The plan that keeps an improved process on track: each key measure with its method, frequency, owner, limits and chart, the response when it goes wrong, and the lean controls.
4 sections Used by Process Improvement Specialist
Process improvement
Use it when
an improved process is handed to its owner and must stay on track.
Why it matters
It hands the gains to the process owner in a form that lasts, so problems are spotted and fixed in days, not months.
Written by
Written by the project leader; owned by the process owner
Approved by
The process owner signs it; the sponsor accepts it at the closing review
When it appears
Written at the start of Control, signed at handover, reviewed regularly and after any process change.
What goes inside
MeasuresOne row per measure.
Response planFor each likely signal: first action and who to tell.
First request to appointment offered, calendar days; 5 random requests a day
Daily
Astrid (Data Analyst)
Xbar 1.85 to 6.86; R up to 9.41
Xbar-R
Daily average wait
All routine requests booked that day
Daily
Astrid (Data Analyst)
2.76 to 5.56; CUSUM h = 2.2
I-MR and CUSUM
Not offered within 7 days
Share of the day's requests
Daily
Alma (Reception Team Lead)
Upper limit by day (about 0.21)
P chart
Missed appointments
Out of 50 checked a day
Daily for 3 months, then weekly
Alma (Reception Team Lead)
Up to 9.8 of 50
NP chart
Booking errors
Errors per booking
Daily
Alma (Reception Team Lead)
Upper limit by day (about 0.12)
U chart
8 am answer time
12 calls, minutes
Monthly
Alma (Reception Team Lead)
1.38 to 3.39
Xbar-S
Response plan
Signal
First action
Who acts
Who to tell
Doctor off at short notice
Book cover from the list
Aurelie (Practice Nurse Manager)
Doctors' team
Booking system down
Paper booking sheets; enter later
Alma (Reception Team Lead)
IT, Aurelie
CUSUM or EWMA signal
Check locum sessions and the rota
Aurelie (Practice Nurse Manager)
Atticus (Sponsor) if not fixed in a week
Point outside any limit
Find the cause the same day; record it
Measure owner
Aurelie
Lean controls
Weekly 5-minute 5S check of the booking desk, against the photo standard
Monthly test of the urgent-slot lock
Two-bin kanban for the 12 most-used supplies; cards checked weekly
Signals: a point outside a limit, 8 in a row on one side of the centre line, 6 in a row rising or falling. Record every signal, its cause and the action.
Process owner
Signature
Date
Project leader
Signature
Date
Day in the Role · Control planIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleControl planKeeping the gains
Version
Date
Process
Process owner
Review date
Measures
Measure
Definition and sample
How often
Owner
Limits or target
Chart
Response plan
Signal
First action
Who acts
Who to tell
Lean controls
Signals: a point outside a limit, 8 in a row on one side of the centre line, 6 in a row rising or falling. Record every signal, its cause and the action.
Process owner
Signature
Date
Project leader
Signature
Date
Day in the Role · Control planTemplate · free to use and adapt · dayintherole.com
Illustrative example in our own words: not a real project or organisation.