Approve €4.2M to convert the Riverside warehouse into a community health clinic, opening in 7 months.
Executive summary
Residents of Riverside travel 40 minutes for basic care and wait 3 weeks for a GP. Converting the empty warehouse into a 24-room clinic is the only option that fits the budget, meets demand and opens by next autumn.
Investment€4.2M
Running cost€1.9M / year
Payback≈ 7 years
OpeningMonth 7
1. Why we need this
40-minute journeys to the nearest clinic
GP waiting time 3 weeks and rising
Many minor cases at the emergency department
2. Options considered
Option
Outcome of the comparison
Do nothing
Not chosen: waiting times keep growing
Renovate old clinic
Not chosen: too small for demand
Convert warehouse
Recommended: right size, fits budget and time
Build new
Not chosen: €7.5M and 18 months
3. Benefits
Benefit
Today
Target
By when
Owner
Travel time to care
40 min
Under 15 min
Opening
Atticus (Sponsor)
GP waiting time
3 weeks
Under 1 week
Year 1
Amani (Clinical Lead)
Minor emergency visits
100%
−20%
Year 1
Amani (Clinical Lead)
4. Main risks
Risk
Likelihood (L/M/H)
Impact (L/M/H)
Response
Old building structure
M
H
Structural survey before purchase
Equipment lead times (14 weeks)
H
M
Order in month 1
Not enough staff hired in time
M
H
Start hiring in month 3
5. Approval
ApprovedApproved with conditionsNot approved
Conditions or comments
Sponsor
Signature
Date
Funding body
Signature
Date
Day in the Role · Business caseIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleBusiness caseBusiness case report
Version
Date
Decision requested
Executive summary
Investment
Running cost
Payback
Start or opening
1. Why we need this
2. Options considered
Option
Outcome of the comparison
3. Benefits
Benefit
Today
Target
By when
Owner
4. Main risks
Risk
Likelihood (L/M/H)
Impact (L/M/H)
Response
5. Approval
ApprovedApproved with conditionsNot approved
Conditions or comments
Sponsor
Signature
Date
Funding body
Signature
Date
Day in the Role · Business caseTemplate · free to use and adapt · dayintherole.com
Illustrative example in our own words: not a real project or organisation.