The record of how well a process meets its requirement: the data used, the stability check, the shape of the data, the capability figures and what they mean.
5 sections Used by Process Improvement Specialist
Process improvement
Use it when
you need to fix and record how well a process meets its requirement.
Why it matters
It fixes the baseline the project will be judged against, in a form the sponsor and the next team can trust.
Written by
The project leader, with the data analyst
Approved by
Reviewed at the Measure phase review
When it appears
At the end of Measure (the baseline), and again after Improve to show the change.
What goes inside
What was studiedProcess, requirement limits, data, period, sample size.
StabilityRun chart or control chart, and the stable period used.
Shape of the dataDescriptive statistics and normality.
Day in the RoleCapability study reportHow well the process meets its requirement
Version
1.0
Date
15 March
ProcessRoutine appointment booking
RequirementUpper limit 7 days
Data and periodWaits, weeks 12 to 20 (stable period)
Sample size60 random requests
1. Stability first
Run chart of 20 weeks: a shift at week 12 (9 points above the median). Weeks 12 to 20 are stable and used.
2. Shape of the data
Statistic
Value
Mean
10.43 days
Median
10 days
Standard deviation
6.46 days
Range
3 to 28 days
Shape
Skewed right
Normality test
p about 0.0001: not normal
3. Capability
Measure
Value
How calculated
Observed over the limit
55%
33 of 60
Per million
550,000
0.55 × 1,000,000
Ppk (upper)
−0.18
(7 − 10.43) ÷ (3 × 6.46)
Sigma level
about 1.4
NORM.S.INV(0.45) + 1.5
Log scale (Box-Cox λ ≈ 0)
63% predicted
checked against 55% observed
Report the observed share outside the limits first. Use Cp, Cpk, Pp and Ppk only when the data is roughly normal, or after a checked transformation.
4. What it means
The process can't meet the requirement: more than half of patients wait too long. Because the data is skewed, the observed share is the headline figure.
Project leader
Signature
Date
Sponsor
Signature
Date
Day in the Role · Capability study reportIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleCapability study reportHow well the process meets its requirement
Version
Date
Process
Requirement
Data and period
Sample size
1. Stability first
2. Shape of the data
Statistic
Value
3. Capability
Measure
Value
How calculated
Report the observed share outside the limits first. Use Cp, Cpk, Pp and Ppk only when the data is roughly normal, or after a checked transformation.
4. What it means
Project leader
Signature
Date
Sponsor
Signature
Date
Day in the Role · Capability study reportTemplate · free to use and adapt · dayintherole.com
Illustrative example in our own words: not a real project or organisation.