Planning · document briefCost baseline
The approved, time-phased budget: what each part of the work costs, when the money is spent, and what is held in reserve.
3 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
the budget must be set, phased over time and tracked.
Why it matters
It tells finance how much is needed and when, and gives the project a yardstick to measure spending and progress against.
Written by
The project manager with finance
Approved by
The sponsor and finance
When it appears
In planning, after the WBS and schedule. Approved with the plan; actual spending is tracked against it.
What goes inside
Cost per deliverable Bottom-up estimates per WBS branch.
Reserves Contingency for known risks; management reserve for the unknown.
Spending by month Planned spend per month and cumulative.
Watch out for
- No contingency, or contingency hidden inside every estimate.
- A budget with no time profile.
- Using management reserve without the sponsor's approval.
How this document fits
This documentCost baselineMade with
The document
Day in the RoleCost baselineBudget, reserves and spending profile
Amounts in€ thousands
Approved onTuesday, month 1
Cost per deliverable
| WBS | Deliverable | Estimate |
|---|
| 1 | Building | 3,000 |
| 2 | Equipment | 650 |
| 3 | Booking system | 200 |
| 4 | People | 120 |
| 5 | Licence and opening | 30 |
| 6 | Project management | 50 |
Total work estimates4,050
From estimates to funding
Work estimates4,050Bottom-up, from the WBS
+ Contingency reserve150For identified risks · project manager
= Cost baseline4,200Approved yardstick for spending
+ Management reserve300For the unknown · sponsor approves use
= Total funding4,500What the funder sets aside
Spending over time
Bars: planned spend per month. Line: cumulative spend (the S-curve).
| Month | M1 | M2 | M3 | M4 | M5 | M6 | M7 |
|---|
| Planned | 150 | 350 | 900 | 1,000 | 900 | 600 | 300 |
| Cumulative | 150 | 500 | 1,400 | 2,400 | 3,300 | 3,900 | 4,200 |
Day in the RoleCost baselineBudget, reserves and spending profile
Cost per deliverable
Total work estimates
From estimates to funding
Work estimatesBottom-up, from the WBS
+ Contingency reserveFor identified risks · project manager
= Cost baselineApproved yardstick for spending
+ Management reserveFor the unknown · sponsor approves use
= Total fundingWhat the funder sets aside
Spending over time
Bars: planned spend per month. Line: cumulative spend (the S-curve). Draw both by hand.
Illustrative example in our own words: not a real project or organisation.