Monitoring and controlling · document briefException report
The report a project manager sends when a forecast goes beyond an agreed tolerance: what happened, the impact, the options and a recommendation.
6 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
a forecast goes beyond an agreed tolerance.
Why it matters
It gets the decision to the people with the authority to make it, quickly, with everything they need to decide.
Written by
The project manager
Approved by
The sponsor or board decide on the options
When it appears
As soon as a forecast breaks a tolerance on time, cost, scope, quality, risk or benefits.
What goes inside
What happened The cause.
Tolerance and forecast The limit and what's now forecast.
Impact On the plan, the business case and risks.
Options Each with cost, time and risk.
Recommendation Your preferred option and why.
Decision What the board decided.
Watch out for
- Waiting to see if it gets better.
- A problem without options.
- Using it to assign blame.
How this document fits
This documentException reportMade with FeedsBoard decisionUpdated plan (exception plan)Lessons log
The document
Day in the RoleException reportA tolerance will be exceeded: options for the board
ExceptionA forecast is beyond tolerance. The board must decide.
ReferenceEX-01
DateWeek 23
AreaTime (online booking)
What happened
The council's patient records system needs a security upgrade before the booking system can connect. Integration will be three weeks late.
Tolerance and forecast
Time (weeks)-2+2
+3 weeks for online booking Cost (€ thousands)-25+25
Within tolerance: about +€10k against the stage plan Shaded band: agreed tolerance. Marker: current forecast.
Impact
Online booking not ready for opening in week 30. Online users' benefits start later. No effect on the building or licence.
Options
| Option | Cost | Time | Risk |
|---|
| A. Open with phone booking; online from week 4 after opening | €0 | On time | Low |
| B. Delay opening by 3 weeks | €0 | +3 weeks | Public promise broken |
| C. Pay for an extra vendor team | €40,000 | May still slip | Medium |
Recommendation
ABC
WhyOpens on time at no cost; phone booking was already planned as the back-up.
Board decision
Approved option A
Day in the RoleException reportA tolerance will be exceeded: options for the board
ExceptionA forecast is beyond tolerance. The board must decide.
Tolerance and forecast
Time
Mark the tolerance band and the forecast Cost
Mark the tolerance band and the forecast Shaded band: agreed tolerance. Marker: current forecast.
Illustrative example in our own words: not a real project or organisation.