Cost baseline

The approved, time-phased budget: what each part of the work costs, when the money is spent, and what is held in reserve.

3 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

the budget must be set, phased over time and tracked.

Why it matters

It tells finance how much is needed and when, and gives the project a yardstick to measure spending and progress against.

Written by

The project manager with finance

Approved by

The sponsor and finance

When it appears

In planning, after the WBS and schedule. Approved with the plan; actual spending is tracked against it.

What goes inside

  1. Cost per deliverable Bottom-up estimates per WBS branch.
  2. Reserves Contingency for known risks; management reserve for the unknown.
  3. Spending by month Planned spend per month and cumulative.

Watch out for

  • No contingency, or contingency hidden inside every estimate.
  • A budget with no time profile.
  • Using management reserve without the sponsor's approval.

How this document fits

FeedsProject management planFunding requestsProgress tracking
Where you will meet this: Project budget · cost baseline · contingency and management reservePrint the example ↗Print the blank ↗

The document

Day in the RoleCost baselineBudget, reserves and spending profile
Version1.0
Date15 March
Amounts in€ thousands
Approved onTuesday, month 1

Cost per deliverable

WBSDelive­rableEstimate
1Building3,000
2Equipment650
3Booking system200
4People120
5Licence and opening30
6Project management50
Total work estimates4,050

From estimates to funding

Work estimates4,050Bottom-up, from the WBS
+ Contingency reserve150For identified risks · project manager
= Cost baseline4,200Approved yardstick for spending
+ Management reserve300For the unknown · sponsor approves use
= Total funding4,500What the funder sets aside

Spending over time

01,0502,1003,1504,200M1M2M3M4M5M6M7

Bars: planned spend per month. Line: cumulative spend (the S-curve).

MonthM1M2M3M4M5M6M7
Planned1503509001,000900600300
Cumulative1505001,4002,4003,3003,9004,200
Day in the Role · Cost baselineIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleCost baselineBudget, reserves and spending profile
Version
Date
Amounts in
Approved on

Cost per deliverable

WBSDelive­rableEstimate
Total work estimates

From estimates to funding

Work estimatesBottom-up, from the WBS
+ Contingency reserveFor identified risks · project manager
= Cost baselineApproved yardstick for spending
+ Management reserveFor the unknown · sponsor approves use
= Total fundingWhat the funder sets aside

Spending over time

M1M2M3M4M5M6M7

Bars: planned spend per month. Line: cumulative spend (the S-curve). Draw both by hand.

MonthM1M2M3M4M5M6M7
Day in the Role · Cost baselineTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.