Initiating and governance · document brief Delivery approach and tailoring Records how each part of the project will be delivered (predictive, agile or hybrid) and which of the organisation's standard documents and controls the project uses.
3 sections Used by Project Manager
Pre-project Initiating Planning Executing Monitoring Closing
Use it when you're deciding predictive, agile or hybrid, and how much process to use.
Why it matters It makes the choice of approach deliberate and explained, and agrees the right amount of process with the people who own the standards.
Written by The project manager
Approved by The sponsor and the portfolio office
When it appears In initiating, reviewed at stage ends.
What goes inside Approach per part Part, approach and why.
Tailored standards Documents and controls kept, combined or dropped.
Agreed Sponsor and portfolio office.
Watch out for One approach forced on everything. Dropping controls without recording why. How this document fits
This document Delivery approach and tailoring Made with
What the letters mean
RAID Risks, Assumptions, Issues, Dependencies
PRINCE2 Projects in Controlled Environments: a project management method
The document Filled-in example Blank template
Day in the Role Delivery approach and tailoring Predictive, agile or hybrid, and the right amount of process
Approach per part Part of the work Requirements clear? Cost of late change Need for user feedback Approach Building works L M H L M H L M H Predictive Agile Hybrid
Booking system L M H L M H L M H Predictive Agile Hybrid
Hiring and training L M H L M H L M H Predictive Agile Hybrid
Licence L M H L M H L M H Predictive Agile Hybrid
Clear requirements and costly change point to predictive; a strong need for user feedback points to agile. Mixed parts make the project hybrid.
Tailoring the organisation's standards Standard document or control Kept, combined or dropped Why Risk register, issue log Combined One RAID log is enough for this size Benefits plan Kept Benefits continue after closure Software design document Dropped Vendor's own; the backlog serves us Weekly highlight report Kept Sponsor's preferred update
Day in the Role Delivery approach and tailoring Predictive, agile or hybrid, and the right amount of process
Approach per part Part of the work Requirements clear? Cost of late change Need for user feedback Approach L M H L M H L M H Predictive Agile Hybrid
L M H L M H L M H Predictive Agile Hybrid
L M H L M H L M H Predictive Agile Hybrid
L M H L M H L M H Predictive Agile Hybrid
L M H L M H L M H Predictive Agile Hybrid
L M H L M H L M H Predictive Agile Hybrid
Clear requirements and costly change point to predictive; a strong need for user feedback points to agile. Mixed parts make the project hybrid.
Tailoring the organisation's standards Standard document or control Kept, combined or dropped Why
Illustrative example in our own words: not a real project or organisation.