RACI chart

A grid of deliverables or decisions against people, showing who does the work, who owns the result, who is asked and who is told.

3 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

several people and suppliers share deliverables and ownership must be clear.

Why it matters

It removes the “I thought you were doing that” moments. Everyone sees their part, and each item has exactly one person accountable for it.

Written by

The project manager, agreed with the people named in it

Approved by

The sponsor or project board, for the main lines

When it appears

In initiating, once the main deliverables and people are known. Revisited when people or deliverables change.

What goes inside

  1. Deliverables or decisions One per row: the main pieces of work and the decisions that matter.
  2. People or roles One per column.
  3. Assignments R, A, C or I in each cell. One A per row.

Watch out for

  • Two A's on one row, or none.
  • Everyone consulted on everything: decisions slow down.
  • Filling it in alone, without the people named in it.

How this document fits

NeedsProject charterStakeholder registerThe main deliverables
This documentRACI chartMade with
FeedsKick-off meeting packTeam roles and responsibilitiesResource plan
Where you will meet this: Responsibility assignment matrix (RAM) · RACI chart · RASCIPrint the example ↗Print the blank ↗

The document

Day in the RoleRACI chartWho does what, who owns it
Version1.0
Date15 March
RResponsible: does the work
AAccountable: owns the result. Exactly one per row
CConsulted: asked before
IInformed: told after
Deliverable or decisionAtticus (Sponsor)Annelise (Project Manager)Amani (Clinical Lead)Aine (IT Lead)Adaugo (HR Lead)Antonia (Compliance Lead)Alfonso (Software Vendor)Abigail (Finance)One A?
Building designARCCCI✓
Building worksIAICCI✓
Equipment purchaseIACCR✓
Booking system setupICAR✓
Hiring and trainingICARI✓
Licence applicationICCR✗
Opening dateARCIICII✓
Spending above €25kARC✓

Write a person's name at the top of each column. Check that each row has one A, and that no column is overloaded with R's.

Gaps and follow-ups

Licence application: Antonia (Compliance Lead) is responsible, but nobody is accountable yet. Atticus (Sponsor) to decide by Friday.

Agreed by the sponsor
Signature
Date
Day in the Role · RACI chartIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleRACI chartWho does what, who owns it
Version
Date
RResponsible: does the work
AAccountable: owns the result. Exactly one per row
CConsulted: asked before
IInformed: told after
Deliverable or decisionOne A?

Write a person's name at the top of each column. Check that each row has one A, and that no column is overloaded with R's.

Gaps and follow-ups

Agreed by the sponsor
Signature
Date
Day in the Role · RACI chartTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.

See it in the story

In the Project Manager story

Related documents

← All documents and templates