Monitoring and controlling · document brief

Change request

The form used to propose a change to scope, time, cost or quality, assess its impact, and record the decision.

5 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

someone wants to change scope, time, cost or quality.

Why it matters

It makes sure every change is understood, decided by the right person and reflected in the plans, instead of slipping in unnoticed.

Written by

Raised by anyone; assessed by the project manager

Approved by

The project manager within tolerance; the change board or sponsor beyond it

When it appears

Whenever anyone wants to change something already agreed in the baselines, from initiating to closing.

What goes inside

  1. Request What change, who asks, and why.
  2. Description and reason What and why.
  3. Impact On each area.
  4. Options Including doing nothing or doing it later.
  5. Decision Approved, rejected or deferred, by whom.

Watch out for

  • Deciding before assessing.
  • Approving without updating the plans.
  • Small changes skipping the process, adding up to big ones.

How this document fits

This documentChange requestMade with
FeedsChange logUpdated baselines and plansContract change orders
Where you will meet this: Change request · request for change · change orderPrint the example ↗Print the blank ↗

The document

Day in the RoleChange requestRequest · impact · decision
Change no.CR-07
Raised byAmani (Clinical Lead)
DateWeek 22
TypeScope

1. What change?

Move two walls in the treatment area so a wheelchair and a trolley fit side by side.

2. Why?

Safe access for wheelchair users; the current layout fails the clinical team's walk-through.

3. Impact (L = low, M = medium, H = high)

AreaImpactDetail
ScopeLMHTwo walls and ventilation ducts moved
TimeLMH1 week on the critical path, recoverable by overlapping two finishing tasks
CostLMH€18,000 from contingency
QualityLMHImproves accessibility; ventilation re-inspection needed
RiskLMHSmall risk of rework in the overlap
Other workLMHEquipment layout drawing updated

4. Options

OptionCostTimeRisk
Do it now, overlap finishing tasks€18,0000 weeks netLow
Do it after opening€30,000Clinic closed 1 weekMedium
Don't do it€0NoneAccess problem remains

5. Decision

ApprovedApproved with conditionsRejectedDeferred
Decided by
Change board: Atticus (Sponsor), Amani (Clinical Lead), Arash (Contractor)

After approval: update the change log, plans, baselines and contracts, and tell everyone affected.

Day in the Role · Change requestIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleChange requestRequest · impact · decision
Change no.
Raised by
Date
Type

1. What change?

2. Why?

3. Impact (L = low, M = medium, H = high)

AreaImpactDetail
ScopeLMH
TimeLMH
CostLMH
QualityLMH
RiskLMH
Other workLMH

4. Options

OptionCostTimeRisk

5. Decision

ApprovedApproved with conditionsRejectedDeferred
Decided by

After approval: update the change log, plans, baselines and contracts, and tell everyone affected.

Day in the Role · Change requestTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.