Planning · document briefStatement of work
The part of a contract that tells a supplier exactly what to deliver, by when, to what standard, and how payment and acceptance work.
6 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
a supplier must know exactly what to deliver, by when and how it's accepted.
Why it matters
It makes sure every bidder prices the same work and that both sides know what “done” means before money changes hands.
Written by
The project manager with procurement
Approved by
Procurement and the sponsor; signed by both parties
When it appears
In planning, before a tender. It goes out with the request for bids and becomes part of the contract.
What goes inside
Background Why the work is needed.
Scope of work What the supplier must do, and what they don't.
Deliverables and dates What, by when.
Acceptance How each deliverable is checked.
Price and payment Contract type and payment milestones.
Signatures Both parties.
Watch out for
- Vague scope that invites claims later.
- Payment before acceptance.
- Copying the whole project scope instead of the supplier's part.
How this document fits
This documentStatement of workMade with
The document
Day in the RoleStatement of workContract schedule: what the supplier delivers
ReferenceRHC-SOW-01
SupplierThe building contractor (selected by tender)
This statement of work forms part of the contract between Day in the Role (the buyer) and the supplier named above.
1. Background
The council is converting the Riverside warehouse into a community health clinic that must open in month 7.
2. Scope of work
The supplier will:
- Remove asbestos from the roof and walls
- Repair the structure as listed in the survey
- Complete the fit-out to the approved design
Not included:
- Clinical equipment
- IT and network equipment (cabling is included)
3. Deliverables and dates
| Deliverable | Due |
|---|
| Site cleared of asbestos | Week 11 |
| Structure repaired | Week 17 |
| Fit-out complete | Week 25 |
| Handover documents | Week 26 |
4. Acceptance
Building-control sign-off and a joint inspection with the council's compliance lead.
5. Contract type and price
Fixed priceTime and materials (with a cap)Cost-reimbursable plus fee
Price€3,000,000
6. Payment milestones
| Payment due when | Share of price |
|---|
| On start | 10% |
| Site cleared, accepted | 30% |
| Structure repaired, accepted | 30% |
| Fit-out accepted | 20% |
| 6 months without defects | 10% |
7. Changes
Changes to scope, dates or price are agreed in writing by both parties before work on them starts.
Day in the RoleStatement of workContract schedule: what the supplier delivers
This statement of work forms part of the contract between Day in the Role (the buyer) and the supplier named above.
2. Scope of work
The supplier will:
Not included:
3. Deliverables and dates
5. Contract type and price
Fixed priceTime and materials (with a cap)Cost-reimbursable plus fee
Price
6. Payment milestones
| Payment due when | Share of price |
|---|
| |
| |
| |
| |
| |
| |
7. Changes
Changes to scope, dates or price are agreed in writing by both parties before work on them starts.
Illustrative example in our own words: not a real project or organisation.