Process improvement · document brief

Phase review checklist

The questions the sponsor checks at the end of each phase of an improvement project, with the evidence and a clear decision: go on, change course, or stop.

5 sections
Used by Process Improvement Specialist
Process improvement

Use it when

a phase of an improvement project ends and the sponsor must decide what next.

Why it matters

It keeps reviews short and honest, makes sure nothing important is skipped, and records the sponsor's decision.

Written by

The project leader prepares it

Approved by

The sponsor decides

When it appears

At the end of every phase: Define, Measure, Analyse, Improve and Control.

What goes inside

  1. Phase Which phase is being reviewed.
  2. Checks Each question, answered yes or no, with the evidence.
  3. Help needed What the team needs from the sponsor.
  4. Decision Go on, change course, or stop, with any conditions.
  5. Sign-off Sponsor.

Watch out for

  • Turning it into a long presentation.
  • Hiding problems to get a “go”.
  • Moving on without a recorded decision.

How this document fits

NeedsImprovement charterThe phase's results
This documentPhase review checklistMade with
FeedsA decision: go on, change course, or stop
Where you will meet this: Tollgate checklist · phase gate review · DMAIC tollgatePrint the example ↗Print the blank ↗

The document

Day in the RolePhase review checklistEnd of phase: checks and decision
Version1.0
Date15 March

Phase

DefineMeasureAnalyseImproveControl
ProjectRoutine appointment access
DateWeek 2, Wednesday

Checks

QuestionYes or noEvidence
Is the problem stated with data, and without causes or solutions?YesCharter: median 10 days, 1 in 4 over 14
Is the goal measurable, with a date?YesMedian 5 days, 90% within 7, in five months
Is the scope clear, with what's out?YesRoutine GP appointments only
Do we know what customers need?YesSurvey, complaints, 14 conversations; three CTQs
Are the team and their time agreed?YesSigned by managers; about 4 hours each a week
Are stakeholders mapped, with a plan?YesStakeholder register
Are benefits estimated, with finance?YesAbout €35,000 a year; method agreed
Any risks to the project?YesWinter demand peak during Improve

Help needed from the sponsor

  • Protected time for the team
  • Access to the booking system data
  • A 30-minute check-in each month

Decision

Go on to the next phaseGo on, with conditionsChange courseStop the project

Go on to Measure. Online booking is kept as an idea to test in Improve if the analysis supports it.

Sponsor
Signature
Date
Day in the Role · Phase review checklistIllustrative example · not a real project or organisation · dayintherole.com
Day in the RolePhase review checklistEnd of phase: checks and decision
Version
Date

Phase

DefineMeasureAnalyseImproveControl
Project
Date

Checks

QuestionYes or noEvidence

Help needed from the sponsor

Decision

Go on to the next phaseGo on, with conditionsChange courseStop the project
Sponsor
Signature
Date
Day in the Role · Phase review checklistTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.