City marathon 52 questions 5 phases
Lakeside: a Project Manager case study The city of Lakeside wants its first marathon: 8,000 runners, 42 km of closed roads, one Sunday in October. The date is set, the sponsors are signed, and nothing about it can be late. You've been asked to run the project.
What this case study tests
Fixed dates Volunteers and matrix roles Go or no-go Running the live event
You're the Project Manager. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Stakeholders
Ariana (Project Manager) You Alaric (Director of Events) Sponsor Adebayo (Race Director) Senior user: the race itself Annika (Police Liaison Officer) Road closures and security Ahmed (Medical Lead) First aid and ambulances Alva (Sponsorship Manager) Sponsors and their promises Abraham (Volunteer Coordinator) 1,200 volunteers Astrid (Local Business Association) Shops on the route Lakeside
Starting up A date that can't move
Question 1 of 52 Choose 1
Alaric (Director of Events) The mayor wants a marathon in October. Make it happen.
What is your first step? Clarify what success means, and what can't move Correct. Right. The date is fixed; scope and cost are where you'll have room.Book the road closures straight away, to be safe Incorrect. Commit to details before the need, scope and constraints are clear and you'll redo them.Copy another city's marathon plan exactly Incorrect. Learn from it, but this city's roads, people and rules are different.
Learn it on Day 1: A request lands on your desk
Check answer
Question 2 of 52 True or false
Alaric (Director of Events) The date is fixed. What does that mean for the project?
True or false: with a fixed date, scope and cost are where trade-offs happen. True Correct. Correct. If time can't move, scope or cost must be the flexible side.False Incorrect. Something has to give when problems appear; with a fixed date it can't be time.
Learn it on Day 5: Who's in charge here?
Check answer
Question 3 of 52 Choose 1
Alva (Sponsorship Manager) Sponsors want their logos on every kilometre marker and a VIP tent at the finish.
How do you treat sponsors? Leave them alone until race day itself, then meet them Incorrect. Late surprises from sponsors are expensive.Involve them regularly, with clear agreements Correct. Right. Their contracts define scope you must deliver.Give them whatever they ask for, as they pay Incorrect. Some requests may conflict with safety or the route.
Learn it on Day 6: Everyone who matters Technique: Stakeholder map (power and interest)
Check answer
Question 4 of 52 Choose 1
Astrid (Local Business Association) Shops on the route say a Sunday road closure will ruin their trade.
What do you do? Tell them the route decision has already been made, firmly Incorrect. That creates opposition.Cancel that part of the route to stop complaints Incorrect. Out of proportion; look for solutions first.Listen, and explore options like stalls and access maps Correct. Right. Turn a threat into a supporter.
Learn it on Day 6: Everyone who matters Technique: Active listening
Check answer
Question 5 of 52 Choose 1
Adebayo (Race Director) The police, medical team and volunteers all think they decide the start time.
Which tool clarifies this? A RACI chart: one accountable person per decision Correct. Right. Start time: Adebayo (Race Director) accountable, police and medical consulted.A group vote among all the teams on every key decision Incorrect. Votes don't create accountability.Let the loudest person in the room decide each time Incorrect. That's not governance.
Learn it on Day 7: Who does what Technique: RACI
Check answer
Question 6 of 52 Choose 1
Abraham (Volunteer Coordinator) Volunteers report to their own clubs, not to us.
What does this mean for you? You can give them orders, just like paid staff Incorrect. They don't report to you.Agree roles with the clubs, and lead by influence Correct. Right. Like a matrix organisation, people have other managers.Volunteers don't need managing at all on the day Incorrect. 1,200 people need clear roles and briefings.
Learn it on Day 7: Who does what
Check answer
Question 7 of 52 Choose 1
Annika (Police Liaison Officer) At the kick-off: the police can only close roads from 06:00, not 05:00 as assumed.
What happens to the assumption? Ignore it: maybe the police will change their mind before then Incorrect. Plans built on a false assumption fail on race day.Start the race before the roads are fully closed, at 05:00 Incorrect. Unsafe and illegal.It failed, so it's an issue: assess it and tell the sponsor Correct. Right. Record it in the RAID log with an owner.
Learn it on Day 9: The kick-off Technique: Risk identification
Check answer
Question 8 of 52 Choose 1
Alaric (Director of Events) Do we really need a kick-off meeting? Everyone's busy.
What does a kick-off achieve? Everyone aligned on goal, scope, roles and first steps Correct. Right. With police, medics, sponsors and volunteers, alignment early is vital.Nothing that a good email couldn't do just as well, quicker Incorrect. Emails don't build shared understanding or resolve questions.It replaces the need for a written plan for the race Incorrect. It starts the work; it doesn't replace planning.
Learn it on Day 9: The kick-off Technique: Kick-off meeting
Check answer
Question 9 of 52 Choose 1
Alaric (Director of Events) The marathon costs €900,000 a year to run, and councillors ask whether the visitors it brings over the next five editions make it worth it.
How do you show the value? Show the net present value over five editions Correct. Right. Estimate each year's costs and visitor income, discount them to today's money, and show the net present value and when it pays back.Show only this year's costs and this year's income Incorrect. That ignores future editions and their income.Say it's good publicity for the city, which it is Incorrect. Councillors need numbers to compare it with other uses of the money.
Learn it on Day 3: Is it worth it?
Check answer
Question 10 of 52 Choose 1
Alaric (Director of Events) The city runs a programme of events this year. The marathon needs the same police officers and volunteers as the summer festival.
How do you handle it? Book everything you need before the festival does, to be safe Incorrect. That starves the other project and damages trust.Coordinate through the events programme, as a dependency Correct. Right. Agree shared people and dates with the festival project, record the dependency, and report to the programme office: shared resources need agreements across projects.Leave it to the police to decide between the two events Incorrect. Coordinating resources is the projects' job.
Learn it on Day 7: Who does what
Check answer
Question 11 of 52 Choose 1
Alaric (Director of Events) The council approved the marathon last night. Can we start booking barriers and buses today?
What do you need first? Start booking now: time is very short Incorrect. Bookings made without authority may have to be undone.A complete detailed plan before anything Incorrect. Detailed planning comes after the project is authorised.A short charter signed by the sponsor Correct. Right. A project charter with objectives, scope, budget, key dates and your authority to commit money; without it you could spend money you aren't authorised to.
Learn it on Day 5: Who's in charge here?
Check answer
Lakeside
Planning 42 km of plans
Question 12 of 52 Choose 1
Adebayo (Race Director) We also want a half marathon, a kids' race and a night run.
How do you handle it? Add everything: it's all popular with runners and sponsors Incorrect. Scope creep on a fixed date breaks the event.Prioritise against the objective and the constraints Correct. Right. A clear scope protects the fixed date.Refuse all extras, now and in future years, to be safe Incorrect. Record them for future years.
Learn it on Day 10: What exactly are we building? Technique: MoSCoW
Check answer
Question 13 of 52 Choose 1
Abraham (Volunteer Coordinator) How do we make sure nothing is forgotten, from water stations to toilets?
Question 14 of 52 Choose 1
Ahmed (Medical Lead) We need 12 ambulances, but the regional service only confirms 8 weeks before.
Where does this go in the plan? A dependency on the critical path, with a back-up Correct. Right. Without medical cover, no race.Nowhere: it'll be fine, the ambulance service is reliable Incorrect. A dependency outside your control must be visible.At the end of the plan, as a final check before race day Incorrect. It affects many other activities.
Learn it on Day 12: How long will it really take? Technique: Critical path
Check answer
Question 15 of 52 Choose 2
Alaric (Director of Events) Is the budget €900,000, or €900,000 plus something?
Which two statements are true? The sponsor holds a reserve for the unknown Correct. Correct.Contingency can be spent on extra features Incorrect. It's for risks, not scope.Known-risk contingency is inside the baseline Correct. Correct.Reserves aren't needed for one-day events Incorrect. Events are full of risks: weather, security, suppliers.
Learn it on Day 14: What will it cost?
Check answer
Question 16 of 52 Choose 1
Alaric (Director of Events) Our first cost estimate came from another city's marathon, adjusted for size.
What kind of estimate is that? Bottom-up, built up from each item of the race Incorrect. Bottom-up adds up each piece of this project's work.Exact, based on the other city's cost Incorrect. No early estimate is exact; give a range.Analogous: quick and rough, for early use Correct. Right. Replace it with a bottom-up estimate once the work is broken down.
Learn it on Day 14: What will it cost? Technique: Analogous estimating
Check answer
Question 17 of 52 Choose 1
Ahmed (Medical Lead) A heatwave on race day could cause collapses.
Which response reduces the impact? More water, medics, and a trigger to shorten it Correct. Right. The trigger makes the decision objective on the day.Accept it and hope for a cool day in October Incorrect. Too dangerous to just accept.Move the race to the cooler winter months instead Incorrect. The date is fixed.
Learn it on Day 16: What could go wrong? Technique: Risk responses
Check answer
Question 18 of 52 Choose 1
Alva (Sponsorship Manager) A sports drink brand might pay to sponsor the water stations.
What kind of risk is this? Not a risk at all, just some good news Incorrect. Uncertain events that help are positive risks.An opportunity, so contact them early Correct. Right.A threat to the race's existing sponsors Incorrect. It would help the objectives.
Learn it on Day 16: What could go wrong?
Check answer
Question 19 of 52 Choose 1
Abraham (Volunteer Coordinator) Should we buy timing chips or hire a timing company?
How do you decide? Buy the chips: owning is always cheaper over time Incorrect. Not when you lack the skills and the system.Go with whichever option the race director prefers Incorrect. Decide on evidence.Compare whole-life cost, risk, skills and support Correct. Right.
Learn it on Day 18: Buying what we need Technique: Make or buy
Check answer
Question 20 of 52 Choose 1
Adebayo (Race Director) Quality means a perfect race experience with live TV, music on every corner and fireworks.
What is quality here? Meeting the requirements: safe, accurate, on time Correct. Right. Fireworks are grade, not quality.The most spectacular event possible for runners Incorrect. That's gold-plating against a fixed budget.Whatever the sponsors want in return for their money Incorrect. Sponsors are one stakeholder group.
Learn it on Day 19: Good enough, and who hears what
Check answer
Question 21 of 52 Choose 1
Alaric (Director of Events) Can we just add 1,000 more runners? Demand is huge.
What do you do? Yes: more runners means more income for the city Incorrect. Without checking capacity, it's unsafe.Assess the impact on safety and cost, then decide Correct. Right. More runners means more of everything.No: the number is fixed, so it can't change now Incorrect. It may be possible; assess first.
Learn it on Day 20: Signing off the plan Technique: Impact analysis
Check answer
Question 22 of 52 Choose 1
Alaric (Director of Events) Our standard event method has 30 documents. Do we need all of them?
What do you do? Produce all 30 documents, just to be on the safe side Incorrect. Documents nobody uses cost time.Ignore the method: it's for bigger projects Incorrect. Tailor openly instead.Tailor it with the events office, and record why Correct. Right. Safety documents stay; some marketing reports are combined.
Learn it on Day 8: How should we run it? Technique: Tailoring the approach
Check answer
Question 23 of 52 Choose 1
Abraham (Volunteer Coordinator) The same 50 volunteer leaders are booked for the expo, the start and the finish, all at once.
What does the plan need? An hour-by-hour resource plan, levelled for race day Correct. Right. Two extra leaders from partner clubs fill the gaps.Trust that it will all work out on the day itself Incorrect. On race day, it won't.Ask volunteers to run between the areas as needed Incorrect. Unsafe and unrealistic.
Learn it on Day 15: Who's needed when? Technique: Resource levelling
Check answer
Question 24 of 52 Choose 1
Alaric (Director of Events) How sure are we that all road closures will be approved in time?
How do you give an honest answer? Say yes: the approved plan says week 30, so it's fine Incorrect. A single promise hides the uncertainty.Run the schedule many times; show confidence Correct. Right. Confidence levels are more honest than one date.Say it can't be known until it actually happens Incorrect. It can be estimated.
Learn it on Day 17: Putting numbers on risk Technique: Schedule simulation
Check answer
Question 25 of 52 Choose 1
Adebayo (Race Director) The route and the road closures are fixed, but the runner app keeps changing as we hear from runners.
How do you run the work? A hybrid: plan the route, iterate on the app Correct. Right. Plan the route and logistics predictively, and develop the app iteratively with runner feedback; fixed logistics need firm plans, while the app improves by learning.Freeze the app specification now, to be safe Incorrect. Runners' real needs would be ignored.Run the road closures in short Sprints too Incorrect. Road closures need firm, early plans and legal orders.
Learn it on Day 8: How should we run it?
Check answer
Question 26 of 52 Choose 1
Annika (Police Liaison Officer) Closing 42 km of roads needs legal traffic orders and an event licence. Each has its own deadline.
How do you make sure nothing is missed? Assume the police handle all the legal side Incorrect. The organiser is responsible for applying.List every licence and order, with owners Correct. Right. Every licence, legal order and regulation gets an owner and a deadline on the plan's critical path; a missing licence can cancel the race.Apply once everything else is ready to go Incorrect. Approvals take weeks; late applications miss race day.
Learn it on Day 13: Rules we must follow
Check answer
Lakeside
Delivering The weeks before race day
Question 27 of 52 Choose 1
Abraham (Volunteer Coordinator) How do I brief 1,200 volunteers so each knows their job?
What do volunteers need? A general welcome email to everyone before race day Incorrect. Too vague for race day.Nothing: they'll figure it out on the day, as usual Incorrect. Confusion on race day is a safety risk.Clear role cards: where, when, what, and who to call Correct. Right. Like a work package for each role.
Learn it on Day 21: Breaking ground Technique: Work authorisation
Check answer
Question 28 of 52 Choose 1
Abraham (Volunteer Coordinator) Volunteer sign-ups for the 30 km area are low.
What do you do? Treat it as real: call clubs, shift people Correct. Right. Act now and fix the cause.Hope more volunteers sign up in time for it Incorrect. Hope isn't a plan.Leave the 30 km area without any volunteers Incorrect. Unsafe for runners.
Learn it on Day 23: Building the team Technique: Risk responses
Check answer
Question 29 of 52 Choose 1
Alva (Sponsorship Manager) The banner supplier delivered the wrong sponsor logos.
Question 30 of 52 Choose 1
Ahmed (Medical Lead) A walk-through found the medical tent too far from the finish line.
What do you do? Leave it: runners can walk a little further to reach it Incorrect. Collapsed runners can't.Add a second tent quickly, without changing the plan Incorrect. Fix the plan, not just the symptom.Move it, update the plan, and re-check ambulance routes Correct. Right. Inspections exist to catch this before race day.
Learn it on Day 26: Quality on site Technique: Inspection and testing
Check answer
Question 31 of 52 Choose 1
Astrid (Local Business Association) Residents worry they can't get out of their streets on race day.
Question 32 of 52 Choose 1
Abraham (Volunteer Coordinator) Our IT volunteer who built the runner database is moving abroad next week.
Question 33 of 52 True or false
Adebayo (Race Director) Sponsors asked me directly to add a stage at kilometre 21. I said yes.
True or false: the race director can agree changes directly with sponsors. True Incorrect. Changes go through one route so their cost and safety are checked.False Correct. Correct. Route it through change control.
Learn it on Day 30: A key person leaves
Check answer
Question 34 of 52 Choose 1
Abraham (Volunteer Coordinator) One of our volunteer leaders keeps missing briefings and her team is confused.
Question 35 of 52 Choose 1
Abraham (Volunteer Coordinator) Volunteers come from five running clubs with very different habits. Some ignore the briefings completely.
How do you get them working as one? Email everyone the race-day instructions Incorrect. Emails are easily ignored.Replace the volunteers with paid staff instead Incorrect. Costly, and the clubs' goodwill is lost.Involve club leaders, with hands-on training Correct. Right. Respect each club's culture, involve its leaders in shaping the briefings, and give short training so volunteers adopt the race-day routines.
Learn it on Day 31: Getting people ready
Check answer
Lakeside
Keeping control Six weeks to go
Question 36 of 52 Choose 1
Alaric (Director of Events) Give me a one-line status.
What makes a good status report? Colour and reason, progress, risks, decisions Correct. Right. Short, honest, actionable.“All good: everything is on track this week” Incorrect. Not useful, and maybe not true.Every spreadsheet attached in full detail Incorrect. Detail belongs in the logs.
Learn it on Day 32: Are we on track? Technique: RAG status
Check answer
Question 37 of 52 Choose 1
Alaric (Director of Events) Six weeks out: planned value €600,000, earned value €540,000.
What is the schedule performance index, and what does it mean? 1.1: ahead of the planned schedule Incorrect. EV ÷ PV = 540 ÷ 600 = 0.9.0.9: the work done is behind plan Correct. Right. With a fixed date, find where to catch up now.It can't be known without the actual cost Incorrect. Schedule performance only needs EV and PV.
Learn it on Day 32: Are we on track? Technique: Earned value
Check answer
Question 38 of 52 Choose 1
Alva (Sponsorship Manager) A sponsor wants a 5 km fun run on the same day.
Who decides? The sponsorship manager, who signed the deal Incorrect. Not the decision-maker for scope changes.Whoever pays the most money for the race Incorrect. Money isn't the decision rule.The change board, after an impact check Correct. Right.
Learn it on Day 33: The change request Technique: Change board
Check answer
Question 39 of 52 Choose 1
Annika (Police Liaison Officer) The police need the route changed: a bridge on km 14 is closed for repairs.
Your tolerance is ± 500 m on distance. The new route adds 1.2 km before adjustment. Escalate with options, and recommend one Correct. Right. Beyond tolerance: the sponsor and race director decide.Accept a longer race this year, just this once Incorrect. A marathon has to be the right distance.Ignore the police, and keep the route as it is Incorrect. Not an option.
Learn it on Day 34: Out of tolerance Technique: Management by exception
Check answer
Question 40 of 52 Choose 1
Alaric (Director of Events) The forecast says we'll be €40,000 over budget.
What do you do? Hide it until after race day is over, then report Incorrect. Leaders lose the chance to decide.Explain the cause, the options, and recommend Correct. Right.Cut the safety spending quietly to cover it Incorrect. Never the first option.
Learn it on Day 34: Out of tolerance
Check answer
Question 41 of 52 Choose 1
Adebayo (Race Director) The course measurer says the route is certified. Can we sign it off?
Question 42 of 52 Choose 1
Ahmed (Medical Lead) A new risk: a flu wave could cut ambulance availability.
Question 43 of 52 Choose 1
Alaric (Director of Events) The city cuts the event budget by €60,000.
How do you respond? Cut medical cover a little on quiet stretches Incorrect. Safety comes last to be cut, not first.Descope by priority, keep safety, and re-baseline Correct. Right.Overspend anyway, and explain it to the city afterwards Incorrect. Not an option.
Learn it on Day 35: The budget is cut Technique: MoSCoW
Check answer
Lakeside
Closing Race day and after
Question 44 of 52 Choose 1
Adebayo (Race Director) It's Saturday. Are we ready?
How do you decide go or no-go? We're ready because the date has arrived Incorrect. The date isn't readiness.Ask all the volunteers to vote on it Incorrect. The accountable people decide on criteria.Go only if every critical item is ready Correct. Right. And a clear decision-maker for the morning.
Learn it on Day 41: Are we ready to open? Technique: Go or no-go review
Check answer
Question 45 of 52 True or false
Abraham (Volunteer Coordinator) Should we do a full rehearsal of the finish area?
Question 46 of 52 Choose 1
Annika (Police Liaison Officer) Who handles problems on race day: the project team or the event control room?
What's the right setup? Event control runs it, with project people Correct. Right. Operations lead; the project supports closely.The project team runs everything on the day Incorrect. Operations should own the live event.Nobody: on race day the event runs itself Incorrect. Never on race day.
Learn it on Day 42: Opening day Technique: Hypercare
Check answer
Question 47 of 52 Choose 1
Alva (Sponsorship Manager) The timing company sent an invoice for extra chips we didn't order.
What do you do? Pay everything, to keep good relations with them Incorrect. Check first.Check the contract and change log, then discuss Correct. Right.Refuse to pay anything until it's settled Incorrect. Pay undisputed amounts on time.
Learn it on Day 43: Closing the contracts
Check answer
Question 48 of 52 Choose 1
Abraham (Volunteer Coordinator) Volunteers are already asking about next year.
What do you do before the team disbands? Send a generic thank-you email to all Incorrect. Specific thanks matter.Nothing: the race is over, so it's done Incorrect. You'll need them again.Thank everyone and run a lessons review Correct. Right. Recognition and lessons keep next year strong.
Learn it on Day 44: Letting the team go Technique: Recognition
Check answer
Question 49 of 52 Choose 2
Alaric (Director of Events) Next year someone else may run it. What should they get from us?
Which two documents help them most? The sponsors' brochures from this year Incorrect. Not useful for planning.A closure report with the results Correct. Correct.A list of who made which mistakes Incorrect. Blame helps nobody.A lessons report with recommendations Correct. Correct.
Learn it on Day 44: Letting the team go
Check answer
Question 50 of 52 Choose 1
Astrid (Local Business Association) Shops on the route had their best Sunday of the year.
How do you use this? Ignore it: the race is over now, so it's done Incorrect. Benefits justify the investment.Record it as a benefit, with evidence Correct. Right. It supports the case for next year.Claim credit for all city income that weekend Incorrect. Only count what the event caused.
Learn it on Day 46: Was it worth it? Technique: Benefits tracking
Check answer
Question 51 of 52 Choose 1
Alaric (Director of Events) The mayor wants a night run next year.
What happens? Just add it to next year's plan as an extra Incorrect. New scope needs its own decision.Refuse it: one race a year is quite enough Incorrect. Assess it properly.A new request, with a business case of its own Correct. Right.
Learn it on Day 46: Was it worth it?
Check answer
Question 52 of 52 Choose 1
Alaric (Director of Events) The half-marathon planned for spring has been cancelled by the city.
What do you do with it? Close it properly, reuse what you can, and report Correct. Right. Stopping is a decision, not a failure.Just stop answering emails about it from now on Incorrect. Contracts and money would be left in limbo.Keep it running quietly in the background Incorrect. Its reason has gone.
Learn it on Day 45: Closing a stopped project Technique: Stage gate
Check answer