Closing · document brief Project closure report The final report that compares what the project delivered with what was approved, lists what's still open, confirms benefits are handed over and asks the board to close the project.
5 sections Used by Project Manager
Pre-project Initiating Planning Executing Monitoring Closing
Use it when a project ends, or stops, and must be closed formally.
Why it matters It gives a clear, final account of the project and makes closure a formal decision rather than a fade-out.
Written by The project manager
Approved by The project board formally closes the project
When it appears At the very end of the project, after handover and contract closure.
What goes inside Objectives and results What was promised and what happened.
Baselines and actuals Scope, time, cost.
Open items With owners after closure.
Funds Spent and returned.
Closure Board approval.
Watch out for Closing by email. Open items with no owner. Hiding variances. How this document fits
This document Project closure report Made with
Feeds Formal project closure Archived records benefits-review (after the project)
What the letters mean
GP General practitioner: a family doctor
IT Information technology
PRINCE2 Projects in Controlled Environments: a project management method
R · A · G Red, amber, green: status lights
€M Millions of euros (€4.2M = €4,200,000)
The document Filled-in example Blank template
Day in the Role Project closure report The final account of the project
Objectives and results Objective Result Status Clinic open in month 7 Yes: opened week 30 R A G Care within 15 minutes for Riverside Yes: 12 minutes on average R A G GP waiting under 1 week within a year On the way: 1.5 weeks; reviewed at month 12 R A G
Baselines and actuals Cost (€M) Baseline 4.2
Actual 4.16
Time (weeks) Baseline 30
Actual 30
Scope 6 deliverables plus 4 approved changes; online booking 4 weeks after opening
Funds Approved funding € 4,500,000
Spent € 4,160,000
Returned € 340,000
Open items after closure Item Owner and date Online booking go-live IT, week 4 after opening Retention release Procurement, month 6 Benefits reviews Atticus (Sponsor), months 6 and 12
Board closure The board confirms the project is complete and formally closed. Records are archived.
Day in the Role Project closure report The final account of the project
Objectives and results Objective Result Status R A G R A G R A G
Funds Approved funding €
Spent €
Returned €
Board closure The board confirms the project is complete and formally closed. Records are archived.
Illustrative example in our own words: not a real project or organisation.