Executing · document briefSprint Review notes
A short record of what an agile team showed at a review, the feedback from stakeholders and users, and what changed in the plan as a result.
3 sections
Used by Scrum Master, Product Owner, Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
an agile supplier shows work and the feedback must not be lost.
Why it matters
It connects agile progress to the rest of the project and keeps feedback from being lost.
Written by
The supplier's Product Owner or the project coordinator
Approved by
Not approved; shared with the project team
When it appears
After each Sprint Review in agile parts of a project.
What goes inside
Sprint goal What the Sprint aimed for.
Shown Features, and whether they meet the need.
Changes to the backlog What moved and why.
Watch out for
- Notes with no decisions.
- Feedback sent straight to developers instead of the backlog owner.
How this document fits
NeedsThe Sprint's resultsUser feedback
This documentSprint Review notesMade with
The document
Day in the RoleSprint Review notesWhat we saw, what we said, what changes
Sprint goalReceptionists can book, move and cancel appointments by phone.
What was shown
| Shown | Works for users? | Feedback |
|---|
| Book an appointment | YesNeeds work | Fast and clear |
| Move an appointment | YesNeeds work | Works |
| Cancel an appointment | YesNeeds work | Works |
| Book a follow-up | YesNeeds work | Takes six clicks; needs to be one |
Who took part
Amani (Clinical Lead), two receptionists, Annelise (Project Manager), Alfonso (Software Vendor), Ananya (Vendor Development Lead)
Changes to the backlog (decided by its owner)
- One-click follow-up moved to the top of the backlog
- SMS reminders moved earlier
- Reporting screens moved later
Day in the RoleSprint Review notesWhat we saw, what we said, what changes
What was shown
| Shown | Works for users? | Feedback |
|---|
| YesNeeds work | |
| YesNeeds work | |
| YesNeeds work | |
| YesNeeds work | |
| YesNeeds work | |
| YesNeeds work | |
| YesNeeds work | |
| YesNeeds work | |
Changes to the backlog (decided by its owner)
Illustrative example in our own words: not a real project or organisation.