Monitoring and controlling · document briefQuality audit report
The findings of an independent check on whether the project's processes are followed and work, with corrective actions and a follow-up date.
4 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
someone checks whether the project's processes actually work.
Why it matters
It gives leaders confidence that the project is run properly, and finds process weaknesses before they cause failures.
Written by
The auditor (often the portfolio office)
Approved by
The sponsor; actions agreed with the project manager
When it appears
At planned points or when asked by the sponsor or portfolio office.
What goes inside
Scope What was audited.
Findings Severity and evidence.
Corrective actions Owner and date.
Follow-up When it will be checked.
Watch out for
- Defending instead of learning.
- Fixing the instance, not the process.
How this document fits
NeedsProject recordsInterviews
This documentQuality audit reportMade with
The document
Day in the RoleQuality audit reportAre the project's processes working?
ScopeChange control, risk management and document control, weeks 14 to 24
AuditorAdeline (Portfolio Manager)
Findings
| Finding | Severity | Evidence |
|---|
| Approved changes not always reflected in plans (2 of 5) | MajorMinorObservation | CR-05 and CR-07 records |
| Two risks without review dates | MajorMinorObservation | Risk register |
| Issue log well used and up to date | MajorMinorObservation | Issue log |
Corrective actions (fix the process, not just the instance)
| Action | Owner | By when |
|---|
| Post-approval checklist for every change | Annelise (Project Manager) | This week |
| Review dates for all risks | Aya (Project Coordinator) | Friday |
Follow-up checkRe-check in four weeks
Day in the RoleQuality audit reportAre the project's processes working?
Findings
| Finding | Severity | Evidence |
|---|
| MajorMinorObservation | |
| MajorMinorObservation | |
| MajorMinorObservation | |
| MajorMinorObservation | |
| MajorMinorObservation | |
| MajorMinorObservation | |
Corrective actions (fix the process, not just the instance)
Follow-up check
Illustrative example in our own words: not a real project or organisation.