Closing and transition · cheat sheet

Go or no-go review

A meeting that decides whether to go live, based on an agreed readiness checklist rather than the announced date.

Common practice
5 steps
Used by Project Manager

What it is

A meeting that decides whether to go live, based on an agreed readiness checklist, not on the announced date.

When to use it

Shortly before going live, after the rehearsal and the final checks.

Why it works

It makes go-live a conscious decision with fallbacks, rather than momentum.

Do

  • Decide who has the final say before the meeting.

Don't

  • Going live because the date was announced.
  • Hidden “amber” items with no fallback.

Step by step

  1. Agree criteria in advance And which are critical.
  2. Review each item with its owner Green, amber, red.
  3. Agree fallbacks For anything not fully ready.
  4. Decide Go, go with fallbacks, or no-go.
  5. Confirm the first days' support Who does what after go-live.
Also called: Go-live decision, readiness reviewPrint the blank template ↗

Worked example

The situation. Opening a new clinic.

  1. All critical items green; online booking amber with phone booking as fallback.
  2. Decision: go with fallback.

The result. Opened on time, with no surprises.

Go or no-go checklist Print blank
AreaCriticalStatusFallback
BuildingYesGreen
LicenceYesGreen
Online bookingNoAmberPhone booking

Filled in for: Opening a new clinic.

AreaCritical?StatusFallbackOwner

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Project Manager uses it

All critical items for the clinic are green; online booking is amber with phone booking as the planned fallback. Atticus (Sponsor) and Amani (Clinical Lead) decide: go.

Questions people ask

What if one critical item is amber?

Then it's no-go, or the item needs a fallback everyone accepts.