Planning · document brief

Risk register

The detailed list of identified risks, each with its likelihood, impact, score, owner and response, including opportunities.

3 sections
Used by Process Improvement Specialist, Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

risks need scores, owners and responses in one place.

Why it matters

It turns worries into managed items: ranked, owned and acted on before they happen.

Written by

The project manager; each risk has its own owner

Approved by

Reviewed by the project board

When it appears

Started in initiating (often inside a RAID log), analysed in depth during planning, reviewed every week until closing.

What goes inside

  1. Scales What each likelihood and impact score means.
  2. Risks Cause, event, effect; scores; owner.
  3. Responses Strategy and actions per risk.

Watch out for

  • Scores without agreed definitions.
  • Only threats, no opportunities.
  • Responses with no owner or no date.

How this document fits

NeedsRAID logWork breakdown structureRisk workshopLessons from past projects
FeedsCost baselineProject scheduleRisk reviews at every board meeting
Where you will meet this: Risk register (PMI and PRINCE2) · risk logPrint the example ↗Print the blank ↗

The document

Day in the RoleRisk registerRanked risks and opportunities, with responses
Version1.0
Date15 March

Heat map

Likelihood →
5
4
R1 R4
3
R6
R2 R3
2
R5
1
12345
Impact →

Scoring scales

ScoreLikelihoodImpact (time or cost)
5Over 70%Over 1 month late or over €150k
450 to 70%2 to 4 weeks or €75k to €150k
330 to 50%1 to 2 weeks or €25k to €75k
210 to 30%Under 1 week or under €25k
1Under 10%Hardly noticeable

Agree your own scales with the team before scoring. Score = likelihood × impact.

Register

IDRisk or oppor­tunityLIScoreOwnerStrategyResponse actions
R1Equipment takes 14 weeks; opening could slip4312Aya (Project Coordinator)ReduceOrder early with cancellation clause
R2Old structure needs more repair; costs rise3412Annelise (Project Manager)ReduceSurvey done; contingency €150k
R3Not enough nurses hired in time3412Adaugo (HR Lead)ReduceStart hiring month 3; agency backup
R4Equipment prices rise 15% before ordering4312Alder (Procurement)TransferFixed-price contract signed now
R5Licence refused over ventilation2510Antonia (Compliance Lead)ReduceInspector reviews design in month 2
R6Opportunity: digital health grant pays €80k326Aine (IT Lead)EnhanceApplication by week 6

Strategies for threats: avoid · transfer · reduce · accept. For opportunities: exploit · enhance · share · accept.

Day in the Role · Risk registerIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleRisk registerRanked risks and opportunities, with responses
Version
Date

Heat map

Likelihood →
5
4
3
2
1
12345
Impact →

Scoring scales

ScoreLikelihoodImpact (time or cost)
5Over 70%Over 1 month late or over €150k
450 to 70%2 to 4 weeks or €75k to €150k
330 to 50%1 to 2 weeks or €25k to €75k
210 to 30%Under 1 week or under €25k
1Under 10%Hardly noticeable

Agree your own scales with the team before scoring. Score = likelihood × impact.

Register

IDRisk or oppor­tunityLIScoreOwnerStrategyResponse actions

Strategies for threats: avoid · transfer · reduce · accept. For opportunities: exploit · enhance · share · accept.

Day in the Role · Risk registerTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.

See it in the story

In the Process Improvement Specialist story

In the Project Manager story