Planning · document briefRequest for proposal
The invitation sent to possible suppliers: what you need, how bids will be judged, the timeline and how to respond.
5 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
you invite suppliers to bid on clearly described work.
Why it matters
It makes sure every supplier bids on the same information and knows how the choice will be made.
Written by
Procurement with the project manager
Approved by
Procurement lead
When it appears
In planning, once the statement of work is ready and the make-or-buy decision is made.
What goes inside
About the project Context in a few lines.
What we need Summary; the statement of work is attached.
Evaluation criteria Criterion and weight.
Timeline Key dates.
How to respond Format, contact, conflicts of interest.
Watch out for
- Criteria that change after bids arrive.
- Vague needs that produce incomparable bids.
How this document fits
This documentRequest for proposalMade with FeedsBidsTender evaluationContract
The document
Day in the RoleRequest for proposalInvitation to submit a proposal
ReferenceRFP-RHC-03
IssuedWeek 6
ContactAlder (Procurement Officer)
Day in the Role invites suppliers to submit a proposal for the work described below. All bidders receive the same information.
1. About the project
The council is converting the empty Riverside warehouse into a community health clinic that must open in month 7.
2. What we need
Asbestos removal, structural repairs and full fit-out to the approved design, as described in statement of work RHC-SOW-01 (attached).
3. How proposals will be judged
| Criterion | Weight (%) |
|---|
| Price | 40 |
| Experience with healthcare buildings | 20 |
| Method and safety plan | 25 |
| Timeline | 15 |
Criteria and weights will not change after proposals are received.
4. Timeline
| Step | Date |
|---|
| RFP issued | Week 6 |
| Questions in writing by | Week 7 |
| Bids due | Week 9 |
| Decision | Week 10 |
| Works start | Week 11 |
5. How to respond
- Written bid, fixed price, maximum 20 pages
- Questions only in writing to the procurement contact; answers shared with all bidders
- Declare any link to council staff or the project team
6. Conflicts of interest
Bidders must declare any link to the buyer’s staff or project team. Undeclared links may exclude a bid.
Day in the RoleRequest for proposalInvitation to submit a proposal
Day in the Role invites suppliers to submit a proposal for the work described below. All bidders receive the same information.
3. How proposals will be judged
Criteria and weights will not change after proposals are received.
6. Conflicts of interest
Bidders must declare any link to the buyer’s staff or project team. Undeclared links may exclude a bid.
Illustrative example in our own words: not a real project or organisation.