Work breakdown structure

A tree that breaks the whole scope into deliverables and smaller pieces of work, until each piece can be estimated, scheduled and owned.

4 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

the whole scope must be broken into pieces you can plan and own.

Why it matters

It makes sure all the work is included once, and only once. If something isn't in the WBS, it isn't in the project.

Written by

The project manager, built with the team

Approved by

Part of the scope baseline, approved with the plan

When it appears

In planning, right after the scope statement. It is the backbone for the schedule, the budget and the RACI chart.

What goes inside

  1. Level 1 The project.
  2. Level 2 The main deliverables (usually 4 to 8).
  3. Level 3 Smaller pieces under each deliverable.
  4. WBS dictionary For key work packages: what's included, acceptance, estimate.

Watch out for

  • Listing activities (verbs) instead of deliverables (nouns).
  • Forgetting project management itself as a branch.
  • Pieces so big nobody can estimate them, or so small that tracking them costs more than the work.

How this document fits

NeedsScope statementExpert input from each lead
This documentWork breakdown structureMade with
Where you will meet this: WBS (PMI) · product breakdown structure (PRINCE2) · WBS dictionaryPrint the example ↗Print the blank ↗

The document

Day in the RoleWork breakdown structureThe whole scope, broken into pieces
Version1.0
Date15 March
1 · ProjectRiverside Health Centre
1Building
1.1 Design
1.2 Asbestos removal
1.3 Structural repairs
1.4 Fit-out
2Equipment
2.1 Clinical equipment
2.2 Furniture
2.3 Installation
3Booking system
3.1 Purchase
3.2 Setup
3.3 Integration
3.4 Testing
4People
4.1 Hiring
4.2 Training
4.3 Rotas
5Licence and opening
5.1 Licence
5.2 Mock clinic day
5.3 Opening event
6Project management
6.1 Planning
6.2 Reporting
6.3 Closure

Rule of thumb: every box is a deliverable (a noun), the boxes under a parent add up to exactly the parent, and project management has its own branch.

WBS dictionary (key work packages)

CodeDescrip­tionAccepted whenEstimate
1.4Fit-out: rooms, floors, ventilation to infection-control standardBuilding-control sign-off€1.4M · 8 weeks
3.2Setup: appointment types, opening hours, staff rotas in the system50 test bookings succeed€40k · 4 weeks
Day in the Role · Work breakdown structureIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleWork breakdown structureThe whole scope, broken into pieces
Version
Date
1 · Project
1
1.1
1.2
1.3
1.4
1.5
1.6
2
2.1
2.2
2.3
2.4
2.5
2.6
3
3.1
3.2
3.3
3.4
3.5
3.6
4
4.1
4.2
4.3
4.4
4.5
4.6
5
5.1
5.2
5.3
5.4
5.5
5.6
6
6.1
6.2
6.3
6.4
6.5
6.6

Rule of thumb: every box is a deliverable (a noun), the boxes under a parent add up to exactly the parent, and project management has its own branch.

WBS dictionary (key work packages)

CodeDescrip­tionAccepted whenEstimate
Day in the Role · Work breakdown structureTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.