Monitoring and controlling · document briefChange log
The list of every change request: what it was, its impact, the decision, and a running total of contingency used.
2 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
you need the history of every change and the reserve it used.
Why it matters
It shows the whole history of changes in one place, so anyone can see what changed, why, who decided, and what it cost.
Written by
The project manager (often kept by the coordinator)
Approved by
Reviewed by the board
When it appears
Opened when the baselines are approved, kept up to date until closing.
What goes inside
Changes One row per request.
Contingency Starting amount, used, remaining.
Watch out for
- Rejected changes not recorded.
- Approved changes with no cost or time recorded.
- Nobody adding up the total effect.
How this document fits
This documentChange logMade with
The document
Day in the RoleChange logEvery change, and the contingency it used
| No. | Date | Change | Raised by | Cost € | Days | Decision | Decided by | Contingency left € |
|---|
| Opening contingency | 150,000 |
| CR-05 | Week 17 | Extra drying work, north wall damp | Arash (Contractor) | 20,000 | 0 | Approved | Annelise (Project Manager) | 130,000 |
| CR-07 | Week 22 | Move two walls in the treatment area | Amani (Clinical Lead) | 18,000 | 0 | Approved | Change board | 112,000 |
| CR-08 | Week 24 | Oak panelling in reception (unrequested) | Arash (Contractor) | 0 | 0 | Rejected: replaced with specified surface | Annelise (Project Manager) | 112,000 |
| CR-09 | Week 24 | One extra receptionist for Saturdays | Azadeh (Community Council) | 2,000 | 0 | Approved | Atticus (Sponsor) | 110,000 |
Only approved changes reduce the balance. Record rejected and deferred changes too.
Starting contingency€150,000
Used so far€40,000
Remaining€110,000
Day in the RoleChange logEvery change, and the contingency it used
| No. | Date | Change | Raised by | Cost € | Days | Decision | Decided by | Contingency left € |
|---|
| Opening contingency | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
Only approved changes reduce the balance. Record rejected and deferred changes too.
Starting contingency
Used so far
Remaining
Illustrative example in our own words: not a real project or organisation.