Executing · document brief

Work package

The agreement that hands a piece of work to a team or supplier: what to deliver, how it will be accepted, by when, within what limits, and how to report.

7 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

a piece of work is handed to a team or supplier.

Why it matters

It makes ownership clear and gives the project manager and the team the same picture of what done looks like.

Written by

The project manager, agreed with the team lead or supplier

Approved by

Accepted by the team lead or supplier who takes it on

When it appears

During executing, each time a piece of work starts. Closed when the work is accepted.

What goes inside

  1. Work package Code, name and the person who owns it.
  2. What to deliver The deliverables and what's included.
  3. Acceptance How the result will be checked.
  4. Dates and effort Start, finish and estimate.
  5. Tolerances How far time and cost may move before escalating.
  6. Reporting How and how often progress is reported.
  7. Agreed Both sides.

Watch out for

  • No acceptance criteria.
  • Tolerances missing, so every small slip is escalated or none are.
  • Handing work over verbally.

How this document fits

Where you will meet this: Work package (PMI and PRINCE2) · work authorisation · work orderPrint the example ↗Print the blank ↗

The document

Day in the RoleWork packageWork order: one piece of work, handed over
Version1.0
Date15 March
Work package4.1
NameHiring
Handed toAdaugo (HR and Training Lead)
Handed over byAnnelise (Project Manager)

What to deliver

  • 3 doctors
  • 6 nurses
  • 2 healthcare assistants
  • 1 reception lead

Accepted when

Contracts signed, checks complete, start dates agreed before week 23.

StartWeek 11
FinishWeek 22
EffortAbout 40 days of HR time

Tolerances

Time±2 weeks
Cost±€5,000

Inside these limits the owner decides; beyond them, escalate before acting.

Constraints

Offers sent within 48 hours of the final interview.

Reporting

Short update every Monday; escalate at once if two weeks behind or a key role can't be filled.

Owner accepts the work
Signature
Date
Project manager
Signature
Date
✂Closing stub
Accepted on
Checked by
Closed
Day in the Role · Work packageIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleWork packageWork order: one piece of work, handed over
Version
Date
Work package
Name
Handed to
Handed over by

What to deliver

Accepted when

Start
Finish
Effort

Tolerances

Time±
Cost±

Inside these limits the owner decides; beyond them, escalate before acting.

Constraints

Reporting

Owner accepts the work
Signature
Date
Project manager
Signature
Date
✂Closing stub
Accepted on
Checked by
Closed
Day in the Role · Work packageTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.

See it in the story

In the Project Manager story

Related documents

← All documents and templates