Closing · document brief Handover certificate The record that the project's result has been handed over to the people who will run it, with what was transferred, what's still open and how support works.
5 sections Used by Project Manager
Pre-project Initiating Planning Executing Monitoring Closing
Use it when the result passes from the project to the people who'll run it.
Why it matters It marks the moment ownership changes, so it's clear who fixes problems, holds documents and owns the benefits from then on.
Written by The project manager
Approved by Signed by the operations owner and the project manager
When it appears At go-live or shortly after, once the operations team is ready to take ownership.
What goes inside What is handed over Deliverables and the date.
Transferred Documents, warranties, training, access.
Open items With owners and dates.
Support How long the project still helps, and how.
Signatures Both sides.
Watch out for A verbal handover. Waiting for perfection before handing over. Benefits left without an owner. How this document fits
This document Handover certificate Made with
What the letters mean
IT Information technology
The document Filled-in example Blank template
Day in the Role Handover certificate From project to operations
What is handed over Riverside Health Centre: building, equipment, booking system and team
Date Opening day, week 30
From the project Annelise (Project Manager)
→ To operations Amani (Clinical Lead)
Transferred Building manuals and warranties
Equipment certificates
Booking system admin access and guide
Training records
Licence
Supplier contacts
Benefits management plan
Still open, with new owners Open item Owner By when Online booking go-live IT (Aine (IT Lead)'s successor) Week 4 after opening Paint touch-ups, corridor Arash (Contractor) Week 31
Support after handover Four weeks of joint support: project team on site Mondays and Thursdays, same-day response to issues. Ends in week 34.
From the date above, the operations owner is responsible for running the result and for the benefits plan.
Day in the Role Handover certificate From project to operations
Date
From the project
→ To operations
Still open, with new owners From the date above, the operations owner is responsible for running the result and for the benefits plan.
Illustrative example in our own words: not a real project or organisation.