Monitoring and controlling · document brief

End-stage report

The report for the board at the end of a stage: how the stage went against its baselines, whether the business case still holds, and the plan for the next stage, ending in a go or no-go decision.

6 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

a stage ends and the board decides whether to continue.

Why it matters

It makes the decision to continue a conscious one, based on evidence, and passes lessons into the next stage.

Written by

The project manager

Approved by

The project board decides at the stage gate

When it appears

At the end of every management stage.

What goes inside

  1. Stage performance Baseline, actual and forecast.
  2. Business case check Still valid?
  3. Risks and issues The main ones going into the next stage.
  4. Lessons From this stage.
  5. Next stage What it delivers and when.
  6. Board decision Go, go with conditions, or stop.

Watch out for

  • A formality where nobody would ever say stop.
  • Business case not updated.
  • Lessons not carried forward.

How this document fits

This documentEnd-stage reportMade with
FeedsGo or no-go decisionPlan for the next stageUpdated business case
Where you will meet this: End stage report (PRINCE2) · phase gate review · stage reviewPrint the example ↗Print the blank ↗

The document

Day in the RoleEnd-stage reportStage gate: continue, with conditions, or stop
Version1.0
Date15 March
Pre-project
◆
Initiating
◆
Planning
◆
Executing
◆
Monitoring
◆
Closing

◆ = stage gate. Circle the gate this report is for.

Stage performance against baselines

AreaBaselineActual or forecastStatus
TimeOpening week 30Week 30 (online booking +4 weeks)RAG
Cost€4.2M€4.1M to €4.13MRAG
Scope6 deliverables6, plus 3 approved changesRAG
QualityAccepted to criteriaAccepted with 6 minor defectsRAG

Business case check

QuestionAnswer
Still needed?Yes: waiting times keep rising
Still affordable?Yes: about €4.2M, inside the approved funding
Benefits still achievable?Yes: online booking benefits a month later
PaybackAbout 7.1 years (was 7)

Risks going forward

  • Licence inspection (slot booked, week 28)
  • Staff training complete in time
  • Online booking go-live after opening

Lessons from this stage

  • Book every external inspection as early as possible
  • Watch supplier backlogs as triggers
  • The drawing revision log works

Next stage

Handover and opening: licence, mock clinic day, opening in week 30, contract closure and the benefits plan.

Board decision

GoGo with conditionsStop
Conditions
The licence result must be in before the opening event is announced.
Sponsor
Signature
Date
Day in the Role · End-stage reportIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleEnd-stage reportStage gate: continue, with conditions, or stop
Version
Date
Pre-project
◆
Initiating
◆
Planning
◆
Executing
◆
Monitoring
◆
Closing

◆ = stage gate. Circle the gate this report is for.

Stage performance against baselines

AreaBaselineActual or forecastStatus
TimeRAG
CostRAG
ScopeRAG
QualityRAG

Business case check

QuestionAnswer
Still needed?
Still affordable?
Benefits still achievable?
Payback

Risks going forward

Lessons from this stage

Next stage

Board decision

GoGo with conditionsStop
Conditions
Sponsor
Signature
Date
Day in the Role · End-stage reportTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.