Planning · document brief

Risk management plan

How risk will be managed on the project: scales, appetite per area, roles, review rhythm, reserves and how quantitative analysis is used.

4 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

everyone should handle risk the same way, with an agreed appetite.

Why it matters

It makes risk decisions consistent: everyone uses the same scales and knows how much risk is acceptable where.

Written by

The project manager

Approved by

The sponsor

When it appears

In planning; reviewed at stage ends.

What goes inside

  1. Risk appetite Per area: low, moderate or high.
  2. Scales and thresholds Likelihood and impact definitions.
  3. Roles and rhythm Who owns, who reviews, how often.
  4. Reserves Contingency and management reserve rules.

Watch out for

  • Scales nobody agreed.
  • No stated appetite, so every decision is argued afresh.

How this document fits

NeedsProject charterOrganisation's risk policy
FeedsRisk registerRisk reviews
Where you will meet this: Risk management plan (PMI) · risk management approach (PRINCE2)Print the example ↗Print the blank ↗

The document

Day in the RoleRisk management planHow this project handles risk
Version1.0
Date15 March

Risk appetite by area

AreaRisk appetiteWhat it means in practice
Patient safety
LowModerateHigh
No avoidable risk to patients is accepted
Legal compliance
LowModerateHigh
Every obligation met before opening
Cost
LowModerateHigh
Within contingency; reserve with sponsor approval
Schedule
LowModerateHigh
± 2 weeks per stage
Opening-day extras
LowModerateHigh
Nice to have; can be dropped

Roles and review rhythm

Risk owners update their risks weekly. The project manager reviews the register weekly; the board reviews the top 10 monthly.

Reserves

Contingency €150k, used by the project manager for identified risks and logged. Management reserve €300k, used only with the sponsor's approval.

When we put numbers on risk

Expected value for decisions over €25k; schedule simulation before each stage gate.

Sponsor
Signature
Date
Day in the Role · Risk management planIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleRisk management planHow this project handles risk
Version
Date

Risk appetite by area

AreaRisk appetiteWhat it means in practice
Safety
LowModerateHigh
Legal compliance
LowModerateHigh
Cost
LowModerateHigh
Schedule
LowModerateHigh
Quality
LowModerateHigh
Reputation
LowModerateHigh

Roles and review rhythm

Reserves

When we put numbers on risk

Sponsor
Signature
Date
Day in the Role · Risk management planTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.