Planning · document brief

Communication plan

Who needs what information, in what format, how often, and who provides it.

3 sections
Used by Process Improvement Specialist, Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

many people need different information at different times.

Why it matters

It makes sure the right people get the right information at the right time, without flooding everyone.

Written by

The project manager

Approved by

The sponsor

When it appears

In planning, after the stakeholder register. Updated when stakeholders or needs change.

What goes inside

  1. Audiences and messages Per audience: what, how, how often, who.
  2. Meeting rhythm Regular meetings and reports.
  3. Escalation How urgent news travels.

Watch out for

  • Same message to everyone.
  • Reports nobody reads.
  • No route for bad news to travel fast.

How this document fits

NeedsStakeholder registerRACI chartGovernance from the charter
FeedsProject management planStatus reportsResidents' updates
Where you will meet this: Communication management plan (PMI) · communication management approach (PRINCE2)Print the example ↗Print the blank ↗

The document

Day in the RoleCommunication planWho needs what, how, and how often
Version1.0
Date15 March

Who hears what

AudienceWhat they needHowHow oftenFrom
Atticus (Sponsor)Progress, risks, decisions neededOne-page status by emailWeekly, FridayAnnelise (Project Manager)
Project boardProgress against baselines, exceptionsMeeting and reportMonthlyAnnelise (Project Manager)
Project teamActions, blockers, next weekMonday meetingWeeklyAya (Project Coordinator)
ResidentsNews, dates, how to registerNewsletter and council websiteMonthlyAya (Project Coordinator)
Health authority inspectorDesign and building progressReview meetingAt milestonesAntonia (Compliance Lead)
SuppliersDates, changes, acceptanceProgress meetingFortnightlyAnnelise (Project Manager)

The weekly rhythm

MonTeam meeting
TueBoard (1st Tue)
WedSupplier meeting (fortnightly)
Thu
FriStatus to Atticus (Sponsor)Residents' update (last Fri)

Write each regular meeting or report on its day. Note how often (weekly, fortnightly, monthly).

Escalation: how bad news travels

Anything that threatens a milestone or a tolerance: same day to Annelise (Project Manager), within two days to Atticus (Sponsor) with options.

Channels

With n people there are n × (n − 1) ÷ 2 possible channels.

People12
Channels66
Day in the Role · Communication planIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleCommunication planWho needs what, how, and how often
Version
Date

Who hears what

AudienceWhat they needHowHow oftenFrom

The weekly rhythm

Mon
Tue
Wed
Thu
Fri

Write each regular meeting or report on its day. Note how often (weekly, fortnightly, monthly).

Escalation: how bad news travels

Channels

With n people there are n × (n − 1) ÷ 2 possible channels.

People
Channels
Day in the Role · Communication planTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.