Initiating and governance · document brief

Kick-off meeting pack

The agenda for the project's first meeting with everyone involved, and the record of what was agreed and who does what next.

5 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

everyone involved is meeting for the first time.

Why it matters

It makes sure the first meeting aligns everyone on the goal, scope, roles and ways of working, and that it ends in actions rather than goodwill.

Written by

The project manager

Approved by

Not approved; the notes and actions are shared with everyone who attended

When it appears

At the end of initiating (or the start of planning), once the charter is signed and the team is named.

What goes inside

  1. Meeting details Date, time, place, chair and note-taker.
  2. Attendees Who was there, and who sent apologies.
  3. Agenda Timed items with who leads each.
  4. Decisions What was agreed in the meeting.
  5. Actions What, who, by when.

Watch out for

  • A presentation with no time for questions.
  • No actions with names and dates.
  • Inviting everyone but forgetting key suppliers or the user side.

How this document fits

This documentKick-off meeting packMade with
FeedsRAID logAn aligned team with first actionsCommunication rhythm
Where you will meet this: Kick-off agenda · project start-up meeting notesPrint the example ↗Print the blank ↗

The document

Day in the RoleKick-off meeting packKick-off: agenda and minutes
DateThursday 4 April
Time10:00 to 12:00
PlaceCouncil building, room 2
ChairAnnelise (Project Manager)
Notes byAya (Project Coordinator)
Purpose of the meeting

Start the Riverside Health Centre project together: one goal, clear roles, first actions.

Agenda

10:00
Why this project mattersLed by Atticus (Sponsor)
10:15
Objective, scope and milestonesLed by Annelise (Project Manager)
10:40
Who does what (RACI)Led by Annelise (Project Manager)
11:05
How we work and communicateLed by Aya (Project Coordinator)
11:25
Main risks and assumptionsLed by Annelise (Project Manager)
11:45
Questions and next stepsLed by All

Present

  • Atticus (Sponsor)
  • Amani (Clinical Lead)
  • Abigail (Finance)
  • Aine (IT Lead)
  • Adaugo (HR Lead)
  • Antonia (Compliance Lead)
  • Alfonso (Software Vendor)
  • Azadeh (Community Council)
  • Aya (Project Coordinator)
  • Annelise (Project Manager)

Apologies

  • Arash (contract not yet signed)

Parking lot

  • Hire doctors or nurses first? (Amani (Clinical Lead), Adaugo (HR Lead): resolved 13:30)
  • Pharmacy as a later extension: Azadeh (Community Council)

Decisions

  • Weekly team meeting on Mondays at 09:00; project board monthly
  • Senior doctors and lead nurses hired first, the rest from month 4
  • Purchase delay logged as issue I1

Actions

ActionOwnerDueDone
Re-plan building works for a month 2 purchaseAnnelise (Project Manager)Friday
Book the inspector's design reviewAntonia (Compliance Lead)Next week
First residents' updateAya (Project Coordinator)End of month
Network requirements to the contractorAine (IT Lead)Month 2
Next meetingMonday 8 April, 09:00
Day in the Role · Kick-off meeting packIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleKick-off meeting packKick-off: agenda and minutes
Date
Time
Place
Chair
Notes by
Purpose of the meeting

Agenda

Led by
Led by
Led by
Led by
Led by
Led by
Led by
Led by

Present

Apologies

Parking lot

Decisions

Actions

ActionOwnerDueDone
Next meeting
Day in the Role · Kick-off meeting packTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.