Supplier performance review

A regular review that scores a supplier against agreed measures, records evidence, and agrees improvements with them.

5 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

a supplier's performance needs a regular, evidence-based review.

Why it matters

It keeps supplier performance visible and fact-based, and turns problems into agreed actions before they become disputes.

Written by

The project manager with procurement

Approved by

Shared with and acknowledged by the supplier

When it appears

Monthly (or at milestones) for each major supplier, throughout the contract.

What goes inside

  1. Supplier and period Who and when.
  2. Scores Each measure, its score and the evidence.
  3. What went well Strengths to keep.
  4. Improvements agreed Actions, owners, dates.
  5. Acknowledged Both sides.

Watch out for

  • Scores with no evidence.
  • Only bad news, so suppliers get defensive.
  • Reviews that don't lead to actions.

How this document fits

NeedsStatement of workProgress and inspection records
This documentSupplier performance reviewMade with
FeedsAgreed improvementsPayment decisionsLessons log
Where you will meet this: Supplier scorecard · vendor performance review · contract reviewPrint the example ↗Print the blank ↗

The document

Day in the RoleSupplier performance reviewScored on evidence, improved together
Version1.0
Date15 March
SupplierBuilding contractor
ContractRHC-SOW-01
PeriodMonth 4

Scores

MeasureScore (circle one)Evidence
Time12345Two weeks behind (damp in north wall)
Quality12345Ventilation defect in rooms 4 to 6
Safety12345No incidents; asbestos removal certified
Communication12345Cabling completion not shared
Cost12345One claim, settled at €20,000

1 = well below what was agreed · 3 = as agreed · 5 = well above. Every score needs evidence.

Average3.4 of 5

What went well

  • Excellent safety record
  • Quick response to the asbestos condition

Overall

Performing wellImprovement neededFormal warning

Improvements agreed

ActionOwnerBy when
Recovery plan with weekly checkpointsArash (Contractor)Friday
Drawing revision log, confirmed by each tradeArash (Contractor)Next week
Weekly coordination meeting attendanceArash (Contractor)Ongoing
For the buyer
Signature
Date
For the supplier
Signature
Date
Day in the Role · Supplier performance reviewIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleSupplier performance reviewScored on evidence, improved together
Version
Date
Supplier
Contract
Period

Scores

MeasureScore (circle one)Evidence
Time12345
Quality12345
Safety12345
Communication12345
Cost12345

1 = well below what was agreed · 3 = as agreed · 5 = well above. Every score needs evidence.

Average

What went well

Overall

Performing wellImprovement neededFormal warning

Improvements agreed

ActionOwnerBy when
For the buyer
Signature
Date
For the supplier
Signature
Date
Day in the Role · Supplier performance reviewTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.