Closing · document brief Contract closure checklist A checklist for closing each contract: deliverables accepted, claims settled, final payments and retention, documents received, final review, closure letter.
3 sections Used by Project Manager
Pre-project Initiating Planning Executing Monitoring Closing
Use it when a supplier's work ends and the contract must be closed properly.
Why it matters It makes sure nothing is left open: no unpaid amounts, no unsettled claims, no missing warranties.
Written by Procurement with the project manager
Approved by Procurement; confirmed in writing to the supplier
When it appears As each supplier's work ends, and before the project closes.
What goes inside Contracts One row per contract with each closure step.
Final accounts Agreed final amounts.
Procurement lessons What to keep and change.
Watch out for Paying the last invoice and calling it closed. Releasing retention early. No record of why claims were settled. How this document fits
This document Contract closure checklist Made with
The document Filled-in example Blank template
Day in the Role Contract closure checklist Every contract closed, on the agreed terms
Closure steps per contract Contract Accepted Claims settled Final payment Retention released Documents received Closure letter Building works (RHC-SOW-01) ✓ ✓ ✓ Month 6 ✓ ✓ Booking system ✓ ✓ ✓ — ✓ ✓
Tick each step, or write the agreed date if it comes later (for example a retention release).
Final accounts (€) Supplier Contract value Approved changes Final amount Building contractor 3,000,000 38,000 3,038,000 Booking system vendor 200,000 5,000 205,000
What we learned about buying Fixed price worked well for clearly defined works Check the buyer's own systems before signing integration contracts Supplier scorecards from month 1 kept reviews factual
Day in the Role Contract closure checklist Every contract closed, on the agreed terms
Closure steps per contract Contract Accepted Claims settled Final payment Retention released Documents received Closure letter
Tick each step, or write the agreed date if it comes later (for example a retention release).
Final accounts (€) Supplier Contract value Approved changes Final amount
What we learned about buying
Illustrative example in our own words: not a real project or organisation.
See it in the story In the Project Manager story