Closing · document brief

Benefits review

A review, months after the project, of whether each benefit is happening: measured against its baseline and target, with the trend, causes and actions.

3 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

months after go-live, you check whether the money achieved its purpose.

Why it matters

It answers the question the project was started for, and triggers action when benefits lag.

Written by

The benefit owners, coordinated by the sponsor

Approved by

The sponsor and leadership

When it appears

At the points in the benefits plan, usually 6 and 12 months after going live.

What goes inside

  1. Benefits Baseline, target, actual, status.
  2. Causes and actions Why lagging benefits lag, and what's done.
  3. Overall Project success and benefit success.

Watch out for

  • Changing targets to fit results.
  • Calling the project a failure because benefits take time.
  • No actions for lagging benefits.

How this document fits

NeedsBenefits management planData from operationsBusiness case
This documentBenefits reviewMade with
FeedsActions by benefit ownersNext reviewNew requests (project-mandate)
Where you will meet this: Benefits review · benefits realisation report · post-implementation reviewPrint the example ↗Print the blank ↗

The document

Day in the RoleBenefits reviewIs the investment paying off?
Version1.0
Date15 March
Review pointMonth 6 after opening

Progress from baseline to target

GP waiting time (weeks)
311.5
AchievedOn the wayNot happening
Travel time to care (minutes)
401512
AchievedOn the wayNot happening
Minor emergency visits (% change)
0-20-12
AchievedOn the wayNot happening

Left: baseline before the project. Right: target. Marker: today’s measurement.

Causes and actions

BenefitCauseActionOwner
GP waiting time15% of appointments are no-showsText reminders the day beforeAmani (Clinical Lead)
Minor emergency visitsResidents don't know about evening slotsAwareness campaignAzadeh (Community Council)

Overall

The project delivered what was approved, on time and under budget. Benefits are partly realised, with clear actions. Next review: month 12.

Sponsor
Signature
Date
Day in the Role · Benefits reviewIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleBenefits reviewIs the investment paying off?
Version
Date
Review point

Progress from baseline to target

BaselineTarget
AchievedOn the wayNot happening
BaselineTarget
AchievedOn the wayNot happening
BaselineTarget
AchievedOn the wayNot happening

Left: baseline before the project. Right: target. Marker: today’s measurement.

Causes and actions

BenefitCauseActionOwner

Overall

Sponsor
Signature
Date
Day in the Role · Benefits reviewTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.