Planning · document brief

Request for proposal

The invitation sent to possible suppliers: what you need, how bids will be judged, the timeline and how to respond.

5 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

you invite suppliers to bid on clearly described work.

Why it matters

It makes sure every supplier bids on the same information and knows how the choice will be made.

Written by

Procurement with the project manager

Approved by

Procurement lead

When it appears

In planning, once the statement of work is ready and the make-or-buy decision is made.

What goes inside

  1. About the project Context in a few lines.
  2. What we need Summary; the statement of work is attached.
  3. Evaluation criteria Criterion and weight.
  4. Timeline Key dates.
  5. How to respond Format, contact, conflicts of interest.

Watch out for

  • Criteria that change after bids arrive.
  • Vague needs that produce incomparable bids.

How this document fits

NeedsStatement of workMake-or-buy decision
This documentRequest for proposalMade with
FeedsBidsTender evaluationContract
Where you will meet this: RFP · invitation to tender · request for quotation (RFQ) for simpler purchasesPrint the example ↗Print the blank ↗

The document

Day in the RoleRequest for proposalInvitation to submit a proposal
Version1.0
Date15 March
ReferenceRFP-RHC-03
IssuedWeek 6
ContactAlder (Procurement Officer)

Day in the Role invites suppliers to submit a proposal for the work described below. All bidders receive the same information.

1. About the project

The council is converting the empty Riverside warehouse into a community health clinic that must open in month 7.

2. What we need

Asbestos removal, structural repairs and full fit-out to the approved design, as described in statement of work RHC-SOW-01 (attached).

3. How proposals will be judged

Crite­rionWeight (%)
Price40
Experience with healthcare buildings20
Method and safety plan25
Timeline15

Criteria and weights will not change after proposals are received.

4. Timeline

StepDate
RFP issuedWeek 6
Questions in writing byWeek 7
Bids dueWeek 9
DecisionWeek 10
Works startWeek 11

5. How to respond

  • Written bid, fixed price, maximum 20 pages
  • Questions only in writing to the procurement contact; answers shared with all bidders
  • Declare any link to council staff or the project team

6. Conflicts of interest

Bidders must declare any link to the buyer’s staff or project team. Undeclared links may exclude a bid.

Day in the Role · Request for proposalIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleRequest for proposalInvitation to submit a proposal
Version
Date
Reference
Issued
Contact

Day in the Role invites suppliers to submit a proposal for the work described below. All bidders receive the same information.

1. About the project

2. What we need

3. How proposals will be judged

Crite­rionWeight (%)

Criteria and weights will not change after proposals are received.

4. Timeline

StepDate

5. How to respond

6. Conflicts of interest

Bidders must declare any link to the buyer’s staff or project team. Undeclared links may exclude a bid.

Day in the Role · Request for proposalTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.