000 Ppk (upper) −0.18 (7 − 10.43) ÷ (3 × 6.46) Sigma level about 1.4 NORM.S.INV(0.45) + 1.5 Log scale (Box-Cox λ ≈ 0) 63% predicted checked against 55% observed
Report the observed share outside the limits first. Use Cp, Cpk, Pp and Ppk only when the data is roughly normal, or after a checked transformation.
4. What it means The process can't meet the requirement: more than half of patients wait too long. Because the data is skewed, the observed share is the headline figure.
PreviewCapability study report Process improvement The project leader, with the data analyst Reviewed at the Measure phase review You need to fix and record how well a process meets its requirement. Process Improvement Specialist
Day in the Role Analysis record Every test, planned and recorded
Choose the test before looking at the result. Record every test, including those that found nothing. Give the size of the difference, not just the p-value.
Practical question Hypotheses Data Test and why Checks Result Decision Is the mean wait above 7 days? H0: mean = 7 · H1: mean > 7 60 waits One-sample t (n = 60, averages near normal) Skew noted; Wilcoxon run as a check t = 4.11, p = 0.00006 Gap to target is real Did waits change at week 12? H0: no difference 20 weekly medians Two-sample t; Mann-Whitney F-test p = 0.10 (similar spreads) +3.3 days; p below 0.0001 Root cause: lost sessions Do waits differ by weekday? H0: all days equal 60 waits by day ANOVA; Kruskal-Wallis; Mood's median Levene p = 0.07; data skewed F = 7.39; H = 19.66; all p below 0.001 Root cause: Monday demand Is Monday worst every week? H0: no day effect within weeks 9 weeks × 5 days Friedman (blocks = weeks) Every cell filled 22.85, p = 0.0001 Consistent effect Do reminders matter? H0: same missed share 1,400 appointments Two-proportion test Expected counts large 8.1% against 19.0%, z = 5.13 Likely cause; pilot to confirm Missed by days booked ahead? H0: independent 4 × 2 table Chi-square All expected counts above 5 74.6, p below 0.0001 Vicious circle confirmed
PreviewAnalysis record Process improvement The project leader or data analyst Reviewed at the Analyse and Improve phase reviews Statistical tests must be planned, checked and recorded honestly. Process Improvement Specialist
Day in the Role Benefits sign-off Benefits measured and confirmed
Benefit lines Benefit Method agreed in Define Before After Value a year Missed appointments 12,700 × change in missed share × €15 15.7% 8.3% €14,100 Repeat calls Calls × €1.20 11,250 2,813 €10,125 Emergency visits (avoided cost) Visits × €120 208 104 €12,480
Costs Cost One-off A year Team time €14,000 €0 System changes €3,000 €0 Training €1,500 €0 Cover sessions €0 within existing budget
Result €36,705 a year (€24,225 clinic savings, €12,480 avoided health-system cost). One-off cost €18,500; payback about 9 months on the clinic's own savings. Check again at 12 months.
Measure each line with the method agreed in Define. Show cash savings and avoided costs separately. Include the running costs of the new process.
PreviewBenefits sign-off Process improvement The project leader prepares it Finance signs it An improvement's benefits must be measured and confirmed by finance. Process Improvement Specialist
Day in the Role Product vision and Product Goal One direction for everyone
Vision Fresh groceries at your door in 30 minutes, ordered in three taps.
For whom, and their problem Busy households who run out of basics and have no time to shop.
Product Goal: the next measurable step Shoppers can buy their groceries online and pay by card.
How we'll know (outcomes, not features) Repeat orders Average delivery time Customer satisfaction Revenue Not doing Restaurant meals A marketplace for other shops Test every request against the vision: does it move us towards the Product Goal?
PreviewProduct vision and Product Goal Scrum and product The Product Owner, with the team and stakeholders The Product Owner is accountable for the Product Goal A product needs one clear direction and a filter for requests. Product Owner, Scrum Master
Day in the Role Product Backlog Everything that might be done, in order of value
Product Goal Shoppers can buy their groceries online and pay by card.
Order Item Value (H/M/L) Size Ready? Notes 1 Login (email and password) H 5 Yes 2 Browse products H 3 Yes 3 Add to cart H 3 Yes 4 Checkout H 8 Yes 5 Card payment, one provider H 8 Not yet Split from “payment” 6 Delivery slots M 5 Not yet 40% drop-off without it 7 Order tracking M 8 No Needs a map licence 8 Ratings L 3 No 9 Promo codes L 5 No After shoppers can buy
Not now, and why Summer banner: marketing, not product Restaurant meals: outside the vision One ordered list per product. The top items are small, clear and ready; lower items can stay rough.
PreviewProduct Backlog Scrum and product The Product Owner is accountable Ordered by the Product Owner All the work on a product must be in one ordered list. Product Owner, Scrum Master
Day in the Role Sprint Backlog This Sprint's goal, items and plan
Sprint Sprint 1 (one week)
Sprint Goal Shoppers can log in, browse and add to the cart.
Selected items Item Acceptance criteria met? Status Login (email and password) Yes Done Browse products Yes Done Add to cart Yes Done
The Developers' plan In progress Cart tests on real phones Done Login screen Product list Cart service The Developers own this plan and update it every day. Scope can be clarified with the Product Owner; the Sprint Goal stays.
PreviewSprint Backlog Scrum and product The Developers The Developers own it The team plans a Sprint and tracks its progress daily. Product Owner, Scrum Master
Day in the Role Definition of Done Our shared quality standard
An item is done when ✓ Meets its acceptance criteria
✓ Code reviewed by another Developer
✓ Tested on real phones (iPhone and Android)
✓ No known bugs
✓ Documented for customer support
How we check it Ava (Developer) checks testing; another Developer reviews the code before an item moves to done. Nothing undone is released.
Next improvements to the definition Automated tests for payments Performance check on older phones Work that doesn't meet the Definition of Done isn't shown at the Sprint Review and isn't released. It goes back to the Product Backlog.
PreviewDefinition of Done Scrum and product The Scrum Team Agreed by the Scrum Team Everyone must share the same meaning of “done”. Product Owner, Scrum Master
Day in the Role Retrospective actions What we learned, and what we'll change
What went well Clear Sprint Goal Pairing on payments What to improve Testing on phones came late Acceptance criteria were vague Actions: few, small, with an owner Action Owner By when Worked? (checked next Retrospective) Test on real phones every day Ava (Developer) Sprint 3 Yes Acceptance criteria written before refinement Anna (Product Owner) Sprint 3 Yes
PreviewRetrospective actions Scrum and product The Scrum Team Agreed by the Scrum Team Retrospective ideas must turn into real improvements. Product Owner, Scrum Master
Day in the Role Impediment log What blocks the team, and who's removing it
Raised Impediment Impact Owner Action Resolved Day 2 No API keys for login Login blocked Aaron (Scrum Master) Chased IT with the impact Day 3 Day 8 No phone testing tool Cart can't be tested Aaron (Scrum Master) Free trial, then a licence Day 10 Week 6 Map service licence for tracking Tracking blocked Adam (CEO) Licence approved: value outweighs cost Week 7
Patterns worth fixing at the root Access and licences: a fast route agreed with IT and the sponsor An impediment is anything the team can't solve by itself that slows progress. Record when it was raised: waiting time is the cost.
PreviewImpediment log Scrum and product The Scrum Master Not approved Blockers need to be visible and removed quickly. Product Owner, Scrum Master
Day in the Role Release plan and forecast What's in the release, and when it's likely
Release scope Item Must Should Could Won't this time Login ✓ Browse ✓ Cart ✓ Checkout ✓ Card payment ✓ Delivery slots ✓ Favourites ✓ Promo codes ✓ Ratings ✓
Progress so far (items done) Sprint Done to date Total scope Sprint 1 3 11 Sprint 2 6 11 Sprint 3 8 11
Forecast: a likely range, from actual progress Most likely Sprint 5, possibly 6, if scope stays the same. Adding promo codes would move it a Sprint later.
Forecast from what the team has actually finished, as a range. If scope grows, the forecast moves: show both.
PreviewRelease plan and forecast Scrum and product The Product Owner, with the Developers' forecast Release decided by the Product Owner Stakeholders ask “when?” and scope must be traded honestly. Product Owner, Scrum Master
Day in the Role Product roadmap Direction: now, next, later
Now Shoppers can buy groceries Next Delivery they can trust: slots and tracking Weekly subscriptions (moved up) Later Loyalty rewards More cities What changed since last time, and why Subscriptions moved from later to next: customers ask weekly and competitors are adding them.
Outcomes, not dated features. The further out, the less certain: later items may change or disappear.
PreviewProduct roadmap Scrum and product The Product Owner Shared with stakeholders Stakeholders need direction without dated promises. Product Owner
Day in the Role Product value measures The value the product delivers
Current value: Value customers get today Measure Before Now Repeat orders a month 0 1,800 Customer satisfaction n/a 4.4 of 5
Unrealised value: Value still possible Measure Before Now Customers asking for subscriptions few 120 a week
Time to market: How fast value reaches users Measure Before Now Time from idea to users 4 weeks 1 Sprint
Ability to innovate: Capacity for new value Measure Before Now Time on new features, not fixes 50% 70%
What we'll do differently Start subscriptions as the next Product Goal; keep testing on real phones to protect time for innovation.
Measure outcomes and the ability to deliver them, not output. Pick few measures and act on them.
PreviewProduct value measures Scrum and product The Product Owner Shared with the sponsor You need to show the value a product delivers, not the output. Product Owner, Scrum Master