Planning · document brief Project management plan The approved plan for how the project will be run: the baselines for scope, time and cost, plus how risk, quality, buying, communication and change will be managed.
4 sections Used by Project Manager
Pre-project Initiating Planning Executing Monitoring Closing
Use it when all plans and baselines must be agreed as one reference.
Why it matters It brings all the plans together into one agreed reference, and sets the baselines that progress is measured against.
Written by The project manager
Approved by The sponsor or project board
When it appears At the end of planning, for approval by the sponsor or board. Updated through change control.
What goes inside Baselines Scope, schedule and cost.
Management plans How each area is managed, with a reference to the detail.
Change control How changes are requested, assessed and approved.
Approval Sign-off.
Watch out for A huge document nobody reads; summarise and refer. Baselines changed without approval. Detail for later stages that can't be known yet. How this document fits
This document Project management plan Made with
Feeds Approved baselines Executing stage starts Change control
What the letters mean
PMI Project Management Institute
RACI Responsible (does the work), Accountable (owns the result), Consulted (asked before), Informed (told after)
PRINCE2 Projects in Controlled Environments: a project management method
T&M Time and materials: paying for hours worked and materials used
WBS Work breakdown structure
€k Thousands of euros (€150k = €150,000)
€M Millions of euros (€4.2M = €4,200,000)
The document Filled-in example Blank template
Day in the Role Project management plan The plan on a page
Scope baseline Scope statement v1.0 and WBS (6 deliverables)
Schedule baseline Opening in week 30 (month 7); critical path through the building works
Cost baseline €4.2M including €150k contingency; €300k reserve held by the sponsor
Management approach per area Area How we manage it Detail in Risk Weekly review; board monthly Risk register Quality Checks at each building phase; mock clinic day Scope statement Buying Fixed price for works; capped T&M for investigations Statement of work Communication Weekly status, monthly board and residents' update Communication plan Stakeholders Engagement plan per key person Stakeholder register Resources Time agreed with line managers RACI chart
Change control 1 Request logged
2 Impact assessed (scope, time, cost, risk)
3 Decided within tolerance or by the board
4 Plans and baselines updated
5 Everyone informed
Tolerances Annelise (Project Manager): up to €25k and 2 weeks per stage. Beyond that: the board.
Day in the Role Project management plan The plan on a page
Management approach per area Area How we manage it Detail in Risk Quality Buying Communication Stakeholders Resources
Change control 1 Request logged
2 Impact assessed (scope, time, cost, risk)
3 Decided within tolerance or by the board
4 Plans and baselines updated
5 Everyone informed
Illustrative example in our own words: not a real project or organisation.
See it in the story In the Project Manager story