Executing · document brief

Meeting minutes and action log

A short record of a meeting: who attended, what was discussed and decided, and the actions with owners and dates.

3 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

a meeting's decisions and actions must be recorded and followed up.

Why it matters

It turns talk into decisions and actions that get done, and gives absent people the outcome.

Written by

The chair or project coordinator

Approved by

Confirmed at the start of the next meeting

When it appears

After every regular project meeting, sent the same day.

What goes inside

  1. Details Meeting, date, chair, attendees.
  2. Items Topic, discussion, decision.
  3. Actions What, who, by when, done.

Watch out for

  • Writing everything said instead of decisions and actions.
  • Actions with no owner or date.
  • Sent days later.

How this document fits

NeedsAgendaPrevious actions
This documentMeeting minutes and action logMade with
FeedsDecision logIssue logActions done
Where you will meet this: Minutes · action log · meeting notesPrint the example ↗Print the blank ↗

The document

Day in the RoleMeeting minutes and action logDecisions and actions, not a transcript
MeetingSite coordination
DateThursday, week 12
ChairAnnelise (Project Manager)
Notes byAya (Project Coordinator)
Next meetingThursday, week 13, 08:00
Present
Arash (Contractor), Aine (IT Lead), Anwar (Facilities Coordinator), Antonia (Compliance Lead)
Apologies
Alfonso (Software Vendor)

Items

No.ItemDiscussionDecision
1Previous actionsAll done except the network test dateAine to confirm by Friday
2Cabling handoverFinished last week; IT not toldThree-week look-ahead shared every Monday
3DeliveriesShops complain about morning lorriesDelivery window 9:30 to 15:00

Actions

ActionOwnerDueDone
Share the three-week look-aheadArash (Contractor)Every Monday
Confirm network test dateAine (IT Lead)Friday
Tell the shops about the delivery windowAya (Project Coordinator)Tomorrow

Send the same day. Confirm the actions at the start of the next meeting.

Day in the Role · Meeting minutes and action logIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleMeeting minutes and action logDecisions and actions, not a transcript
Meeting
Date
Chair
Notes by
Next meeting
Present
Apologies

Items

No.ItemDiscussionDecision

Actions

ActionOwnerDueDone

Send the same day. Confirm the actions at the start of the next meeting.

Day in the Role · Meeting minutes and action logTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.