Scrum and product · document briefImpediment log
A visible list of what is blocking the team, its impact, who is removing it and by when.
2 sections
Used by Product Owner, Scrum Master
Scrum and product
Use it when
blockers need to be visible and removed quickly.
Why it matters
It makes blockers visible early, shows the cost of waiting, and keeps the Scrum Master's work on removing them transparent.
Written by
The Scrum Master
Approved by
Not approved; kept open and visible
When it appears
Throughout every Sprint; reviewed at the Daily Scrum and in the Retrospective.
What goes inside
Impediments
Patterns Repeated causes worth fixing at the root.
Watch out for
- Logging blockers the team could solve itself.
- No date raised, so waiting time is invisible.
- Closing an item without fixing the cause.
How this document fits
NeedsDaily ScrumTeam observations
This documentImpediment logMade with
The document
Day in the RoleImpediment logWhat blocks the team, and who's removing it
| Raised | Impediment | Impact | Owner | Action | Resolved |
|---|
| Day 2 | No API keys for login | Login blocked | Aaron (Scrum Master) | Chased IT with the impact | Day 3 |
| Day 8 | No phone testing tool | Cart can't be tested | Aaron (Scrum Master) | Free trial, then a licence | Day 10 |
| Week 6 | Map service licence for tracking | Tracking blocked | Adam (CEO) | Licence approved: value outweighs cost | Week 7 |
Patterns worth fixing at the root
- Access and licences: a fast route agreed with IT and the sponsor
An impediment is anything the team can't solve by itself that slows progress. Record when it was raised: waiting time is the cost.
Day in the RoleImpediment logWhat blocks the team, and who's removing it
| Raised | Impediment | Impact | Owner | Action | Resolved |
|---|
| | | | | |
| | | | | |
| | | | | |
| | | | | |
| | | | | |
| | | | | |
| | | | | |
| | | | | |
| | | | | |
| | | | | |
| | | | | |
Patterns worth fixing at the root
An impediment is anything the team can't solve by itself that slows progress. Record when it was raised: waiting time is the cost.
Illustrative example in our own words: not a real project or organisation.