One page that sets up an improvement project: the problem, the goal, the scope, what customers need, the team, the plan and the expected benefits, signed by the sponsor.
8 sections Used by Process Improvement Specialist
Process improvement
Use it when
an improvement project starts and everyone must agree its problem, goal and edges.
Why it matters
It makes sure the sponsor, the process owner and the team agree what the project is for and where its edges are, before any analysis starts.
Written by
The project leader, with the team
Approved by
The sponsor signs it; the process owner agrees it
When it appears
Written in the Define phase and signed at its review. Updated whenever the project learns something that changes it, and checked at every phase review.
What goes inside
Problem statementWhat, where, since when, how big, and the impact. No causes or solutions.
GoalWhat will change, by how much, by when, measured how.
ScopeIn scope, out of scope, where the process starts and ends.
What customers needThe critical-to-quality requirements, with targets.
Team and rolesSponsor, process owner, project leader, mentor, team members and their time.
PlanEach phase and the date of its review.
Expected benefitsCash and non-cash, and how they'll be counted.
Over the last 20 weeks, patients asking for a routine GP appointment at the Riverside Health Centre waited a median of 10 days, and 1 in 4 waited more than 14. The target is under 7. About 1,900 appointments a year are missed, patients call repeatedly, and some go to the emergency department instead.
Goal
Median wait of 5 working days or less, and 9 in 10 patients offered an appointment within 7 days, within five months. Measured weekly from booking data.
In scope
Routine GP appointments
From first request (phone, online or in person) to appointment offered
All five GPs
Out of scope
Urgent same-day appointments (watched for side effects)
Nurse appointments
Home visits
What customers need (critical to quality)
Requirement
Target
Measured how
Appointment within 7 days
90%
Booking data, weekly
Date offered on first contact
95%
Reception tally, then booking data
Median wait
5 working days
Booking data, weekly
Team and roles
Name
Role
Hours a week
Atticus
Sponsor
1
Aurelie
Process owner
2
Amara
Project leader (Green Belt)
20
Augustin
Mentor (Black Belt)
1
Astrid
Data Analyst
4
Alma
Reception Team Lead
4
Ayumi
Healthcare Assistant
3
Arjun
GP
3
Plan: phases and reviews
DefineWeek 2
MeasureWeek 6
AnalyseWeek 10
ImproveWeek 16
ControlWeek 20
Expected benefits
About €35,000 a year: €22,785 of clinic savings from fewer missed appointments and repeat calls, and €12,480 of avoided emergency visits (method agreed with Abigail, Finance Business Partner). Better patient experience.
Sponsor
Signature
Date
Process owner
Signature
Date
Day in the Role · Improvement charterIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleImprovement charterProblem, goal, scope and team on one page
Version
Date
Project
Sponsor
Process owner
Project leader
Problem statement
Goal
In scope
Out of scope
What customers need (critical to quality)
Requirement
Target
Measured how
Team and roles
Name
Role
Hours a week
Plan: phases and reviews
DefineReview date: ________
MeasureReview date: ________
AnalyseReview date: ________
ImproveReview date: ________
ControlReview date: ________
Expected benefits
Sponsor
Signature
Date
Process owner
Signature
Date
Day in the Role · Improvement charterTemplate · free to use and adapt · dayintherole.com
Illustrative example in our own words: not a real project or organisation.