Monitoring and controlling · document brief

Exception report

The report a project manager sends when a forecast goes beyond an agreed tolerance: what happened, the impact, the options and a recommendation.

6 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

a forecast goes beyond an agreed tolerance.

Why it matters

It gets the decision to the people with the authority to make it, quickly, with everything they need to decide.

Written by

The project manager

Approved by

The sponsor or board decide on the options

When it appears

As soon as a forecast breaks a tolerance on time, cost, scope, quality, risk or benefits.

What goes inside

  1. What happened The cause.
  2. Tolerance and forecast The limit and what's now forecast.
  3. Impact On the plan, the business case and risks.
  4. Options Each with cost, time and risk.
  5. Recommendation Your preferred option and why.
  6. Decision What the board decided.

Watch out for

  • Waiting to see if it gets better.
  • A problem without options.
  • Using it to assign blame.

How this document fits

This documentException reportMade with
FeedsBoard decisionUpdated plan (exception plan)Lessons log
Where you will meet this: Exception report (PRINCE2) · escalation report · variance reportPrint the example ↗Print the blank ↗

The document

Day in the RoleException reportA tolerance will be exceeded: options for the board
Version1.0
Date15 March
ExceptionA forecast is beyond tolerance. The board must decide.
ReferenceEX-01
DateWeek 23
AreaTime (online booking)

What happened

The council's patient records system needs a security upgrade before the booking system can connect. Integration will be three weeks late.

Tolerance and forecast

Time (weeks)
-2+2
+3 weeks for online booking
Cost (€ thousands)
-25+25
Within tolerance: about +€10k against the stage plan

Shaded band: agreed tolerance. Marker: current forecast.

Impact

Online booking not ready for opening in week 30. Online users' benefits start later. No effect on the building or licence.

Options

OptionCostTimeRisk
A. Open with phone booking; online from week 4 after opening€0On timeLow
B. Delay opening by 3 weeks€0+3 weeksPublic promise broken
C. Pay for an extra vendor team€40,000May still slipMedium

Recommendation

ABC
Why
Opens on time at no cost; phone booking was already planned as the back-up.

Board decision

Approved option A

Sponsor
Signature
Date
Day in the Role · Exception reportIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleException reportA tolerance will be exceeded: options for the board
Version
Date
ExceptionA forecast is beyond tolerance. The board must decide.
Reference
Date
Area

What happened

Tolerance and forecast

Time
Mark the tolerance band and the forecast
Cost
Mark the tolerance band and the forecast

Shaded band: agreed tolerance. Marker: current forecast.

Impact

Options

OptionCostTimeRisk

Recommendation

ABC
Why

Board decision

Sponsor
Signature
Date
Day in the Role · Exception reportTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.