Benefits management plan

How each expected benefit will be measured after the project: its baseline, target, measure, timing and the person in the organisation who owns it.

3 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

benefits will arrive after the project and need owners and measures.

Why it matters

It makes sure someone keeps checking whether the money achieved its purpose, long after the project team has gone.

Written by

Drafted by the project manager; owned by the sponsor

Approved by

The sponsor

When it appears

Drafted with the business case, completed before handover, and used for reviews after the project closes.

What goes inside

  1. Benefits Each benefit and how it's measured.
  2. Review points When each benefit is reviewed.
  3. Risks to the benefits What could stop them.

Watch out for

  • Benefits without baselines.
  • Owners who leave with the project.
  • Only reviewing once.

How this document fits

This documentBenefits management planMade with
FeedsBenefits reviewDecisions on further actions
Where you will meet this: Benefits management plan (PMI) · benefits management approach and benefits review plan (PRINCE2) · benefits realisation planPrint the example ↗Print the blank ↗

The document

Day in the RoleBenefits management planWho checks the benefits, how and when
Version1.0
Date15 March

Benefits

GP waiting time
Baseline3 weeks
→
TargetUnder 1 week
Measured byAverage wait for a routine appointment
OwnerAmani (Clinical Lead)
Travel time to care
Baseline40 minutes
→
TargetUnder 15 minutes
Measured byTravel time survey of residents
OwnerAtticus (Sponsor)
Minor emergency visits
Baseline100% (today's level)
→
Target−20%
Measured byRegional emergency department data
OwnerAmani (Clinical Lead)

Review points

OpeningBaselines confirmedAbigail (Finance)
Month 6All benefitsAtticus (Sponsor)
Month 12All benefits and the business caseCouncil leadership

Risks to the benefits

  • Appointment no-shows
  • Staff turnover in the first year
  • Slow take-up of online booking
Sponsor
Signature
Date
Day in the Role · Benefits management planIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleBenefits management planWho checks the benefits, how and when
Version
Date

Benefits

Baseline
→
Target
Measured by
Owner
Baseline
→
Target
Measured by
Owner
Baseline
→
Target
Measured by
Owner
Baseline
→
Target
Measured by
Owner
Baseline
→
Target
Measured by
Owner

Review points

Risks to the benefits

Sponsor
Signature
Date
Day in the Role · Benefits management planTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.

See it in the story

In the Project Manager story

Related documents

← All documents and templates