Planning · document briefProject schedule
When each activity happens, how long it takes, what it depends on, and which chain of activities decides the end date.
4 sections
Used by Process Improvement Specialist, Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
you need to know when everything happens and what decides the end date.
Why it matters
It shows whether the dates are possible, where there's slack and where there isn't, and gives everyone the same timeline.
Written by
The project manager (often with a planner)
Approved by
The sponsor or board, as part of the plan
When it appears
In planning, after the WBS and estimates. Updated with progress every week; the approved version becomes the schedule baseline.
What goes inside
Activities Each activity with its duration and what must finish first.
Milestones Key dates with no duration.
Critical path The longest chain of dependent activities.
Main schedule risks What could move the end date.
Watch out for
- Dates with no dependencies behind them.
- One-number estimates for very uncertain work.
- A plan that was never updated after week one.
How this document fits
This documentProject scheduleMade with
The document
Day in the RoleProject scheduleGantt chart · weeks 1 to 30
ActivityCritical path (no slack)◆ MilestoneShade the weeks for each activity; mark critical bars darker.
| ID | Activity | Dur. | After | Month 1 | Month 2 | Month 3 | Month 4 | Month 5 | Month 6 | Month 7 |
|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 |
|---|
| A1 | Survey and design | 7 wk | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| A2 | Purchase completes | 1 wk | A1 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| A3 | Asbestos removal | 3 wk | A2 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| A4 | Building works | 14 wk | A3 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| A5 | Equipment order and delivery | 14 wk | A1 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| A6 | Booking system setup | 10 wk | A2 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| A7 | Hiring | 12 wk | A2 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| A8 | Training | 5 wk | A6, A7 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| A9 | Equipment installation | 2 wk | A4, A5 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| A10 | Inspection | 1 wk | A9 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| A11 | Licence | 2 wk | A10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| A12 | Opening | – | A8, A11 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ◆ |
Critical path and slack
Critical path: A1 → A2 → A3 → A4 → A9 → A10 → A11 → A12, no slack. Hiring (A7) and training (A8) have 5 weeks of slack.
Day in the RoleProject scheduleGantt chart · weeks 1 to 30
ActivityCritical path (no slack)◆ MilestoneShade the weeks for each activity; mark critical bars darker.
| ID | Activity | Dur. | After | Month 1 | Month 2 | Month 3 | Month 4 | Month 5 | Month 6 | Month 7 |
|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 |
|---|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Illustrative example in our own words: not a real project or organisation.