Readiness checklist

A checklist of everything that must be ready before the result goes live, with a status per item and the go or no-go decision.

3 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

go-live is near and readiness must be checked on facts.

Why it matters

It turns “are we ready?” into an objective check, and makes sure fallbacks exist for anything not fully ready.

Written by

The project manager with the operations lead

Approved by

The sponsor and the user side decide go or no-go

When it appears

In the weeks before going live, reviewed at the go or no-go meeting.

What goes inside

  1. Areas Each area, its items and status.
  2. Rehearsal findings What the trial run found and the fix.
  3. Decision Go, go with fallbacks, or no-go.

Watch out for

  • Deciding on the announced date instead of the checklist.
  • No fallback for items that aren't ready.
  • Leaving out people and communication, not just systems.

How this document fits

NeedsAcceptance certificateLicence or approvalsTraining recordsRehearsal results
This documentReadiness checklistMade with
FeedsGo or no-go decisionHandover certificate
Where you will meet this: Go-live checklist · operational readiness assessment · go/no-go checklistPrint the example ↗Print the blank ↗

The document

Day in the RoleReadiness checklistReady to go live?
Version1.0
Date15 March
Go-liveMonday, week 30

Readiness by area

AreaStatus noteCriticalReady?Fallback if not ready
BuildingAccepted, defects listedRAG
LicenceGranted after two conditions closedRAG
Staff30 hired and trainedRAG
Phone bookingSecond line added after rehearsalRAG
Online bookingIntegration 3 weeks lateRAGPhone booking for the first 4 weeks
Supplies and courierCourier moved to 15:30RAG
CommunicationOpening announced, newsletter sentRAG

Every critical item must be green, or have a fallback everyone accepts.

Rehearsal findings

FindingFixOwnerRe-tested
Phone queue too long at peakSecond receptionist 08:00 to 11:00Amani (Clinical Lead)✓
Lab samples missed the courierPick-up moved to 15:30Aya (Project Coordinator)✓

Decision

GoGo with fallbacksNo-go
Sponsor
Signature
Date
Operations owner
Signature
Date
Day in the Role · Readiness checklistIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleReadiness checklistReady to go live?
Version
Date
Go-live

Readiness by area

AreaStatus noteCriticalReady?Fallback if not ready
DeliverableRAG
ApprovalsRAG
PeopleRAG
SystemsRAG
SuppliesRAG
SupportRAG
CommunicationRAG

Every critical item must be green, or have a fallback everyone accepts.

Rehearsal findings

FindingFixOwnerRe-tested

Decision

GoGo with fallbacksNo-go
Sponsor
Signature
Date
Operations owner
Signature
Date
Day in the Role · Readiness checklistTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.

See it in the story

In the Project Manager story

Related documents

← All documents and templates