Executing · document brief

Incident report

The record of a safety incident: what happened, immediate actions, who was affected, reporting to authorities, causes and corrective actions.

5 sections
Used by Project Manager
Pre-projectInitiatingPlanningExecutingMonitoringClosing

Use it when

a safety incident happens on the project.

Why it matters

It makes sure people are cared for, legal reporting happens, causes are found and the same thing doesn't happen again.

Written by

The contractor or employer, with the project manager

Approved by

Health and safety lead; shared with the sponsor

When it appears

As soon as possible after an incident, then completed after investigation.

What goes inside

  1. What happened When, where, who, what.
  2. Immediate actions Care, area made safe, reported.
  3. Causes From a blameless investigation.
  4. Corrective actions What changes, who, by when.
  5. Sign-off Safety lead and project manager.

Watch out for

  • Blaming before investigating.
  • Downplaying the facts.

How this document fits

NeedsWitness accountsSite records
This documentIncident reportMade with
FeedsLessons logAuthorities' reportProcess changes
Where you will meet this: Accident report · health and safety incident reportPrint the example ↗Print the blank ↗

The document

Day in the RoleIncident reportSafety incident: record, causes, actions
IncidentPeople first. Make the area safe. Preserve evidence. Report as the law requires.
WhenWeek 18, 10:05
WhereEast scaffold, level 2
WhoA contractor's worker
SeverityInjury, hospital treatment

What happened

A worker fell about two metres from the east scaffold while moving materials. Injured arm; conscious throughout.

Immediate actions

First aid given and ambulance called
Scaffold closed and scene kept unchanged
Reported to the authorities by the contractor
Sponsor informed

Causes (blameless investigation)

A guard rail was removed for a delivery and not replaced. No step in the process checked guard rails before the scaffold was used again.

Corrective actions

ActionOwnerBy when
Sign-off of every scaffold before reuseArash (Contractor)Immediately
Toolbox talk for all crewsArash (Contractor)This week
Add to the lessons logAnnelise (Project Manager)Today
Safety lead
Signature
Date
Project manager
Signature
Date
Day in the Role · Incident reportIllustrative example · not a real project or organisation · dayintherole.com
Day in the RoleIncident reportSafety incident: record, causes, actions
IncidentPeople first. Make the area safe. Preserve evidence. Report as the law requires.
When
Where
Who
Severity

What happened

Immediate actions

Care given; emergency services called if needed
Area made safe and scene kept
Reported to the authorities as required
Sponsor and safety lead informed

Causes (blameless investigation)

Corrective actions

ActionOwnerBy when
Safety lead
Signature
Date
Project manager
Signature
Date
Day in the Role · Incident reportTemplate · free to use and adapt · dayintherole.com

Illustrative example in our own words: not a real project or organisation.