When each activity happens, how long it takes, what it depends on, and which chain of activities decides the end date.

4 sections
Used by Process Improvement Specialist, Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

you need to know when everything happens and what decides the end date.

Why it matters

It shows whether the dates are possible, where there's slack and where there isn't, and gives everyone the same timeline.

Written by

The project manager (often with a planner)

Approved by

The sponsor or board, as part of the plan

When it appears

In planning, after the WBS and estimates. Updated with progress every week; the approved version becomes the schedule baseline.

What goes inside

  1. Activities Each activity with its duration and what must finish first.
  2. Milestones Key dates with no duration.
  3. Critical path The longest chain of dependent activities.
  4. Main schedule risks What could move the end date.

Watch out for

  • Dates with no dependencies behind them.
  • One-number estimates for very uncertain work.
  • A plan that was never updated after week one.

How this document fits

NeedsWork breakdown structureEstimates from the leadsSupplier lead times
Where you will meet this: Schedule · Gantt chart · schedule baseline · network diagramPrint the example ↗Print the blank ↗

The document

Day in the RoleProject scheduleGantt chart · weeks 1 to 30
Version1.0
Date15 March
ActivityCritical path (no slack)◆ MilestoneShade the weeks for each activity; mark critical bars darker.
IDActivityDur.AfterMonth 1Month 2Month 3Month 4Month 5Month 6Month 7
123456789101112131415161718192021222324252627282930
A1Survey and design7 wk
A2Purchase completes1 wkA1
A3Asbestos removal3 wkA2
A4Building works14 wkA3
A5Equipment order and delivery14 wkA1
A6Booking system setup10 wkA2
A7Hiring12 wkA2
A8Training5 wkA6, A7
A9Equipment installation2 wkA4, A5
A10Inspection1 wkA9
A11Licence2 wkA10
A12Opening–A8, A11◆

Critical path and slack

Critical path: A1 → A2 → A3 → A4 → A9 → A10 → A11 → A12, no slack. Hiring (A7) and training (A8) have 5 weeks of slack.

Day in the Role · Project scheduleIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleProject scheduleGantt chart · weeks 1 to 30
Version
Date
ActivityCritical path (no slack)◆ MilestoneShade the weeks for each activity; mark critical bars darker.
IDActivityDur.AfterMonth 1Month 2Month 3Month 4Month 5Month 6Month 7
123456789101112131415161718192021222324252627282930

Critical path and slack

Day in the Role · Project scheduleTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.