Scrum and product · document brief

Release plan and forecast

What the next release must contain, should contain and won't contain, with a forecast of when, based on the team's actual progress.

3 sections
Used by Product Owner, Scrum Master
Scrum and product

Use it when

stakeholders ask “when?” and scope must be traded honestly.

Why it matters

It answers “when?” honestly, as a range from evidence, and makes the scope trade-off visible to stakeholders.

Written by

The Product Owner, with the Developers' forecast

Approved by

Release decided by the Product Owner

When it appears

Before each release, updated after every Sprint Review.

What goes inside

  1. Release scope
  2. Progress so far Items done per Sprint.
  3. Forecast A likely range, and what would change it.

Watch out for

  • Promising a single date.
  • Forecasting from estimates instead of actual progress.
  • Hiding scope changes from the forecast.

How this document fits

NeedsProduct BacklogPast Sprints
FeedsReleaseProduct roadmap
Where you will meet this: Release plan · burn-up forecast (common practice, not in the Scrum Guide)Print the example ↗Print the blank ↗

The document

Day in the RoleRelease plan and forecastWhat's in the release, and when it's likely
Version1.0
Date15 March

Release scope

ItemMustShouldCouldWon't this time
Login✓
Browse✓
Cart✓
Checkout✓
Card payment✓
Delivery slots✓
Favourites✓
Promo codes✓
Ratings✓

Progress so far (items done)

SprintDone to dateTotal scope
Sprint 1311
Sprint 2611
Sprint 3811

Forecast: a likely range, from actual progress

Most likely Sprint 5, possibly 6, if scope stays the same. Adding promo codes would move it a Sprint later.

Forecast from what the team has actually finished, as a range. If scope grows, the forecast moves: show both.

Day in the Role · Release plan and forecastIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleRelease plan and forecastWhat's in the release, and when it's likely
Version
Date

Release scope

ItemMustShouldCouldWon't this time

Progress so far (items done)

SprintDone to dateTotal scope

Forecast: a likely range, from actual progress

Forecast from what the team has actually finished, as a range. If scope grows, the forecast moves: show both.

Day in the Role · Release plan and forecastTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.