Process improvement · document brief

Benefits sign-off

Finance's confirmation of what an improvement project is worth: each benefit line measured with the method agreed at the start, the project's costs, and the net result.

4 sections
Used by Process Improvement Specialist
Process improvement

Use it when

an improvement's benefits must be measured and confirmed by finance.

Why it matters

It turns estimated benefits into confirmed ones, so the organisation knows what it gained and trusts the next project's estimates.

Written by

The project leader prepares it

Approved by

Finance signs it; the sponsor accepts it at the closing review

When it appears

In Control, once the new process has run long enough to measure (often three months), and again later (often at 12 months).

What goes inside

  1. Benefit lines Each line with its method, before, after and value.
  2. Costs One-off and running costs of the changes.
  3. Result Net benefit, payback, and what is cash or avoided cost.
  4. Sign-off Finance and sponsor.

Watch out for

  • Counting the estimate instead of measuring.
  • Changing the method after the event.
  • Leaving out the running costs of the new process.

How this document fits

This documentBenefits sign-offMade with
Where you will meet this: Benefits realisation · financial validation · savings sign-offPrint the example ↗Print the blank ↗

The document

Day in the RoleBenefits sign-offBenefits measured and confirmed
Version1.0
Date15 March

Benefit lines

BenefitMethod agreed in DefineBeforeAfterValue a year
Missed appointments12,700 × change in missed share × €1515.7%8.3%€14,100
Repeat callsCalls × €1.2011,2502,813€10,125
Emergency visits (avoided cost)Visits × €120208104€12,480

Costs

CostOne-offA year
Team time€14,000€0
System changes€3,000€0
Training€1,500€0
Cover sessions€0within existing budget

Result

€36,705 a year (€24,225 clinic savings, €12,480 avoided health-system cost). One-off cost €18,500; payback about 9 months on the clinic's own savings. Check again at 12 months.

Measure each line with the method agreed in Define. Show cash savings and avoided costs separately. Include the running costs of the new process.

Finance
Signature
Date
Sponsor
Signature
Date
Day in the Role · Benefits sign-offIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleBenefits sign-offBenefits measured and confirmed
Version
Date

Benefit lines

BenefitMethod agreed in DefineBeforeAfterValue a year

Costs

CostOne-offA year

Result

Measure each line with the method agreed in Define. Show cash savings and avoided costs separately. Include the running costs of the new process.

Finance
Signature
Date
Sponsor
Signature
Date
Day in the Role · Benefits sign-offTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.