Handover certificate

The record that the project's result has been handed over to the people who will run it, with what was transferred, what's still open and how support works.

5 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

the result passes from the project to the people who'll run it.

Why it matters

It marks the moment ownership changes, so it's clear who fixes problems, holds documents and owns the benefits from then on.

Written by

The project manager

Approved by

Signed by the operations owner and the project manager

When it appears

At go-live or shortly after, once the operations team is ready to take ownership.

What goes inside

  1. What is handed over Deliverables and the date.
  2. Transferred Documents, warranties, training, access.
  3. Open items With owners and dates.
  4. Support How long the project still helps, and how.
  5. Signatures Both sides.

Watch out for

  • A verbal handover.
  • Waiting for perfection before handing over.
  • Benefits left without an owner.

How this document fits

This documentHandover certificateMade with
Where you will meet this: Handover to operations · transition document · operational acceptancePrint the example ↗Print the blank ↗

The document

Day in the RoleHandover certificateFrom project to operations
Version1.0
Date15 March
What is handed over
Riverside Health Centre: building, equipment, booking system and team
DateOpening day, week 30
From the projectAnnelise (Project Manager)
→
To operationsAmani (Clinical Lead)

Transferred

Building manuals and warranties
Equipment certificates
Booking system admin access and guide
Training records
Licence
Supplier contacts
Benefits management plan

Still open, with new owners

Open itemOwnerBy when
Online booking go-liveIT (Aine (IT Lead)'s successor)Week 4 after opening
Paint touch-ups, corridorArash (Contractor)Week 31

Support after handover

Four weeks of joint support: project team on site Mondays and Thursdays, same-day response to issues. Ends in week 34.

From the date above, the operations owner is responsible for running the result and for the benefits plan.

Project manager
Signature
Date
Operations owner
Signature
Date
Day in the Role · Handover certificateIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleHandover certificateFrom project to operations
Version
Date
What is handed over
Date
From the project
→
To operations

Transferred

Still open, with new owners

Open itemOwnerBy when

Support after handover

From the date above, the operations owner is responsible for running the result and for the benefits plan.

Project manager
Signature
Date
Operations owner
Signature
Date
Day in the Role · Handover certificateTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.