Monitoring and controlling · document brief

Quality audit report

The findings of an independent check on whether the project's processes are followed and work, with corrective actions and a follow-up date.

4 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

someone checks whether the project's processes actually work.

Why it matters

It gives leaders confidence that the project is run properly, and finds process weaknesses before they cause failures.

Written by

The auditor (often the portfolio office)

Approved by

The sponsor; actions agreed with the project manager

When it appears

At planned points or when asked by the sponsor or portfolio office.

What goes inside

  1. Scope What was audited.
  2. Findings Severity and evidence.
  3. Corrective actions Owner and date.
  4. Follow-up When it will be checked.

Watch out for

  • Defending instead of learning.
  • Fixing the instance, not the process.

How this document fits

NeedsProject recordsInterviews
This documentQuality audit reportMade with
FeedsProcess changesLessons log
Where you will meet this: Project assurance report · audit reportPrint the example ↗Print the blank ↗

The document

Day in the RoleQuality audit reportAre the project's processes working?
Version1.0
Date15 March
ScopeChange control, risk management and document control, weeks 14 to 24
AuditorAdeline (Portfolio Manager)

Findings

FindingSeverityEvidence
Approved changes not always reflected in plans (2 of 5)
MajorMinorObservation
CR-05 and CR-07 records
Two risks without review dates
MajorMinorObservation
Risk register
Issue log well used and up to date
MajorMinorObservation
Issue log

Corrective actions (fix the process, not just the instance)

ActionOwnerBy when
Post-approval checklist for every changeAnnelise (Project Manager)This week
Review dates for all risksAya (Project Coordinator)Friday
Follow-up checkRe-check in four weeks
Auditor
Signature
Date
Project manager
Signature
Date
Day in the Role · Quality audit reportIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleQuality audit reportAre the project's processes working?
Version
Date
Scope
Auditor

Findings

FindingSeverityEvidence
MajorMinorObservation
MajorMinorObservation
MajorMinorObservation
MajorMinorObservation
MajorMinorObservation
MajorMinorObservation

Corrective actions (fix the process, not just the instance)

ActionOwnerBy when
Follow-up check
Auditor
Signature
Date
Project manager
Signature
Date
Day in the Role · Quality audit reportTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.