Pre-project and business justification · document briefOptions analysis
A side-by-side look at the different ways to meet the need, including doing nothing, so the choice is made on evidence.
5 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
there's more than one way to meet a need, including doing nothing.
Why it matters
It stops the first idea becoming the only idea. Comparing real options, with the same criteria, makes the recommendation defensible.
Written by
The project manager or business analyst, with experts for each option
Approved by
The sponsor, as part of the business case
When it appears
Pre-project, before the business case recommends a way forward. Its result goes into the business case.
What goes inside
The need The problem every option must solve.
Options Three to five realistic options, always including “do nothing” or “do minimum”.
Criteria What you compare: cost, time, benefits, risk, fit with strategy.
Comparison A table of each option against each criterion.
Recommendation The preferred option and why, plus what would change the choice.
Watch out for
- A “do nothing” option written to look terrible on purpose.
- Comparing options on different criteria.
- Choosing first and building the analysis to fit.
How this document fits
This documentOptions analysisMade with
The document
Day in the RoleOptions analysisWeighted decision matrix
The need every option must meet
Everyday health care within 15 minutes of home for 18,000 Riverside residents.
| Criterion | Weight | A | B | C | D |
|---|
| Option | | Do nothing | Renovate the old clinic (12 rooms) | Convert the warehouse (24 rooms) | Build new on a green site |
| Fits the €4.5M budget | 3 | 5×3 = 15 | 4×3 = 12 | 4×3 = 12 | 1×3 = 3 |
| Time to open | 2 | 5×2 = 10 | 4×2 = 8 | 3×2 = 6 | 1×2 = 2 |
| Capacity for demand | 3 | 1×3 = 3 | 2×3 = 6 | 5×3 = 15 | 5×3 = 15 |
| Risk (5 = low risk) | 2 | 2×2 = 4 | 4×2 = 8 | 3×2 = 6 | 3×2 = 6 |
| Community access | 1 | 1×1 = 1 | 3×1 = 3 | 4×1 = 4 | 4×1 = 4 |
| Weighted total | | 33 | 37 | 43 | 30 |
| Rank | | 3 | 2 | 1 | 4 |
Scoring key: 1 = poor · 2 = weak · 3 = acceptable · 4 = good · 5 = excellent. Weight: how much the criterion matters (1 to 3). Always keep “Do nothing” as option A.
Recommended option
ABCD
WhyThe only option that fits the budget, meets demand and can open by next autumn.
What would change our choiceIf the warehouse survey shows major structural problems, re-score option C on cost and risk.
Day in the RoleOptions analysisWeighted decision matrix
The need every option must meet
| Criterion | Weight | A | B | C | D |
|---|
| Option | | Do nothing | | | |
| | | | | |
| | | | | |
| | | | | |
| | | | | |
| | | | | |
| | | | | |
| Weighted total | | | | | |
| Rank | | | | | |
Scoring key: 1 = poor · 2 = weak · 3 = acceptable · 4 = good · 5 = excellent. Weight: how much the criterion matters (1 to 3). Always keep “Do nothing” as option A.
Recommended option
ABCD
What would change our choice
Illustrative example in our own words: not a real project or organisation.
See it in the story
In the Project Manager story