Delivery approach and tailoring

Records how each part of the project will be delivered (predictive, agile or hybrid) and which of the organisation's standard documents and controls the project uses.

3 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

you're deciding predictive, agile or hybrid, and how much process to use.

Why it matters

It makes the choice of approach deliberate and explained, and agrees the right amount of process with the people who own the standards.

Written by

The project manager

Approved by

The sponsor and the portfolio office

When it appears

In initiating, reviewed at stage ends.

What goes inside

  1. Approach per part Part, approach and why.
  2. Tailored standards Documents and controls kept, combined or dropped.
  3. Agreed Sponsor and portfolio office.

Watch out for

  • One approach forced on everything.
  • Dropping controls without recording why.

How this document fits

NeedsProject charterOrganisation's project standards
This documentDelivery approach and tailoringMade with
Where you will meet this: Development approach · tailoring decision · project approach (PRINCE2)Print the example ↗Print the blank ↗

The document

Day in the RoleDelivery approach and tailoringPredictive, agile or hybrid, and the right amount of process
Version1.0
Date15 March

Approach per part

Part of the workRequirements clear?Cost of late changeNeed for user feedbackApproach
Building worksLMHLMHLMH
PredictiveAgileHybrid
Booking systemLMHLMHLMH
PredictiveAgileHybrid
Hiring and trainingLMHLMHLMH
PredictiveAgileHybrid
LicenceLMHLMHLMH
PredictiveAgileHybrid

Clear requirements and costly change point to predictive; a strong need for user feedback points to agile. Mixed parts make the project hybrid.

Tailoring the organisation's standards

Standard document or controlKept, combined or droppedWhy
Risk register, issue logCombinedOne RAID log is enough for this size
Benefits planKeptBenefits continue after closure
Software design documentDroppedVendor's own; the backlog serves us
Weekly highlight reportKeptSponsor's preferred update
Sponsor
Signature
Date
Portfolio office
Signature
Date
Day in the Role · Delivery approach and tailoringIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleDelivery approach and tailoringPredictive, agile or hybrid, and the right amount of process
Version
Date

Approach per part

Part of the workRequirements clear?Cost of late changeNeed for user feedbackApproach
LMHLMHLMH
PredictiveAgileHybrid
LMHLMHLMH
PredictiveAgileHybrid
LMHLMHLMH
PredictiveAgileHybrid
LMHLMHLMH
PredictiveAgileHybrid
LMHLMHLMH
PredictiveAgileHybrid
LMHLMHLMH
PredictiveAgileHybrid

Clear requirements and costly change point to predictive; a strong need for user feedback points to agile. Mixed parts make the project hybrid.

Tailoring the organisation's standards

Standard document or controlKept, combined or droppedWhy
Sponsor
Signature
Date
Portfolio office
Signature
Date
Day in the Role · Delivery approach and tailoringTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.