Process improvement · document brief

Gemba walk notes

Notes from following one patient, order or form through a process: every step, how long it took, how long it waited, and what was seen.

4 sections
Used by Process Improvement Specialist
Process improvement

Use it when

you follow one item through a process and need to record what really happens.

Why it matters

It captures the real process, as it happens, so the team can see where time is lost and discuss facts instead of opinions.

Written by

Whoever does the walk, usually the improvement specialist with someone who does the work

Approved by

Not approved; shared with the people who were observed

When it appears

At the start of an improvement, and again after changes, to compare. Written on the spot during the walk.

What goes inside

  1. What we followed The process, the item followed, the date and time.
  2. Steps and waits One row per step or wait, in order.
  3. Totals Work time, wait time and total time.
  4. Questions to follow up What we want to ask the team.

Watch out for

  • Writing opinions instead of what was seen.
  • Naming or blaming individuals.
  • Following the process on a quiet day only.

How this document fits

NeedsPermission and a time agreed with the teamA simple floor plan
This documentGemba walk notesMade with
FeedsImprovement opportunity logProcess map (Measure)
Where you will meet this: Gemba walk record · process observation sheet · waste walk notesPrint the example ↗Print the blank ↗

The document

Day in the RoleGemba walk notesFollowing one item through the process
ProcessRoutine appointment with a blood test
Item followedOne patient, with her permission
WhenTuesday, 10:00
ObserversAmara (Process Improvement Specialist), Ayumi (Healthcare Assistant)

Steps and waits

TimeStep or placeWork timeWait before next stepWhat we sawKind of waste
10:00Check-in at reception4 min22 minQueue of 6; screen shows no wait timesWaiting
10:26Consultation with the GP9 minGP asks for a blood test
10:35Back to reception to book the blood test3 min15 minPatient walks back past the waiting roomMovement
10:53Blood taken by Ayumi (Healthcare Assistant)5 min36 minForm waits for a GP signatureWaiting
11:34Form signed, patient leavesPatient asks when results will comeFailure demand
Work time21 min
Wait time73 min
Total time94 min

Questions to follow up

  • Why does a blood test need a second trip to reception?
  • Why does the form wait for a signature after the blood is taken?
  • How do patients find out when results are back?

Write what you see, not opinions. Look at the process, never at who is slow. Kinds of waste: waiting, extra processing, movement, transport, rework, overproduction, excess stock, unused talent, failure demand.

Day in the Role · Gemba walk notesIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleGemba walk notesFollowing one item through the process
Process
Item followed
When
Observers

Steps and waits

TimeStep or placeWork timeWait before next stepWhat we sawKind of waste
Work time
Wait time
Total time

Questions to follow up

Write what you see, not opinions. Look at the process, never at who is slow. Kinds of waste: waiting, extra processing, movement, transport, rework, overproduction, excess stock, unused talent, failure demand.

Day in the Role · Gemba walk notesTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.