Executing · document briefPurchase order
The formal order sent to a supplier: what is bought, how many, at what price, where and when to deliver, and under which terms.
4 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
goods or services are bought and the order must be formal.
Why it matters
It commits the budget, gives the supplier a clear order and is matched against the delivery and invoice before payment.
Written by
Procurement or the project coordinator
Approved by
Whoever holds the budget authority for the amount
When it appears
Whenever goods or services are bought, after approval and before delivery.
What goes inside
Order details Number, supplier, budget code, dates.
Lines Item, quantity, unit price, total.
Terms Delivery address, payment terms, contract reference.
Authorised Within the approver's limit.
Watch out for
- Ordering before approval.
- Paying invoices that don't match the order and delivery.
How this document fits
NeedsApproved budgetSupplier quote or contract
This documentPurchase orderMade with FeedsDeliveryInvoice matchingcost-baseline (actual cost)
The document
Day in the RolePurchase orderWhat we're buying, at what price, by when
Purchase orderPO-1042
DateWeek 4
Budget codeRHC-02 Equipment
Deliver byWeek 23
Supplier
Medical equipment supplier (framework FW-17)
Deliver to
Riverside warehouse, loading bay B
| Item | Quantity | Unit price (€) | Total (€) |
|---|
| X-ray unit | 1 | 180,000 | 180,000 |
| Ultrasound scanner | 2 | 45,000 | 90,000 |
| Examination couch | 12 | 2,500 | 30,000 |
| Installation and testing | 1 | 15,000 | 15,000 |
| Order total | 315,000 |
Terms
- Payment 30 days after accepted delivery
- Fixed prices under framework contract FW-17
- Cancellation allowed without cost until week 14
Authorised by (within their budget authority)Atticus (Sponsor)
Day in the RolePurchase orderWhat we're buying, at what price, by when
Purchase order
Date
Budget code
Deliver by
| Item | Quantity | Unit price (€) | Total (€) |
|---|
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| Order total | |
Authorised by (within their budget authority)
Illustrative example in our own words: not a real project or organisation.