Initiating and governance · document brief

RAID log

One working log of the project's Risks, Assumptions, Issues and Dependencies, each with an owner and a next step.

4 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

risks, assumptions, issues and dependencies need one owned, visible list.

Why it matters

It keeps every uncertainty and problem visible in one place, so nothing is forgotten and every item has someone acting on it.

Written by

The project manager; each item has its own owner

Approved by

Reviewed by the project board; not formally approved

When it appears

Opened in initiating, reviewed at least weekly until the project closes.

What goes inside

  1. Risks Uncertain events that would affect the objectives: cause, effect, likelihood, impact, owner, response.
  2. Assumptions What you're treating as true without proof, and when you'll check it.
  3. Issues Problems happening now: priority, owner, action, due date.
  4. Dependencies What the project needs from others, or others need from it.

Watch out for

  • A long list nobody reads: review it in a fixed weekly slot.
  • Items without an owner or a next step.
  • Never closing items, so real problems get lost among old ones.

How this document fits

NeedsProject charterBusiness caseKick-off and team workshopsLessons from past projects
FeedsRisk registerStatus reportsDecisions by the project board
Where you will meet this: Risk register · assumption log · issue log · decision and dependency logs (often kept together as a RAID log, a common practice)Print the example ↗Print the blank ↗

The document

Day in the RoleRAID logRisks · Assumptions · Issues · Dependencies
Version1.0
Date15 March
ProjectRiverside Health Centre
Reviewed onThursday 4 April
R

Risks

Might happen. Write the cause, then the effect. Likelihood (L) and impact (I): H, M or L.

IDRisk (cause → effect)LIOwnerResponseStatus
R1Equipment takes 14 weeks, so opening could slipHMAya (Project Coordinator)Order early with a cancellation clause (approved)Open
R2Old structure needs more repair than expected, costs riseMHAnnelise (Project Manager)€40k survey before works; contingency held by sponsorOpen
R3Not enough nurses hired in timeMHAdaugo (HR Lead)Start hiring in month 3, agency backupOpen
A

Assumptions

Treated as true without proof. Check each one by a date; if it fails, it becomes an issue.

IDAssum­ptionCheck byStatus
A1Warehouse purchase completes in month 1Kick-offFailed: see I1
A2Regional funding per patient stays at today's rateMonth 3Open
I

Issues

Happening now. Each needs an owner, an action and a due date.

IDIssuePriorityOwnerActionDue
I1Purchase completes in month 2, not month 1HighAnnelise (Project Manager)Re-plan works, options to Atticus (Sponsor)Friday
D

Dependencies

What we need from others, or others need from us.

IDDepen­dencyFrom or to whomNeeded byStatus
D1Licence inspection needs the finished buildingHealth authorityMonth 6Planned
D2Network cabling before booking system installBuilding contractorMonth 4Open
Day in the Role · RAID logIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleRAID logRisks · Assumptions · Issues · Dependencies
Version
Date
Project
Reviewed on
R

Risks

Might happen. Write the cause, then the effect. Likelihood (L) and impact (I): H, M or L.

IDRisk (cause → effect)LIOwnerResponseStatus
A

Assumptions

Treated as true without proof. Check each one by a date; if it fails, it becomes an issue.

IDAssum­ptionCheck byStatus
I

Issues

Happening now. Each needs an owner, an action and a due date.

IDIssuePriorityOwnerActionDue
D

Dependencies

What we need from others, or others need from us.

IDDepen­dencyFrom or to whomNeeded byStatus
Day in the Role · RAID logTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.