Executing · document briefLessons log
A running record of what the project has learned, good and bad, with what to do differently and whether it has been applied.
2 sections
Used by Process Improvement Specialist, Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing
Use it when
lessons should be captured while they're fresh and used straight away.
Why it matters
It makes sure lessons are captured while they're fresh, used in this project, and passed on to the next.
Written by
The project manager; anyone can add a lesson
Approved by
Reviewed by the board at stage ends
When it appears
From the start of the project to the end. Reviewed at stage ends and summarised at closing.
What goes inside
Lessons What happened, why, and what we'll do.
Top lessons to pass on For future projects.
Watch out for
- Only collected at the end.
- Blaming people instead of improving processes.
- Lessons recorded but never applied.
How this document fits
This documentLessons logMade with FeedsProcess improvements nowLessons report at closing
The document
Day in the RoleLessons logWhat we learned, and what we changed
Write lessons when they happen, good and bad. Ask “why” about the process, not “who”. Apply them while the project is still running.
| When | Type | What happened | Why | What we will do | Applied? |
|---|
| Week 9 | KeepImprove | Fit-out started in a certified area during asbestos removal | Checked with compliance first | Always check partial starts with the safety lead | ✓ |
| Week 14 | KeepImprove | Lead nurse lost to a slow offer | Contract took 3 weeks | Offers within 48 hours | ✓ |
| Week 18 | KeepImprove | Wrong ducts in three rooms | Revised drawing never reached the subcontractor | Drawing revision log confirmed by each trade | ✓ |
| Week 19 | KeepImprove | Delivery window agreed with shop owners | Listened before explaining | Meet affected neighbours before works start | ✓ |
| Week 21 | KeepImprove | Integration knowledge held by one person | No pairing on critical systems | Pair on every critical system | In progress |
Top lessons to pass on to the next project
- Agree offer deadlines with HR before hiring starts
- Log and confirm every drawing revision
- No single person holds critical knowledge alone
Day in the RoleLessons logWhat we learned, and what we changed
Write lessons when they happen, good and bad. Ask “why” about the process, not “who”. Apply them while the project is still running.
| When | Type | What happened | Why | What we will do | Applied? |
|---|
| KeepImprove | | | | |
| KeepImprove | | | | |
| KeepImprove | | | | |
| KeepImprove | | | | |
| KeepImprove | | | | |
| KeepImprove | | | | |
| KeepImprove | | | | |
| KeepImprove | | | | |
| KeepImprove | | | | |
Top lessons to pass on to the next project
Illustrative example in our own words: not a real project or organisation.