Scrum and product · document briefRelease plan and forecast
What the next release must contain, should contain and won't contain, with a forecast of when, based on the team's actual progress.
3 sections
Used by Product Owner, Scrum Master
Scrum and product
Use it when
stakeholders ask “when?” and scope must be traded honestly.
Why it matters
It answers “when?” honestly, as a range from evidence, and makes the scope trade-off visible to stakeholders.
Written by
The Product Owner, with the Developers' forecast
Approved by
Release decided by the Product Owner
When it appears
Before each release, updated after every Sprint Review.
What goes inside
Release scope
Progress so far Items done per Sprint.
Forecast A likely range, and what would change it.
Watch out for
- Promising a single date.
- Forecasting from estimates instead of actual progress.
- Hiding scope changes from the forecast.
How this document fits
This documentRelease plan and forecastMade with
The document
Day in the RoleRelease plan and forecastWhat's in the release, and when it's likely
Release scope
| Item | Must | Should | Could | Won't this time |
|---|
| Login | ✓ | | | |
| Browse | ✓ | | | |
| Cart | ✓ | | | |
| Checkout | ✓ | | | |
| Card payment | ✓ | | | |
| Delivery slots | | ✓ | | |
| Favourites | | | ✓ | |
| Promo codes | | | | ✓ |
| Ratings | | | | ✓ |
Progress so far (items done)
| Sprint | Done to date | Total scope |
|---|
| Sprint 1 | 3 | 11 |
| Sprint 2 | 6 | 11 |
| Sprint 3 | 8 | 11 |
Forecast: a likely range, from actual progress
Most likely Sprint 5, possibly 6, if scope stays the same. Adding promo codes would move it a Sprint later.
Forecast from what the team has actually finished, as a range. If scope grows, the forecast moves: show both.
Day in the RoleRelease plan and forecastWhat's in the release, and when it's likely
Release scope
| Item | Must | Should | Could | Won't this time |
|---|
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
Progress so far (items done)
| Sprint | Done to date | Total scope |
|---|
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
Forecast: a likely range, from actual progress
Forecast from what the team has actually finished, as a range. If scope grows, the forecast moves: show both.
Illustrative example in our own words: not a real project or organisation.