Pre-project and business justification · document brief

Feasibility study

A short check, before a business case, of whether an idea can work: legally, technically, financially and practically, and under what conditions.

3 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

an idea needs checking before anyone spends money on a business case.

Why it matters

It stops impossible or unaffordable ideas early, and surfaces the conditions a project must meet.

Written by

The project manager or an analyst, with experts

Approved by

The sponsor or leadership team

When it appears

Pre-project, before money is spent on a full business case.

What goes inside

  1. The idea What's proposed and why.
  2. Feasibility by area Legal, technical, financial, practical: verdict and conditions.
  3. Overall Feasible, feasible with conditions, or not.

Watch out for

  • Turning it into a full business case.
  • Ignoring legal or practical feasibility.

How this document fits

NeedsProject mandateExpert input
This documentFeasibility studyMade with
FeedsOptions analysisBusiness caseA decision to proceed (or not)
Where you will meet this: Feasibility study · pre-feasibility assessmentPrint the example ↗Print the blank ↗

The document

Day in the RoleFeasibility studyCan it be done? Under what conditions?
Version1.0
Date15 March

The idea

A community health clinic in the empty Riverside warehouse, opening next autumn.

Feasibility by area

Legal
FeasibleConditionsNot feasible

Health licence possible; planning permission for change of use needed

Technical
FeasibleConditionsNot feasible

Building can be converted if a structural survey confirms the roof and floors

Financial
FeasibleConditionsNot feasible

About €4M build, within the capital budget; running costs largely covered by regional funding

Practical
FeasibleConditionsNot feasible

Doctors and nurses can be hired regionally with a 3-month lead time

Overall

FeasibleFeasible with conditionsNot feasible

Conditions:

  • Structural survey before purchase
  • Planning permission for change of use
Sponsor
Signature
Date
Day in the Role · Feasibility studyIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleFeasibility studyCan it be done? Under what conditions?
Version
Date

The idea

Feasibility by area

Legal
FeasibleConditionsNot feasible
Technical
FeasibleConditionsNot feasible
Financial
FeasibleConditionsNot feasible
Practical
FeasibleConditionsNot feasible

Overall

FeasibleFeasible with conditionsNot feasible

Conditions:

Sponsor
Signature
Date
Day in the Role · Feasibility studyTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.