Process improvement · document brief

Capability study report

The record of how well a process meets its requirement: the data used, the stability check, the shape of the data, the capability figures and what they mean.

5 sections
Used by Process Improvement Specialist
Process improvement

Use it when

you need to fix and record how well a process meets its requirement.

Why it matters

It fixes the baseline the project will be judged against, in a form the sponsor and the next team can trust.

Written by

The project leader, with the data analyst

Approved by

Reviewed at the Measure phase review

When it appears

At the end of Measure (the baseline), and again after Improve to show the change.

What goes inside

  1. What was studied Process, requirement limits, data, period, sample size.
  2. Stability Run chart or control chart, and the stable period used.
  3. Shape of the data Descriptive statistics and normality.
  4. Capability Observed share outside, indices, sigma level.
  5. What it means

Watch out for

  • Capability on an unstable process.
  • Normal-based indices on skewed data without checking the observed share.
  • No sample size or period stated.
Where you will meet this: Process capability study · baseline report · Measure phase summaryPrint the example ↗Print the blank ↗

The document

Day in the RoleCapability study reportHow well the process meets its requirement
Version1.0
Date15 March
ProcessRoutine appointment booking
RequirementUpper limit 7 days
Data and periodWaits, weeks 12 to 20 (stable period)
Sample size60 random requests

1. Stability first

Run chart of 20 weeks: a shift at week 12 (9 points above the median). Weeks 12 to 20 are stable and used.

2. Shape of the data

Statis­ticValue
Mean10.43 days
Median10 days
Standard deviation6.46 days
Range3 to 28 days
ShapeSkewed right
Normality testp about 0.0001: not normal

3. Capability

MeasureValueHow cal­culated
Observed over the limit55%33 of 60
Per million550,0000.55 × 1,000,000
Ppk (upper)−0.18(7 − 10.43) ÷ (3 × 6.46)
Sigma levelabout 1.4NORM.S.INV(0.45) + 1.5
Log scale (Box-Cox λ ≈ 0)63% predictedchecked against 55% observed

Report the observed share outside the limits first. Use Cp, Cpk, Pp and Ppk only when the data is roughly normal, or after a checked transformation.

4. What it means

The process can't meet the requirement: more than half of patients wait too long. Because the data is skewed, the observed share is the headline figure.

Project leader
Signature
Date
Sponsor
Signature
Date
Day in the Role · Capability study reportIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleCapability study reportHow well the process meets its requirement
Version
Date
Process
Requirement
Data and period
Sample size

1. Stability first

2. Shape of the data

Statis­ticValue

3. Capability

MeasureValueHow cal­culated

Report the observed share outside the limits first. Use Cp, Cpk, Pp and Ppk only when the data is roughly normal, or after a checked transformation.

4. What it means

Project leader
Signature
Date
Sponsor
Signature
Date
Day in the Role · Capability study reportTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.