Process improvement · document brief

Data collection plan

A plan that says, for every measure, exactly what it means, what type of data it is, where it comes from, how much is collected, by whom and when.

3 sections
Used by Process Improvement Specialist
Process improvement

Use it when

a team is about to collect data and must agree exactly what and how much.

Why it matters

It makes sure the team collects the right data, the same way, in the right amount, before anyone analyses anything.

Written by

The project leader, with the data analyst

Approved by

Agreed with the process owner

When it appears

In the Measure phase, before collecting data. Updated if a new measure is added in Analyse.

What goes inside

  1. Measures One row per measure: the result (Y) and the possible causes (X) to check.
  2. Sampling How records are chosen, and why that many.
  3. How the data is checked Measurement checks planned.

Watch out for

  • Measures without an exact definition.
  • Collecting only what's easy to get.
  • No measurement check before analysis.

How this document fits

NeedsImprovement charterCause-and-effect matrix
FeedsMeasurement system studyBaseline data
Where you will meet this: Data collection plan · measurement plan · operational definitionsPrint the example ↗Print the blank ↗

The document

Day in the RoleData collection planWhat we measure, exactly, and how much
Version1.0
Date15 March

Y = the result the customer feels. X = a possible cause. Write each definition so two people would get the same number.

MeasureY or XOperational definitionData typeSourceHow manyWhoWhen
Waiting timeYFirst request, by any route, to the date of the appointment offered; calendar daysContinuousBooking system and call log60 random, weeks 12 to 20Astrid (Data Analyst)Week 3
Date on first contactYPatient offered a date during their first request; yes or noDiscrete (yes or no)Reception tally sheetEvery request for 2 weeksAlma (Reception Team Lead)Weeks 3 and 4
Slot release timeXTime each routine slot became bookableContinuousBooking system logAll slots, 4 weeksAstrid (Data Analyst)Week 3
Urgent use of routine slotsXRoutine slot used for an urgent case, by the agreed guideDiscrete (yes or no)Booking recordsAll bookings, 4 weeksAstrid (Data Analyst)Week 4
Doctor sessions a weekXBookable routine sessions per week, all doctorsCountRota20 weeksAurelie (Practice Nurse Manager)Week 3
Missed appointmentsXBooked appointment not attended, no cancellationDiscrete (yes or no)Booking system20 weeksAstrid (Data Analyst)Week 3

Sampling: how records are chosen, and why that many

Waiting time: 60 requests chosen at random from weeks 12 to 20 (at least 41 needed for ±2 days). Yes-or-no measures: every request, because each record holds less information.

How the data is checked

Attribute agreement on urgent or routine before using that split. Gauge study on stopwatch call timing.

Day in the Role · Data collection planIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleData collection planWhat we measure, exactly, and how much
Version
Date

Y = the result the customer feels. X = a possible cause. Write each definition so two people would get the same number.

MeasureY or XOperational definitionData typeSourceHow manyWhoWhen

Sampling: how records are chosen, and why that many

How the data is checked

Day in the Role · Data collection planTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.