Planning · document briefRisk management plan
How risk will be managed on the project: scales, appetite per area, roles, review rhythm, reserves and how quantitative analysis is used.
4 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
everyone should handle risk the same way, with an agreed appetite.
Why it matters
It makes risk decisions consistent: everyone uses the same scales and knows how much risk is acceptable where.
Written by
The project manager
When it appears
In planning; reviewed at stage ends.
What goes inside
Risk appetite Per area: low, moderate or high.
Scales and thresholds Likelihood and impact definitions.
Roles and rhythm Who owns, who reviews, how often.
Reserves Contingency and management reserve rules.
Watch out for
- Scales nobody agreed.
- No stated appetite, so every decision is argued afresh.
How this document fits
This documentRisk management planMade with
The document
Day in the RoleRisk management planHow this project handles risk
Risk appetite by area
| Area | Risk appetite | What it means in practice |
|---|
| Patient safety | LowModerateHigh | No avoidable risk to patients is accepted |
|---|
| Legal compliance | LowModerateHigh | Every obligation met before opening |
|---|
| Cost | LowModerateHigh | Within contingency; reserve with sponsor approval |
|---|
| Schedule | LowModerateHigh | ± 2 weeks per stage |
|---|
| Opening-day extras | LowModerateHigh | Nice to have; can be dropped |
|---|
Roles and review rhythm
Risk owners update their risks weekly. The project manager reviews the register weekly; the board reviews the top 10 monthly.
Reserves
Contingency €150k, used by the project manager for identified risks and logged. Management reserve €300k, used only with the sponsor's approval.
When we put numbers on risk
Expected value for decisions over €25k; schedule simulation before each stage gate.
Day in the RoleRisk management planHow this project handles risk
Risk appetite by area
| Area | Risk appetite | What it means in practice |
|---|
| Safety | LowModerateHigh | |
|---|
| Legal compliance | LowModerateHigh | |
|---|
| Cost | LowModerateHigh | |
|---|
| Schedule | LowModerateHigh | |
|---|
| Quality | LowModerateHigh | |
|---|
| Reputation | LowModerateHigh | |
|---|
When we put numbers on risk
Illustrative example in our own words: not a real project or organisation.