Monitoring and controlling · document briefChange request
The form used to propose a change to scope, time, cost or quality, assess its impact, and record the decision.
5 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
someone wants to change scope, time, cost or quality.
Why it matters
It makes sure every change is understood, decided by the right person and reflected in the plans, instead of slipping in unnoticed.
Written by
Raised by anyone; assessed by the project manager
Approved by
The project manager within tolerance; the change board or sponsor beyond it
When it appears
Whenever anyone wants to change something already agreed in the baselines, from initiating to closing.
What goes inside
Request What change, who asks, and why.
Description and reason What and why.
Impact On each area.
Options Including doing nothing or doing it later.
Decision Approved, rejected or deferred, by whom.
Watch out for
- Deciding before assessing.
- Approving without updating the plans.
- Small changes skipping the process, adding up to big ones.
How this document fits
This documentChange requestMade with FeedsChange logUpdated baselines and plansContract change orders
The document
Day in the RoleChange requestRequest · impact · decision
Change no.CR-07
Raised byAmani (Clinical Lead)
DateWeek 22
TypeScope
1. What change?
Move two walls in the treatment area so a wheelchair and a trolley fit side by side.
2. Why?
Safe access for wheelchair users; the current layout fails the clinical team's walk-through.
3. Impact (L = low, M = medium, H = high)
| Area | Impact | Detail |
|---|
| Scope | LMH | Two walls and ventilation ducts moved |
|---|
| Time | LMH | 1 week on the critical path, recoverable by overlapping two finishing tasks |
|---|
| Cost | LMH | €18,000 from contingency |
|---|
| Quality | LMH | Improves accessibility; ventilation re-inspection needed |
|---|
| Risk | LMH | Small risk of rework in the overlap |
|---|
| Other work | LMH | Equipment layout drawing updated |
|---|
4. Options
| Option | Cost | Time | Risk |
|---|
| Do it now, overlap finishing tasks | €18,000 | 0 weeks net | Low |
| Do it after opening | €30,000 | Clinic closed 1 week | Medium |
| Don't do it | €0 | None | Access problem remains |
5. Decision
ApprovedApproved with conditionsRejectedDeferred
Decided byChange board: Atticus (Sponsor), Amani (Clinical Lead), Arash (Contractor)
After approval: update the change log, plans, baselines and contracts, and tell everyone affected.
Day in the RoleChange requestRequest · impact · decision
Change no.
Raised by
Date
Type
3. Impact (L = low, M = medium, H = high)
| Area | Impact | Detail |
|---|
| Scope | LMH | |
|---|
| Time | LMH | |
|---|
| Cost | LMH | |
|---|
| Quality | LMH | |
|---|
| Risk | LMH | |
|---|
| Other work | LMH | |
|---|
5. Decision
ApprovedApproved with conditionsRejectedDeferred
After approval: update the change log, plans, baselines and contracts, and tell everyone affected.
Illustrative example in our own words: not a real project or organisation.