Executing · document brief

Lessons log

A running record of what the project has learned, good and bad, with what to do differently and whether it has been applied.

2 sections
Used by Process Improvement Specialist, Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

lessons should be captured while they're fresh and used straight away.

Why it matters

It makes sure lessons are captured while they're fresh, used in this project, and passed on to the next.

Written by

The project manager; anyone can add a lesson

Approved by

Reviewed by the board at stage ends

When it appears

From the start of the project to the end. Reviewed at stage ends and summarised at closing.

What goes inside

  1. Lessons What happened, why, and what we'll do.
  2. Top lessons to pass on For future projects.

Watch out for

  • Only collected at the end.
  • Blaming people instead of improving processes.
  • Lessons recorded but never applied.

How this document fits

This documentLessons logMade with
FeedsProcess improvements nowLessons report at closing
Where you will meet this: Lessons learned register (PMI) · lessons log and lessons report (PRINCE2)Print the example ↗Print the blank ↗

The document

Day in the RoleLessons logWhat we learned, and what we changed
Version1.0
Date15 March

Write lessons when they happen, good and bad. Ask “why” about the process, not “who”. Apply them while the project is still running.

WhenTypeWhat happenedWhyWhat we will doApplied?
Week 9KeepImproveFit-out started in a certified area during asbestos removalChecked with compliance firstAlways check partial starts with the safety lead✓
Week 14KeepImproveLead nurse lost to a slow offerContract took 3 weeksOffers within 48 hours✓
Week 18KeepImproveWrong ducts in three roomsRevised drawing never reached the subcontractorDrawing revision log confirmed by each trade✓
Week 19KeepImproveDelivery window agreed with shop ownersListened before explainingMeet affected neighbours before works start✓
Week 21KeepImproveIntegration knowledge held by one personNo pairing on critical systemsPair on every critical systemIn progress

Top lessons to pass on to the next project

  • Agree offer deadlines with HR before hiring starts
  • Log and confirm every drawing revision
  • No single person holds critical knowledge alone
Day in the Role · Lessons logIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleLessons logWhat we learned, and what we changed
Version
Date

Write lessons when they happen, good and bad. Ask “why” about the process, not “who”. Apply them while the project is still running.

WhenTypeWhat happenedWhyWhat we will doApplied?
KeepImprove
KeepImprove
KeepImprove
KeepImprove
KeepImprove
KeepImprove
KeepImprove
KeepImprove
KeepImprove

Top lessons to pass on to the next project

Day in the Role · Lessons logTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.