Process improvement · document brief

Pilot plan and results

The plan for a small-scale test of a change, with its prediction and success measures, and the results compared with the baseline.

4 sections
Used by Process Improvement Specialist
Process improvement

Use it when

you test a change on a small scale before rolling it out.

Why it matters

It makes sure a change is tested fairly, measured the same way as before, and judged on evidence before roll-out.

Written by

The project leader, with the process owner

Approved by

The sponsor approves the plan and accepts the results

When it appears

In Improve, before rolling out a change; filled in as the pilot runs and finished when it ends.

What goes inside

  1. What we're testing The changes, where, for how long.
  2. Prediction and success measures What we expect, and how we'll measure it, with the same definitions as the baseline.
  3. Risks and how we'll stop if needed
  4. What we learned and decided Adopt, adapt or drop.

Watch out for

  • No prediction written down.
  • Different measures from the baseline.
  • Declaring success without testing the difference.

How this document fits

NeedsRoot cause verificationSolution selection
This documentPilot plan and resultsMade with
Where you will meet this: PDSA record · pilot plan · trial reportPrint the example ↗Print the blank ↗

The document

Day in the RolePilot plan and resultsPlan, do, study, act
Version1.0
Date15 March

Plan, do, study, act. Write the prediction before the pilot starts.

Plan: what we're testing

Book up to 2 weeks ahead, text reminders for every booking, protected urgent slots with a system lock, two extra Monday sessions moved from Thursday. Whole clinic, 4 weeks.

Prediction and results: same definitions as the baseline

MeasureBaselinePredic­tionResult
Median wait (days)105 or less4
Within 7 days45%85% or more88%
Missed appointments15.7%10% or less8.5%
Thursday and Friday waits7.1 to 9.0 daysno worseno worse

Risks, and when we'd stop

  • Thursday waits rise: checked weekly
  • Patients forget bookings made far ahead: reminders
  • System lock fails: daily urgent count

Study: what we learned

All measures improved significantly (two-proportion and Mann-Whitney tests, p below 0.0001). Adopt; add cover for the two lost sessions to reach 90%.

Act: decision

AdoptAdapt and test againDrop
Project leader
Signature
Date
Sponsor
Signature
Date
Day in the Role · Pilot plan and resultsIllustrative example · not a real project or organisation · dayintherole.com
Day in the RolePilot plan and resultsPlan, do, study, act
Version
Date

Plan, do, study, act. Write the prediction before the pilot starts.

Plan: what we're testing

Prediction and results: same definitions as the baseline

MeasureBaselinePredic­tionResult

Risks, and when we'd stop

Study: what we learned

Act: decision

AdoptAdapt and test againDrop
Project leader
Signature
Date
Sponsor
Signature
Date
Day in the Role · Pilot plan and resultsTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.