Monitoring and controlling · document brief End-stage report The report for the board at the end of a stage: how the stage went against its baselines, whether the business case still holds, and the plan for the next stage, ending in a go or no-go decision.
6 sections Used by Project Manager
Pre-project Initiating Planning Executing Monitoring Closing
Use it when a stage ends and the board decides whether to continue.
Why it matters It makes the decision to continue a conscious one, based on evidence, and passes lessons into the next stage.
Written by The project manager
Approved by The project board decides at the stage gate
When it appears At the end of every management stage.
What goes inside Stage performance Baseline, actual and forecast.
Business case check Still valid?
Risks and issues The main ones going into the next stage.
Lessons From this stage.
Next stage What it delivers and when.
Board decision Go, go with conditions, or stop.
Watch out for A formality where nobody would ever say stop. Business case not updated. Lessons not carried forward. How this document fits
This document End-stage report Made with
Feeds Go or no-go decision Plan for the next stage Updated business case
What the letters mean
PRINCE2 Projects in Controlled Environments: a project management method
R · A · G Red, amber, green: status lights
◆ A milestone or decision point
€M Millions of euros (€4.2M = €4,200,000)
The document Filled-in example Blank template
Day in the Role End-stage report Stage gate: continue, with conditions, or stop
Pre-project
◆ Initiating
◆ Planning
◆ Executing
◆ Monitoring
◆ Closing
◆ = stage gate. Circle the gate this report is for.
Stage performance against baselines Area Baseline Actual or forecast Status Time Opening week 30 Week 30 (online booking +4 weeks) R A G Cost €4.2M €4.1M to €4.13M R A G Scope 6 deliverables 6, plus 3 approved changes R A G Quality Accepted to criteria Accepted with 6 minor defects R A G
Business case check Question Answer Still needed? Yes: waiting times keep rising Still affordable? Yes: about €4.2M, inside the approved funding Benefits still achievable? Yes: online booking benefits a month later Payback About 7.1 years (was 7)
Risks going forward Licence inspection (slot booked, week 28) Staff training complete in time Online booking go-live after opening Lessons from this stage Book every external inspection as early as possible Watch supplier backlogs as triggers The drawing revision log works Next stage Handover and opening: licence, mock clinic day, opening in week 30, contract closure and the benefits plan.
Board decision Go Go with conditions Stop
Conditions The licence result must be in before the opening event is announced.
Day in the Role End-stage report Stage gate: continue, with conditions, or stop
Pre-project
◆ Initiating
◆ Planning
◆ Executing
◆ Monitoring
◆ Closing
◆ = stage gate. Circle the gate this report is for.
Stage performance against baselines Area Baseline Actual or forecast Status Time R A G Cost R A G Scope R A G Quality R A G
Business case check Question Answer Still needed? Still affordable? Benefits still achievable? Payback
Board decision Go Go with conditions Stop
Illustrative example in our own words: not a real project or organisation.