Planning · document brief

Scope statement

Describes exactly what the project will deliver, how each deliverable will be accepted, and what is deliberately left out.

6 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

everyone must agree exactly what will and won't be delivered.

Why it matters

It turns the charter's rough scope into something precise enough to plan, buy and check against. Every change request is judged against it.

Written by

The project manager, with the users and experts

Approved by

The sponsor (and senior user)

When it appears

Early in planning, after requirements are collected. It becomes part of the scope baseline.

What goes inside

  1. Project objective The outcome, from the charter.
  2. Deliverables and acceptance Each deliverable and how it will be accepted.
  3. Out of scope What is explicitly excluded.
  4. Constraints Limits that can't move.
  5. Assumptions What we treat as true.
  6. Approval Sign-off.

Watch out for

  • Leaving out exclusions.
  • Acceptance criteria nobody can test (“works well”).
  • Writing it alone, without the users.

How this document fits

NeedsProject charterRequirements from usersStakeholder register
FeedsWork breakdown structureStatement of workChange requests are judged against it
Where you will meet this: Project scope statement (PMI) · product description and project product description (PRINCE2)Print the example ↗Print the blank ↗

The document

Day in the RoleScope statementWhat is in, what is out, how it will be accepted
Version1.0
Date15 March
Project objective

Residents of Riverside get everyday care within 15 minutes of home; GP waiting time under 1 week within a year of opening.

IN What we will deliver

Delive­rableAccepted when
Converted buildingBuilding-control sign-off; joint inspection passed
Clinical equipmentInstalled, tested and certified on site
Booking system50 test bookings succeed online and by phone
30 staff hired and trainedAll roles filled; training records complete
Licence to operateGranted by the health authority
OpeningFirst patients seen; residents informed

OUT Not in this project

  • Emergency care
  • Hospital beds
  • Pharmacy (possible later)
  • Café
  • Dental care

Constraints

  • Budget €4.2M
  • Opening in month 7
  • Health authority licence rules

Assumptions

  • Survey findings are complete
  • Regional funding per patient unchanged
Sponsor
Signature
Date
Senior user
Signature
Date
Day in the Role · Scope statementIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleScope statementWhat is in, what is out, how it will be accepted
Version
Date
Project objective

IN What we will deliver

Delive­rableAccepted when

OUT Not in this project

Constraints

Assumptions

Sponsor
Signature
Date
Senior user
Signature
Date
Day in the Role · Scope statementTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.