Planning · document briefRisk register
The detailed list of identified risks, each with its likelihood, impact, score, owner and response, including opportunities.
3 sections
Used by Process Improvement Specialist, Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
risks need scores, owners and responses in one place.
Why it matters
It turns worries into managed items: ranked, owned and acted on before they happen.
Written by
The project manager; each risk has its own owner
Approved by
Reviewed by the project board
When it appears
Started in initiating (often inside a RAID log), analysed in depth during planning, reviewed every week until closing.
What goes inside
Scales What each likelihood and impact score means.
Risks Cause, event, effect; scores; owner.
Responses Strategy and actions per risk.
Watch out for
- Scores without agreed definitions.
- Only threats, no opportunities.
- Responses with no owner or no date.
How this document fits
This documentRisk registerMade with
The document
Day in the RoleRisk registerRanked risks and opportunities, with responses
Scoring scales
| Score | Likelihood | Impact (time or cost) |
|---|
| 5 | Over 70% | Over 1 month late or over €150k |
|---|
| 4 | 50 to 70% | 2 to 4 weeks or €75k to €150k |
|---|
| 3 | 30 to 50% | 1 to 2 weeks or €25k to €75k |
|---|
| 2 | 10 to 30% | Under 1 week or under €25k |
|---|
| 1 | Under 10% | Hardly noticeable |
|---|
Agree your own scales with the team before scoring. Score = likelihood × impact.
Register
| ID | Risk or opportunity | L | I | Score | Owner | Strategy | Response actions |
|---|
| R1 | Equipment takes 14 weeks; opening could slip | 4 | 3 | 12 | Aya (Project Coordinator) | Reduce | Order early with cancellation clause |
| R2 | Old structure needs more repair; costs rise | 3 | 4 | 12 | Annelise (Project Manager) | Reduce | Survey done; contingency €150k |
| R3 | Not enough nurses hired in time | 3 | 4 | 12 | Adaugo (HR Lead) | Reduce | Start hiring month 3; agency backup |
| R4 | Equipment prices rise 15% before ordering | 4 | 3 | 12 | Alder (Procurement) | Transfer | Fixed-price contract signed now |
| R5 | Licence refused over ventilation | 2 | 5 | 10 | Antonia (Compliance Lead) | Reduce | Inspector reviews design in month 2 |
| R6 | Opportunity: digital health grant pays €80k | 3 | 2 | 6 | Aine (IT Lead) | Enhance | Application by week 6 |
Strategies for threats: avoid · transfer · reduce · accept. For opportunities: exploit · enhance · share · accept.
Day in the RoleRisk registerRanked risks and opportunities, with responses
Scoring scales
| Score | Likelihood | Impact (time or cost) |
|---|
| 5 | Over 70% | Over 1 month late or over €150k |
|---|
| 4 | 50 to 70% | 2 to 4 weeks or €75k to €150k |
|---|
| 3 | 30 to 50% | 1 to 2 weeks or €25k to €75k |
|---|
| 2 | 10 to 30% | Under 1 week or under €25k |
|---|
| 1 | Under 10% | Hardly noticeable |
|---|
Agree your own scales with the team before scoring. Score = likelihood × impact.
Register
| ID | Risk or opportunity | L | I | Score | Owner | Strategy | Response actions |
|---|
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
Strategies for threats: avoid · transfer · reduce · accept. For opportunities: exploit · enhance · share · accept.
Illustrative example in our own words: not a real project or organisation.