Monitoring and controlling · document brief

Status report

A short, regular report on where the project stands against its baselines: overall status, progress, performance figures, top risks and issues, and decisions needed.

5 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

leaders need a regular, honest picture against the plan.

Why it matters

It gives the sponsor and board an honest, comparable picture so they can help early, and it records progress over time.

Written by

The project manager

Approved by

Not approved; sent to the sponsor and board

When it appears

At the rhythm in the communication plan, usually weekly or monthly, throughout executing and monitoring.

What goes inside

  1. Overall status Colour per area with the reason.
  2. Performance Planned value, earned value, actual cost and the indices.
  3. Done and next This period and the next.
  4. Top risks and issues The few that matter most.
  5. Decisions needed From the reader.

Watch out for

  • Green on the outside, red inside.
  • Too long to read.
  • No decisions asked for, so leaders can't help.

How this document fits

This documentStatus reportMade with
FeedsBoard decisionsexception-report (if beyond tolerance)End-stage report
Where you will meet this: Status report · highlight report (PRINCE2) · work performance report · project dashboardPrint the example ↗Print the blank ↗

The document

Day in the RoleStatus reportWhere we are against the baselines
Version1.0
Date15 March
Reporting periodMonth 4 (weeks 14 to 17)
OverallRAG
Why

Two weeks behind on building works with a recovery plan; booking tests at 50%.

Status by area

AreaStatusWhy
ScopeRAGNo unapproved changes
TimeRAGBuilding works 2 weeks behind; recovery plan agreed
CostRAGCPI 0.98; forecast inside baseline
QualityRAGVentilation defect fixed; booking tests at 50% pass
RiskRAGLicence inspection not yet booked

Green: on plan. Amber: off plan, recoverable within tolerance, with a plan. Red: beyond tolerance or needs a decision.

Performance (€ thousands)

PVPlanned value2,400
EVEarned value2,200
ACActual cost2,250
SPIEV ÷ PV0.92
CPIEV ÷ AC0.98

SPI or CPI below 1 means behind schedule or over cost.

Done this period

  • Asbestos removed and certified
  • Structure repaired
  • 9 clinical staff hired

Next period

  • Treatment room fit-out
  • Booking system test cycle 2
  • Book licence inspection

Top risks and issues

  • Booking system tests failing (recovery plan Friday)
  • Building works recovery
  • Licence inspection backlog
Decisions needed from you

None this week. A possible exception on the booking system next week.

Day in the Role · Status reportIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleStatus reportWhere we are against the baselines
Version
Date
Reporting period
OverallRAG
Why

Status by area

AreaStatusWhy
ScopeRAG
TimeRAG
CostRAG
QualityRAG
RiskRAG

Green: on plan. Amber: off plan, recoverable within tolerance, with a plan. Red: beyond tolerance or needs a decision.

Performance (€ thousands)

PVPlanned value
EVEarned value
ACActual cost
SPIEV ÷ PV
CPIEV ÷ AC

SPI or CPI below 1 means behind schedule or over cost.

Done this period

Next period

Top risks and issues

Decisions needed from you
Day in the Role · Status reportTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.

See it in the story

In the Project Manager story

Related documents