Monitoring and controlling · document brief

Sponsor briefing

A short brief for a new sponsor: why the project exists, where it stands, key decisions so far, promises made, open risks, and what is needed from them.

5 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

a new sponsor or senior leader takes over the project.

Why it matters

It helps a new sponsor take ownership quickly, and keeps the knowledge of the outgoing sponsor.

Written by

The project manager, with the outgoing sponsor

Approved by

Discussed with the new sponsor

When it appears

When a sponsor changes, or a new senior leader joins the board.

What goes inside

  1. Why the project exists In two lines.
  2. Where it stands Status per area.
  3. Key decisions so far And why.
  4. Promises made To whom.
  5. What we need from you Decisions and support.

Watch out for

  • Sending the whole project file instead.
  • Hiding past disagreements.

How this document fits

This documentSponsor briefingMade with
FeedsRe-confirmed charter and tolerancesNew sponsor's priorities
Where you will meet this: Sponsor handover note · onboarding briefPrint the example ↗Print the blank ↗

The document

Day in the RoleSponsor briefingEverything a new sponsor needs on one page
Version1.0
Date15 March
From (outgoing sponsor)Atticus (Director of Community Health)
→
To (new sponsor)Alessandro (Deputy Chief Executive)
Why the project exists

Riverside residents travel 40 minutes for basic care and wait 3 weeks for a GP. The clinic brings everyday care within 15 minutes of home.

Where it stands

AreaStatusNote
TimeRAGOpening week 30; online booking after opening
CostRAGWithin the reduced budget after the €210k return
ScopeRAGSix deliverables, four approved changes
RiskRAGLicence inspection booked for week 28

Key decisions so far

  • Warehouse option (business case)
  • Hybrid delivery
  • Phone booking at opening
  • €210k returned by postponing extras

Promises made

  • Opening in month 7 (the mayor)
  • Monthly residents' updates (community council)

What we need from you

  • Confirm the tolerances
  • Chair the next board
  • Decide on the pharmacy idea
Day in the Role · Sponsor briefingIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleSponsor briefingEverything a new sponsor needs on one page
Version
Date
From (outgoing sponsor)
→
To (new sponsor)
Why the project exists

Where it stands

AreaStatusNote
TimeRAG
CostRAG
ScopeRAG
RiskRAG

Key decisions so far

Promises made

What we need from you

Day in the Role · Sponsor briefingTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.