Planning · document brief

Statement of work

The part of a contract that tells a supplier exactly what to deliver, by when, to what standard, and how payment and acceptance work.

6 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

a supplier must know exactly what to deliver, by when and how it's accepted.

Why it matters

It makes sure every bidder prices the same work and that both sides know what “done” means before money changes hands.

Written by

The project manager with procurement

Approved by

Procurement and the sponsor; signed by both parties

When it appears

In planning, before a tender. It goes out with the request for bids and becomes part of the contract.

What goes inside

  1. Background Why the work is needed.
  2. Scope of work What the supplier must do, and what they don't.
  3. Deliverables and dates What, by when.
  4. Acceptance How each deliverable is checked.
  5. Price and payment Contract type and payment milestones.
  6. Signatures Both parties.

Watch out for

  • Vague scope that invites claims later.
  • Payment before acceptance.
  • Copying the whole project scope instead of the supplier's part.

How this document fits

This documentStatement of workMade with
FeedsContract with the supplierTender evaluationCost baseline
Where you will meet this: SOW · procurement statement of work · scope of servicesPrint the example ↗Print the blank ↗

The document

Day in the RoleStatement of workContract schedule: what the supplier delivers
Version1.0
Date15 March
ReferenceRHC-SOW-01
SupplierThe building contractor (selected by tender)

This statement of work forms part of the contract between Day in the Role (the buyer) and the supplier named above.

1. Background

The council is converting the Riverside warehouse into a community health clinic that must open in month 7.

2. Scope of work

The supplier will:

  • Remove asbestos from the roof and walls
  • Repair the structure as listed in the survey
  • Complete the fit-out to the approved design

Not included:

  • Clinical equipment
  • IT and network equipment (cabling is included)

3. Deliverables and dates

Delive­rableDue
Site cleared of asbestosWeek 11
Structure repairedWeek 17
Fit-out completeWeek 25
Handover documentsWeek 26

4. Acceptance

Building-control sign-off and a joint inspection with the council's compliance lead.

5. Contract type and price

Fixed priceTime and materials (with a cap)Cost-reimbursable plus fee
Price€3,000,000

6. Payment milestones

Payment due whenShare of price
On start10%
Site cleared, accepted30%
Structure repaired, accepted30%
Fit-out accepted20%
6 months without defects10%

7. Changes

Changes to scope, dates or price are agreed in writing by both parties before work on them starts.

For the buyer
Signature
Date
For the supplier
Signature
Date
Day in the Role · Statement of workIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleStatement of workContract schedule: what the supplier delivers
Version
Date
Reference
Supplier

This statement of work forms part of the contract between Day in the Role (the buyer) and the supplier named above.

1. Background

2. Scope of work

The supplier will:

Not included:

3. Deliverables and dates

Delive­rableDue

4. Acceptance

5. Contract type and price

Fixed priceTime and materials (with a cap)Cost-reimbursable plus fee
Price

6. Payment milestones

Payment due whenShare of price

7. Changes

Changes to scope, dates or price are agreed in writing by both parties before work on them starts.

For the buyer
Signature
Date
For the supplier
Signature
Date
Day in the Role · Statement of workTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.